2549
Comment:
|
2983
|
Deletions are marked like this. | Additions are marked like this. |
Line 21: | Line 21: |
== 2017-08-28 == | == 2017-11-06 == * Confirm location of sapphire prisms. * Bring SR2 into tunnel. * Find mirror gluing items. * Mirror * Mirror box * Prisms * Secondary prisms * Magnets * Magnet bases * Prism micrometer stages * Prism jigs * Magnet jigs * Balance * Stirrers * Mixing dishes * Lenses for inspecting scribe lines * Procedure document. * EP30 * Glass beads * Rehearse mirror gluing. |
Line 27: | Line 48: |
* Design SR assembly frame. | |
Line 29: | Line 49: |
* Confrim location of sapphire prisms. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-11-06
- Confirm location of sapphire prisms.
- Bring SR2 into tunnel.
- Find mirror gluing items.
- Mirror
- Mirror box
- Prisms
- Secondary prisms
- Magnets
- Magnet bases
- Prism micrometer stages
- Prism jigs
- Magnet jigs
- Balance
- Stirrers
- Mixing dishes
- Lenses for inspecting scribe lines
- Procedure document.
- EP30
- Glass beads
- Rehearse mirror gluing.
SR Prep Tasks
Design/Purchasing
- Do rough mass budget for SR2/SR3/SRM.
- Design final SF ballast masses (Fabian).
- Confrim location of sapphire prisms.
Order now
Bread boards for SR -> Orderd. delivery date:10/18-20
- Include installation work in the contract
- Total budget = 5MJPY
PEEK collet for "Small hexagon"(cable clamp) -> need modification.
Need simple design changes
- SUS wires(3 types) for the LBB
Change the length -> Orderd. delivery date:10/
- Receptacles for Bread board damper
- There is a mistake in the PROMEC drawing.
- Hirata-san will make a new 2D drawing
- IM wire clamps for SR
Need to change the height -> watiting second quote.
SR assembly frame -> Ordered. delivery date:9/27-29
- Mark is checking the design from Fabian
- We should order the parts necessary to modify the BS assembly frame to the SR2 assembly frame
Need Fabian's input
Cable clamps for BF,SF and PI -> 方式を決める
- Design change for the PI clamps, because the SR PIs are NIKHEF ones.
- Ballast masses for BF and SF
- 製作に2週間程度
- 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。
測定に必要な物品の準備 -> 月曜日に高橋さんと相談
Need more discussion/checks
- Blade spring assembly for LBB
- Check the load of the LBB and decide the design load of the springs
- Correct the length
Scale the width of the current blades to design the new blades -> 高橋さんと相談
- SR用LBBの重さを確認
- Bread board damper rings
Need to check whether we can put a full ring into the chamber from the side flanges or not. -> need modification
Electronics
- Get cables/cards for SR3:
- 5 DSub-37 cables (tent)
- 5 DSub-15M to DSub-9M adapter cables (tent)
- 3 DIO cards (tent)
- 2 DSub-9 FF gender benders (for LVDTs)
- extra ADC card(s)?
- extra DAC card(s)?
- BNC-LEMO adapter (for LVDTs)
- etc