Line 20: | Line 20: |
== Coming Weeks == === 2018-05-14 === === Main Sequence === * Weigh IM/... section. * Do === F0/LBB Stuff === * Final prep for F0 prototype blade test (5/14) * F0 prototype blade test with Takahashi-san (5/15 or TBD) |
|
Line 21: | Line 30: |
== 2018-01-09 == * Wipe/blow frame. * Drape clean bag. * Reinstall L-brackets * Crane in IM. * Center IM. * Set up optical lever for leveling optic. * Hang optic. * Hang RM. * Cable up OSEMs. * Find in-vac cables: * 1 x Type 3-2m * 5 x Type 1-2m * Set up SR2 rack * Get more 1-m power cables and connect up remaining boxes. * Run LAN and power cables for stepper drivers. * Do inventory of ballast masses. * Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). * Review Shoda-san's Guardian. * Decide if we're really going to renumber IP channels. * Review DIO stuff. * Review SR2 model (especially screens, macro text file). * Review DAC channel requests. |
== 2018-05-21 == === Main Sequence === === F0/LBB Stuff === == 2018-05-28 == === Main Sequence === === F0/LBB Stuff === == 2018-06-04 == === Main Sequence === === F0/LBB Stuff === == 2018-06-11 == === Main Sequence === === F0/LBB Stuff === == 2018-06-18 == === Main Sequence === === F0/LBB Stuff === == 2018-06-25 == === Main Sequence === === F0/LBB Stuff === == 2018-07-02 == === Main Sequence === === F0/LBB Stuff === == 2018-07-09 == === Main Sequence === === F0/LBB Stuff === == 2018-07-16 == === Main Sequence === === F0/LBB Stuff === == 2018-07-23 == === Main Sequence === === F0/LBB Stuff === |
Line 49: | Line 73: |
* Find out (from Takahashi-san) specifications for geophone pod items: * Screws for pod (cap-neck and neck-body). * --(Cu O-rings for pod (two sizes).)-- * Viton O-ring for under geophone. * Screws for immobilizing geophone (M4?). * Screws for geophone to interface plate. * Screws for interface plate to PI. * Find or order geophone items. * Get geophone circuit boards from Okutomi-san. * Find fourth feedthrough * Hassle Miyo-kun for stepper drivers. * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done. * Design final SF ballast masses (Fabian). * Get safety bars moved. * Get air hose connection moved. |
=== Tunnel === * Get SRM mushroom installed. * --(Find 4 more feedthroughs for SRM.)-- * Install first set of LBB damper rings in SR2 (or SR3?) tank. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * Finish half-completed geophones. * Characterize top filter prototype blades. * Decide final top filter blade parameters and order. * Rebuild three top filters. * Do buoyancy calculation (see LIGO-T1100616). === Mitaka or remotely === * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass. * Set up SR2 Guardian. * Install damping filters for SR2. * Review Shoda-san's Guardian. * Review DIO stuff. * Review DAC channel requests. * Set up SR2 and SR3 Guardian. * Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen. * Install damping filters for SR2. === Ordering === See ../WishList . |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-05-14
Main Sequence
- Weigh IM/... section.
- Do
F0/LBB Stuff
- Final prep for F0 prototype blade test (5/14)
- F0 prototype blade test with Takahashi-san (5/15 or TBD)
2018-05-21
Main Sequence
F0/LBB Stuff
2018-05-28
Main Sequence
F0/LBB Stuff
2018-06-04
Main Sequence
F0/LBB Stuff
2018-06-11
Main Sequence
F0/LBB Stuff
2018-06-18
Main Sequence
F0/LBB Stuff
2018-06-25
Main Sequence
F0/LBB Stuff
2018-07-02
Main Sequence
F0/LBB Stuff
2018-07-09
Main Sequence
F0/LBB Stuff
2018-07-16
Main Sequence
F0/LBB Stuff
2018-07-23
Main Sequence
F0/LBB Stuff
SR Prep Tasks - To Be Scheduled
Tunnel
- Get SRM mushroom installed.
Find 4 more feedthroughs for SRM.
- Install first set of LBB damper rings in SR2 (or SR3?) tank.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- Finish half-completed geophones.
- Characterize top filter prototype blades.
- Decide final top filter blade parameters and order.
- Rebuild three top filters.
- Do buoyancy calculation (see LIGO-T1100616).
Mitaka or remotely
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review Shoda-san's Guardian.
- Review DIO stuff.
- Review DAC channel requests.
- Set up SR2 and SR3 Guardian.
- Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
- Install damping filters for SR2.
Ordering
See ../WishList .