2012
Comment:
|
1790
|
Deletions are marked like this. | Additions are marked like this. |
Line 21: | Line 21: |
== 2017-12-18 == * --(Assemble SR2 IP.)-- * --(Final assembly.)-- * --(Test IP picos.)-- |
== 2018-01-09 == * Reinstall L-brackets * Crane in IM. * Center IM. * Set up optical lever for leveling optic. * Hang optic. * Hang RM. * Cable up OSEMs. |
Line 31: | Line 36: |
* Debug SR2 real-time model (Yamamoto-san). * --(Calibrate BF LVDT.)-- |
|
Line 34: | Line 37: |
* Assembly frame stuff: * --(Center and immobilize optical table.)-- * --(Adjust verticality of assembly frame.)-- * --(Remove internal crossbars for SF and BF.)-- * --(Adjust external crossbar heights.)-- * Find out (from Takahashi-san) specifications for geophone pod items: * Screws for pod (cap-neck and neck-body). * --(Cu O-rings for pod (two sizes).)-- * Viton O-ring for under geophone. * Screws for immobilizing geophone (M4?). * Screws for geophone to interface plate. * Screws for interface plate to PI. * Find or order geophone items. |
|
Line 56: | Line 46: |
* Find out (from Takahashi-san) specifications for geophone pod items: * Screws for pod (cap-neck and neck-body). * --(Cu O-rings for pod (two sizes).)-- * Viton O-ring for under geophone. * Screws for immobilizing geophone (M4?). * Screws for geophone to interface plate. * Screws for interface plate to PI. * Find or order geophone items. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2018-01-09
- Reinstall L-brackets
- Crane in IM.
- Center IM.
- Set up optical lever for leveling optic.
- Hang optic.
- Hang RM.
- Cable up OSEMs.
- Find in-vac cables:
- 1 x Type 3-2m
- 5 x Type 1-2m
- Set up SR2 rack
- Get more 1-m power cables and connect up remaining boxes.
- Run LAN and power cables for stepper drivers.
- Do inventory of ballast masses.
- Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor).
- Review Shoda-san's Guardian.
- Review DIO stuff.
- Review SR2 model (especially screens, macro text file).
- Review DAC channel requests.
SR Prep Tasks - To Be Scheduled
- Find out (from Takahashi-san) specifications for geophone pod items:
- Screws for pod (cap-neck and neck-body).
Cu O-rings for pod (two sizes).
- Viton O-ring for under geophone.
- Screws for immobilizing geophone (M4?).
- Screws for geophone to interface plate.
- Screws for interface plate to PI.
- Find or order geophone items.
- Get geophone circuit boards from Okutomi-san.
- Find fourth feedthrough
- Hassle Miyo-kun for stepper drivers.
- Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
- Design final SF ballast masses (Fabian).
- Get safety bars moved.
- Get air hose connection moved.