Differences between revisions 23 and 85 (spanning 62 versions)
Revision 23 as of 2017-12-18 08:46:46
Size: 1817
Editor: MarkBarton
Comment:
Revision 85 as of 2018-07-17 18:15:24
Size: 3549
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 13: Line 13:
=== Facilities === ==== Facilities ====
Line 15: Line 15:
 * Wipe ladders.  * Wipe ladders, assembly frame.
Line 20: Line 20:
== Coming Weeks ==
Line 21: Line 22:
== 2017-12-18 ==
 * Assemble SR2 IP.
  * Final assembly.
  * Test IP picos.
 * Find in-vac cables:
  * 1 x Type 3-2m
  * 5 x Type 1-2m
 * Set up SR2 rack
  * Get more 1-m power cables and connect up remaining boxes.
  * Run LAN and power cables for stepper drivers.
  * Debug SR2 real-time model (Yamamoto-san).
 * Do inventory of ballast masses.
 * Adjust verticality of assembly frame; center and immobilize optical table.
 * Find out (from Takahashi-san) specifications for geophone pod items:
  * Screws for pod (cap-neck and neck-body).
  * Cu O-rings for pod (two sizes)
  * Viton O-ring for under geophone.
  * Screws for immobilizing geophone (M4?).
  * Screws for geophone to interface plate.
  * Screws for interface plate to PI.
 * Find or order geophone items.
 * Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor).
 * Review Shoda-san's Guardian.
 * Review DIO stuff.
 * Review SR2 model (especially screens, macro text file).
 * Review DAC channel requests.
=== 2018-07-17 ===
==== Main Sequence ====
 * Find LBB damper rods and associated parts.
 * Set tank jacks to nominal height (50 mm).
 * --(Check/restore verticality of security structure.)--
 * Set SF damper magnet ring height.
 * --(Check/correct IP LVDT polarities.)--
 * Calibrate F0 LVDT actuation and FR.
 * Calibrate IP LVDTs and FRs.
 * Cable geophones (temporary routing OK).
 * Set up optical lever.
 * Check/restore alignment of payload, especially optic pitch.
 * Do token TFs (time permitting).
 * Reset all PI FRs to midrange.
 * Lock F0 keystone.
 * Lock suspension laterally except for SF level.
 * Add IM-RM safety bar?
 * Disconnect all cables at inside of feedthroughs.
 * Find LBB damper rods and associated parts.
 * Remove top of tank (including service ring).
 * Set tank jacks to nominal height (50 mm).
 * Lift suspension.
 * Install LBB damper rods.
 * Crane suspension into tank.
 * Hook LBB damper rods.
 * Replace tank lid and service ring.
 * Remove tank lid leaving service ring.
 * Move feedthroughs.
 * Move cables over.
 * Remove safety bar and unlock suspension.
 * Remove First Contact?
 * Restore payload alignment, especially pitch.
 * TFs!

==== F0/LBB/Tank Stuff ====
 * Add LBB ballast masses.
 * Help Sato-san with swapping IP in PI #2.
 * Crane IP to second floor.
 * Rebuild PI #2 F0.

==== Software Etc ====
Line 51: Line 67:
 * Get geophone circuit boards from Okutomi-san.
 * Find fourth feedthrough
 * Hassle Miyo-kun for stepper drivers.
 * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
 * Design final SF ballast masses (Fabian).
 * Get safety bars moved.
 * Get air hose connection moved.
=== Tunnel ===
 * Retrieve BNC-Lemo cable from Nakano-kun.
 * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
 * Install, cable SR3 PI yaw stepper.
 * Correct flipped connections in SR2 PI LVDTs.
 * Correct flipped connections in SRM PI LVDTs.
 * Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
 * Get independent power supply for SR3 so SR2 can be powered back up.
 * Check SR2, SR3 TM coil gains for magnet polarity compensation.
 * Calibrate last six IM OSEMs.
 * Rebuild filter in PI #1.
 * Install clamps on PI #1.
 * Install geophone plates on PI #3.
 * Install geophone plates on PI #1.
 * Install correct IP in PI #2.
 * Rebuild filter in PI #2.
 * Install clamps on PI #2.
 * Install LBB blade units on PI #2.
 * Install geophone plates on PI #2.
 * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

=== Mitaka or remotely ===
 * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
 * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
 * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
 * Set up SR2 Guardian.
 * Install damping filters for SR2.
 * Review DAC channel requests.
 * Set up SR2 Guardian.
 * Install damping filters for SR2.
 * Split SRx real-time models?

=== Ordering ===
See ../WishList .

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders, assembly frame.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-07-17

Main Sequence

  • Find LBB damper rods and associated parts.
  • Set tank jacks to nominal height (50 mm).
  • Check/restore verticality of security structure.

  • Set SF damper magnet ring height.
  • Check/correct IP LVDT polarities.

  • Calibrate F0 LVDT actuation and FR.
  • Calibrate IP LVDTs and FRs.
  • Cable geophones (temporary routing OK).
  • Set up optical lever.
  • Check/restore alignment of payload, especially optic pitch.
  • Do token TFs (time permitting).
  • Reset all PI FRs to midrange.
  • Lock F0 keystone.
  • Lock suspension laterally except for SF level.
  • Add IM-RM safety bar?
  • Disconnect all cables at inside of feedthroughs.
  • Find LBB damper rods and associated parts.
  • Remove top of tank (including service ring).
  • Set tank jacks to nominal height (50 mm).
  • Lift suspension.
  • Install LBB damper rods.
  • Crane suspension into tank.
  • Hook LBB damper rods.
  • Replace tank lid and service ring.
  • Remove tank lid leaving service ring.
  • Move feedthroughs.
  • Move cables over.
  • Remove safety bar and unlock suspension.
  • Remove First Contact?
  • Restore payload alignment, especially pitch.
  • TFs!

F0/LBB/Tank Stuff

  • Add LBB ballast masses.
  • Help Sato-san with swapping IP in PI #2.
  • Crane IP to second floor.
  • Rebuild PI #2 F0.

Software Etc

SR Prep Tasks - To Be Scheduled

Tunnel

  • Retrieve BNC-Lemo cable from Nakano-kun.
  • Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
  • Install, cable SR3 PI yaw stepper.
  • Correct flipped connections in SR2 PI LVDTs.
  • Correct flipped connections in SRM PI LVDTs.
  • Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
  • Get independent power supply for SR3 so SR2 can be powered back up.
  • Check SR2, SR3 TM coil gains for magnet polarity compensation.
  • Calibrate last six IM OSEMs.
  • Rebuild filter in PI #1.
  • Install clamps on PI #1.
  • Install geophone plates on PI #3.
  • Install geophone plates on PI #1.
  • Install correct IP in PI #2.
  • Rebuild filter in PI #2.
  • Install clamps on PI #2.
  • Install LBB blade units on PI #2.
  • Install geophone plates on PI #2.
  • Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

Mitaka or remotely

  • Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
  • Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review DAC channel requests.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Split SRx real-time models?

Ordering

See ../WishList .

KAGRA/Subgroups/VIS/TypeB/ToDoSR (last edited 2019-01-04 15:25:56 by MarkBarton)