== 2017-12-18 == * Assemble SR2 IP. * Final assembly. * Test IP picos. * Find in-vac cables: * 1 x Type 3-2m * 5 x Type 1-2m * Set up SR2 rack * Get more 1-m power cables and connect up remaining boxes. * Run LAN and power cables for stepper drivers. * Debug SR2 real-time model (Yamamoto-san). * Do inventory of ballast masses. * Adjust verticality of assembly frame; center and immobilize optical table. * Find out (from Takahashi-san) specifications for geophone pod items: * Screws for pod (cap-neck and neck-body). * Cu O-rings for pod (two sizes) * Viton O-ring for under geophone. * Screws for immobilizing geophone (M4?). * Screws for geophone to interface plate. * Screws for interface plate to PI. * Find or order geophone items. * Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). * Review Shoda-san's Guardian. * Review DIO stuff. * Review SR2 model (especially screens, macro text file). * Review DAC channel requests. |
==== Plan for week of 3/5 ==== * See important pump down-related stuff at [[../ToDoBS]]. * Calibrate SF LVDT. * Cable SF FR. * Add SF cap. * Lift SF/... with LGA and check weight/balance. * Get SRM mushroom installed. * Start BF rebuild. |
Line 51: | Line 33: |
* Review Shoda-san's Guardian. * Decide if we're really going to renumber IP channels. * Review DIO stuff. * Review SR2 model (especially screens, macro text file). * Review DAC channel requests. * Find out (from Takahashi-san) specifications for geophone pod items: * Screws for pod (cap-neck and neck-body). * Screws for geophone to interface plate. * Screws for interface plate to PI. * Find or order geophone items. |
|
Line 53: | Line 45: |
* Hassle Miyo-kun for stepper drivers. | |
Line 58: | Line 49: |
* Glue SR3. * Set up SR3 rack. * Set up SRM rack. * Rebuild two BFs. * Disassemble two top filters. * Rebuild three top filters. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
Plan for week of 3/5
See important pump down-related stuff at ../ToDoBS.
- Calibrate SF LVDT.
- Cable SF FR.
- Add SF cap.
- Lift SF/... with LGA and check weight/balance.
- Get SRM mushroom installed.
- Start BF rebuild.
SR Prep Tasks - To Be Scheduled
- Review Shoda-san's Guardian.
- Decide if we're really going to renumber IP channels.
- Review DIO stuff.
- Review SR2 model (especially screens, macro text file).
- Review DAC channel requests.
- Find out (from Takahashi-san) specifications for geophone pod items:
- Screws for pod (cap-neck and neck-body).
- Screws for geophone to interface plate.
- Screws for interface plate to PI.
- Find or order geophone items.
- Get geophone circuit boards from Okutomi-san.
- Find fourth feedthrough
- Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
- Design final SF ballast masses (Fabian).
- Get safety bars moved.
- Get air hose connection moved.
- Glue SR3.
- Set up SR3 rack.
- Set up SRM rack.
- Rebuild two BFs.
- Disassemble two top filters.
- Rebuild three top filters.