1697
Comment:
|
3312
|
Deletions are marked like this. | Additions are marked like this. |
Line 13: | Line 13: |
=== Facilities === | ==== Facilities ==== |
Line 20: | Line 20: |
== Coming Weeks == | |
Line 21: | Line 22: |
== 2018-01-09 == * Center IM. * Set up optical lever for leveling optic. * Hang optic. * Hang RM. * Cable up OSEMs. |
=== 2018-06-04 === ==== Main Sequence ==== * Debug stuff. * Finish debugging BS BIO. * Make SR3, SR2, SRM like BS. * IM BIO connection is wrong. V goes H and H goes V. * Swap the LPCD to HPCD. * Check the payload so that it gives us the correct TF. * Install L-brackets on BF and SF rings. * Add extra spacers under SF to give more jack range. * Suspend BF/... section. * Adjust BF trim mass. * Route cables through SF-BF flying saucer up to bottom of SF. * Adjust BF trim mass. * Readjust payload. * Take TFs. * Add budgeted ballast mass to SF. * Cable, test SF LVDT and FR. * Grab and configure a picomotor driver as SR2_BF 10.68.150.25. * Set up software pico drivers for SR3_IM and SR3_BF. ==== F0/LBB Stuff ==== * Finish tuning F0 in PI #3. * Characterize more blades? * Park PI #1 in SR3 AF. * Crane PI #3 behind SR3. * Crane PI #1 to factory area. * Build/tune F0 in PI #1. ==== Software ==== * Split SRx real-time models? * Fix white channels on BS screens (will probably be an issue for SRx models if/when split). === 2018-06-18 === ==== Main Sequence ==== * SF/... TFs. ==== F0/LBB Stuff ==== * Wrap PI #1. * Crane PI #1 to SR2 AF. * Crane PI #3 into SR3 AF. * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank. |
Line 28: | Line 63: |
* Find in-vac cables: * 1 x Type 3-2m * 5 x Type 1-2m * Set up SR2 rack * Get more 1-m power cables and connect up remaining boxes. * Run LAN and power cables for stepper drivers. * Do inventory of ballast masses. * Review Shoda-san's Guardian. * Decide if we're really going to renumber IP channels. * Review DIO stuff. * Review SR2 model (especially screens, macro text file). * Review DAC channel requests. |
=== 2018-06-25 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-02 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-09 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-16 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-23 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== |
Line 44: | Line 87: |
* Find out (from Takahashi-san) specifications for geophone pod items: * Screws for pod (cap-neck and neck-body). * --(Cu O-rings for pod (two sizes).)-- * Viton O-ring for under geophone. * Screws for immobilizing geophone (M4?). * Screws for geophone to interface plate. * Screws for interface plate to PI. * Find or order geophone items. * Get geophone circuit boards from Okutomi-san. * Find fourth feedthrough * Hassle Miyo-kun for stepper drivers. * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done. * Design final SF ballast masses (Fabian). * Get safety bars moved. * Get air hose connection moved. |
=== Tunnel === * Calibrate last six IM OSEMs. * Install first set of LBB damper rings in SR3 tank. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * Finish half-completed geophones. * Characterize final top filter blades (from 5/31). * Rebuild filters in PIs #1 and #3. * Install clamps on PIs #1 and #3. * Install LBB units on PIs #1 and #3. * Install correct IP in PI #3. * Rebuild filter in PI #2. * Install clamps on PI #2. * Install LBB blade units on PI #2. === Mitaka or remotely === * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass. * Set up SR2 Guardian. * Install damping filters for SR2. * Review Shoda-san's Guardian. * Review DIO stuff. * Review DAC channel requests. * Set up SR2 and SR3 Guardian. * Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen. * Install damping filters for SR2. * Do buoyancy calculation (see LIGO-T1100616). === Ordering === See ../WishList . |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-06-04
Main Sequence
- Debug stuff.
- Finish debugging BS BIO.
- Make SR3, SR2, SRM like BS.
- IM BIO connection is wrong. V goes H and H goes V.
- Swap the LPCD to HPCD.
- Check the payload so that it gives us the correct TF.
- Install L-brackets on BF and SF rings.
- Add extra spacers under SF to give more jack range.
- Suspend BF/... section.
- Adjust BF trim mass.
- Route cables through SF-BF flying saucer up to bottom of SF.
- Adjust BF trim mass.
- Readjust payload.
- Take TFs.
- Add budgeted ballast mass to SF.
- Cable, test SF LVDT and FR.
- Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
- Set up software pico drivers for SR3_IM and SR3_BF.
F0/LBB Stuff
- Finish tuning F0 in PI #3.
- Characterize more blades?
- Park PI #1 in SR3 AF.
- Crane PI #3 behind SR3.
- Crane PI #1 to factory area.
- Build/tune F0 in PI #1.
Software
- Split SRx real-time models?
- Fix white channels on BS screens (will probably be an issue for SRx models if/when split).
2018-06-18
Main Sequence
- SF/... TFs.
F0/LBB Stuff
- Wrap PI #1.
- Crane PI #1 to SR2 AF.
- Crane PI #3 into SR3 AF.
- Remove SR3 tank lid, crane LBB rings to top of lower half of the tank.
2018-06-25
Main Sequence
F0/LBB Stuff
2018-07-02
Main Sequence
F0/LBB Stuff
2018-07-09
Main Sequence
F0/LBB Stuff
2018-07-16
Main Sequence
F0/LBB Stuff
2018-07-23
Main Sequence
F0/LBB Stuff
SR Prep Tasks - To Be Scheduled
Tunnel
- Calibrate last six IM OSEMs.
- Install first set of LBB damper rings in SR3 tank.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- Finish half-completed geophones.
- Characterize final top filter blades (from 5/31).
- Rebuild filters in PIs #1 and #3.
- Install clamps on PIs #1 and #3.
- Install LBB units on PIs #1 and #3.
- Install correct IP in PI #3.
- Rebuild filter in PI #2.
- Install clamps on PI #2.
- Install LBB blade units on PI #2.
Mitaka or remotely
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review Shoda-san's Guardian.
- Review DIO stuff.
- Review DAC channel requests.
- Set up SR2 and SR3 Guardian.
- Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
- Install damping filters for SR2.
- Do buoyancy calculation (see LIGO-T1100616).
Ordering
See ../WishList .