Line 13: | Line 13: |
=== Facilities === | ==== Facilities ==== |
Line 20: | Line 20: |
== Coming Weeks == | |
Line 21: | Line 22: |
== 2017-12-11 == * Assemble SR2 IP. * Final assembly. * Test IP picos. * Find in-vac cables: * 1 x Type 3-2m * 5 x Type 1-2m * Set up SR2 rack * Get more 1-m power cables and connect up remaining boxes. * Run LAN and power cables for stepper drivers. * Debug SR2 real-time model (Yamamoto-san). * Do inventory of ballast masses. * Adjust verticality of assembly frame; center and immobilize optical table. * Find out (from Takahashi-san) specifications for geophone pod items: * Screws for pod (cap-neck and neck-body). * Cu O-rings for pod (two sizes) * Viton O-ring for under geophone. * Screws for immobilizing geophone (M4?). * Screws for geophone to interface plate. * Screws for interface plate to PI. * Find or order geophone items. * Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). * Review Shoda-san's Guardian. * Review DIO stuff. * Review SR2 model (especially screens, macro text file). * Review DAC channel requests. |
=== 2018-07-02 === ==== Main Sequence ==== * Install, cable PI yaw stepper. * Decide whether to install ballast mass inside SF. * Install SF ballast mass inside or on top, less reserve for cables. * Route cables around SF up to flying saucer and PI. * Finalize SF trim mass. * Install and cable geophones. * Install arc weights. * Unclamp assembly frame at IM level. * Unlock and center IP. * Calibrate horizontal LVDTs. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. * Create software stepper drivers for SR3 and SRM and link to from STEP_MASTER.adl screen. ==== F0/LBB Stuff ==== * Characterize more blades? * Build filter in PI #1 for SR2. * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position. ==== Software ==== * Review/improve macro file fixes for split models; write klog; submit changes to SVN. * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually). * Create Python drivers for SR3_IM and SR3_BF steppers and link to them from Mio-kun's PICO_MASTER.adl MEDM screen. === 2018-07-09 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== |
Line 51: | Line 56: |
* Get geophone circuit boards from Okutomi-san. * Find fourth feedthrough * Hassle Miyo-kun for stepper drivers. * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done. * Design final SF ballast masses (Fabian). * Get safety bars moved. * Get air hose connection moved. |
=== Tunnel === * Grab and configure a picomotor driver as SR2_BF 10.68.150.25. * Get independent power supply for SR3 so SR2 can be powered back up. * Check SR2, SR3 TM coil gains for magnet polarity compensation. * Calibrate last six IM OSEMs. * Rebuild filter in PI #1. * Install clamps on PI #1. * Install geophone plates on PI #3. * Install geophone plates on PI #1. * Install correct IP in PI #2. * Rebuild filter in PI #2. * Install clamps on PI #2. * Install LBB blade units on PI #2. * Install geophone plates on PI #2. === Mitaka or remotely === * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass. * Set up SR2 Guardian. * Install damping filters for SR2. * Review Shoda-san's Guardian. * Review DIO stuff. * Review DAC channel requests. * Set up SR2 Guardian. * Install damping filters for SR2. * Split SRx real-time models? === Ordering === See ../WishList . |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-07-02
Main Sequence
- Install, cable PI yaw stepper.
- Decide whether to install ballast mass inside SF.
- Install SF ballast mass inside or on top, less reserve for cables.
- Route cables around SF up to flying saucer and PI.
- Finalize SF trim mass.
- Install and cable geophones.
- Install arc weights.
- Unclamp assembly frame at IM level.
- Unlock and center IP.
- Calibrate horizontal LVDTs.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM.
- Create software stepper drivers for SR3 and SRM and link to from STEP_MASTER.adl screen.
F0/LBB Stuff
- Characterize more blades?
- Build filter in PI #1 for SR2.
- Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
Software
- Review/improve macro file fixes for split models; write klog; submit changes to SVN.
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create Python drivers for SR3_IM and SR3_BF steppers and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
2018-07-09
Main Sequence
F0/LBB Stuff
SR Prep Tasks - To Be Scheduled
Tunnel
- Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
- Get independent power supply for SR3 so SR2 can be powered back up.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Calibrate last six IM OSEMs.
- Rebuild filter in PI #1.
- Install clamps on PI #1.
- Install geophone plates on PI #3.
- Install geophone plates on PI #1.
- Install correct IP in PI #2.
- Rebuild filter in PI #2.
- Install clamps on PI #2.
- Install LBB blade units on PI #2.
- Install geophone plates on PI #2.
Mitaka or remotely
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review Shoda-san's Guardian.
- Review DIO stuff.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .