2467
Comment:
|
3052
|
Deletions are marked like this. | Additions are marked like this. |
Line 13: | Line 13: |
=== Facilities === | ==== Facilities ==== |
Line 20: | Line 20: |
== Coming Weeks == | |
Line 21: | Line 22: |
== 2017-12-11 == * --(Double check prism heights.)-- * --(Do mirror gluing.)-- * --(Check mirror gluing.)-- * Assemble SR2 IP. * --(Hassle Miyo-kun for pico driver.)-- * --(Set up for testing IP with pico driver.)-- * --(Make pico cable.)-- * --(Glue Misumi plug in movable mass (also glue remaining disks in IM flags).)-- * Assemble IP. * Test IP picos. * --(Weigh BF.)-- * --(Find accessories.)-- * --(Do weighing.)-- * Find in-vac cables: * --(2 x Type 3-6m )-- * 1 x Type 3-2m * --(4)-- 3 x Type 4-1.5m * 5 x Type 1-2m * --(7 x Type 2-2m)-- * --(Set up SR2 rack)-- * --(Get ADC/DAC/DIO cards)-- * --(Get cables/cards for SR2)-- * --(Get BIO white cables x 10)-- * --(Hassle Miyakawa/Yamamoto to connect rack to DC power, Internet, etc.)-- * Get SR2 real-time model running (Yamamoto-san). * Do inventory of ballast masses. * Adjust verticality of assembly frame; center and immobilize optical table. * --(Find and attach feedthroughs.)-- * --(Find circuit boards for geophones)-- (Okutomi-san says we have 5 free plus 5 tied up in his experiment till Feb-Mar 2018.) * --(Check if they have sockets soldered on.)-- (Yes.) * --(Check if they come with hex posts.)-- (Yes.) * Find out (from Takahashi-san) specifications for geophone pod items: * Screws for pod (cap-neck and neck-body). * Cu O-rings for pod (two sizes) * Viton O-ring for under geophone. * Screws for immobilizing geophone (M4?). * Screws for geophone to interface plate. * Screws for interface plate to PI. * Find or order geophone items. |
=== 2018-05-28 === ==== Main Sequence ==== * Modify and clean Promec masses at Mitaka (making threaded holes unthreaded to allow stacking). * Test LVDT driver repaired by Tanaka-san. * Cable and test BF cap picos. * Install internal ballast masses. * Install cap ballast masses. * Build up security structure to SF level. * Crane in SF and remove cap. * Hook BF and adjust total ballast. * Route cables through SF-BF flying saucer up to bottom of SF. * Adjust BF trim mass. === 2018-06-04 === ==== Main Sequence ==== * Readjust payload. * Take TFs. * Add budgeted ballast mass to SF. * Cable, test SF LVDT and FR. * Finish four half-assembled geophones. ==== F0/LBB Stuff ==== * Characterize final F0 blades. === 2018-06-11 === ==== Main Sequence ==== * SF/... TFs. ==== F0/LBB Stuff ==== * Rebuild F0 #3 for SR3. * Park F0 #1 (for SR2) in top of SR3 assembly frame. * Move F0 #3 behind SR3. * Make LBB blade sets (or at least 3 of 9). === 2018-06-18 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-06-25 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-02 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-09 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-16 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-23 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== |
Line 65: | Line 82: |
* Hassle Miyo-kun for stepper drivers. * Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done. * Design final SF ballast masses (Fabian). * Get safety bars moved. * Get air hose connection moved. * Get geophone circuit boards from Okutomi-san. * |
=== Tunnel === * Calibrate last six IM OSEMs. * Install first set of LBB damper rings in SR3 tank. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * Finish half-completed geophones. * Characterize final top filter blades (from 5/31). * Rebuild filters in PIs #1 and #3. * Install clamps on PIs #1 and #3. * Install LBB units on PIs #1 and #3. * Install correct IP in PI #3. * Rebuild filter in PI #2. * Install clamps on PI #2. * Install LBB blade units on PI #2. === Mitaka or remotely === * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass. * Set up SR2 Guardian. * Install damping filters for SR2. * Review Shoda-san's Guardian. * Review DIO stuff. * Review DAC channel requests. * Set up SR2 and SR3 Guardian. * Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen. * Install damping filters for SR2. * Do buoyancy calculation (see LIGO-T1100616). === Ordering === See ../WishList . |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-05-28
Main Sequence
- Modify and clean Promec masses at Mitaka (making threaded holes unthreaded to allow stacking).
- Test LVDT driver repaired by Tanaka-san.
- Cable and test BF cap picos.
- Install internal ballast masses.
- Install cap ballast masses.
- Build up security structure to SF level.
- Crane in SF and remove cap.
- Hook BF and adjust total ballast.
- Route cables through SF-BF flying saucer up to bottom of SF.
- Adjust BF trim mass.
2018-06-04
Main Sequence
- Readjust payload.
- Take TFs.
- Add budgeted ballast mass to SF.
- Cable, test SF LVDT and FR.
- Finish four half-assembled geophones.
F0/LBB Stuff
- Characterize final F0 blades.
2018-06-11
Main Sequence
- SF/... TFs.
F0/LBB Stuff
- Rebuild F0 #3 for SR3.
- Park F0 #1 (for SR2) in top of SR3 assembly frame.
- Move F0 #3 behind SR3.
- Make LBB blade sets (or at least 3 of 9).
2018-06-18
Main Sequence
F0/LBB Stuff
2018-06-25
Main Sequence
F0/LBB Stuff
2018-07-02
Main Sequence
F0/LBB Stuff
2018-07-09
Main Sequence
F0/LBB Stuff
2018-07-16
Main Sequence
F0/LBB Stuff
2018-07-23
Main Sequence
F0/LBB Stuff
SR Prep Tasks - To Be Scheduled
Tunnel
- Calibrate last six IM OSEMs.
- Install first set of LBB damper rings in SR3 tank.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- Finish half-completed geophones.
- Characterize final top filter blades (from 5/31).
- Rebuild filters in PIs #1 and #3.
- Install clamps on PIs #1 and #3.
- Install LBB units on PIs #1 and #3.
- Install correct IP in PI #3.
- Rebuild filter in PI #2.
- Install clamps on PI #2.
- Install LBB blade units on PI #2.
Mitaka or remotely
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review Shoda-san's Guardian.
- Review DIO stuff.
- Review DAC channel requests.
- Set up SR2 and SR3 Guardian.
- Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
- Install damping filters for SR2.
- Do buoyancy calculation (see LIGO-T1100616).
Ordering
See ../WishList .