2983
Comment:
|
2878
|
Deletions are marked like this. | Additions are marked like this. |
Line 13: | Line 13: |
=== Facilities === | ==== Facilities ==== |
Line 20: | Line 20: |
== Coming Weeks == | |
Line 21: | Line 22: |
== 2017-11-06 == * Confirm location of sapphire prisms. * Bring SR2 into tunnel. * Find mirror gluing items. * Mirror * Mirror box * Prisms * Secondary prisms * Magnets * Magnet bases * Prism micrometer stages * Prism jigs * Magnet jigs * Balance * Stirrers * Mixing dishes * Lenses for inspecting scribe lines * Procedure document. * EP30 * Glass beads * Rehearse mirror gluing. |
=== 2018-06-04 === ==== Main Sequence ==== * Debug stuff. * IM BIO connection is wrong. V goes H and H goes V. * Swap the LPCD to HPCD. * Check the payload so that it gives us the correct TF. * Debug IP BIO connection. (Debug BS IP at the same time.) * Adjust BF trim mass. * Route cables through SF-BF flying saucer up to bottom of SF. * Adjust BF trim mass. * Readjust payload. * Take TFs. * Add budgeted ballast mass to SF. * Cable, test SF LVDT and FR. * Grab and configure a picomotor driver as SR2_BF 10.68.150.25. * Set up software pico drivers for SR3_IM and SR3_BF. ==== F0/LBB Stuff ==== * Finish tuning F0 in PI #3. * Park PI #1 in SR3 AF. * Crane PI #3 behind SR3. * Crane PI #1 to factory area. * Build/tune F0 in PI #1. * Wrap PI #1. * Crane PI #1 to SR2 AF. === 2018-06-18 === ==== Main Sequence ==== * SF/... TFs. === 2018-06-25 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-02 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-09 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-16 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-23 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== |
Line 45: | Line 75: |
== SR Prep Tasks == === Design/Purchasing === * Do rough mass budget for SR2/SR3/SRM. * Design final SF ballast masses (Fabian). * Confrim location of sapphire prisms. |
== SR Prep Tasks - To Be Scheduled == === Tunnel === * Calibrate last six IM OSEMs. * Install first set of LBB damper rings in SR3 tank. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * Finish half-completed geophones. * Characterize final top filter blades (from 5/31). * Rebuild filters in PIs #1 and #3. * Install clamps on PIs #1 and #3. * Install LBB units on PIs #1 and #3. * Install correct IP in PI #3. * Rebuild filter in PI #2. * Install clamps on PI #2. * Install LBB blade units on PI #2. === Mitaka or remotely === * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass. * Set up SR2 Guardian. * Install damping filters for SR2. * Review Shoda-san's Guardian. * Review DIO stuff. * Review DAC channel requests. * Set up SR2 and SR3 Guardian. * Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen. * Install damping filters for SR2. * Do buoyancy calculation (see LIGO-T1100616). |
Line 51: | Line 102: |
==== Order now ==== * Bread boards for SR -> Orderd. delivery date:10/18-20 * Include installation work in the contract * Total budget = 5MJPY * PEEK collet for "Small hexagon"(cable clamp) -> need modification. ==== Need simple design changes ==== * SUS wires(3 types) for the LBB * Change the length -> Orderd. delivery date:10/ * Receptacles for Bread board damper * There is a mistake in the PROMEC drawing. * Hirata-san will make a new 2D drawing * IM wire clamps for SR * Need to change the height -> watiting second quote. * SR assembly frame -> Ordered. delivery date:9/27-29 * Mark is checking the design from Fabian * We should order the parts necessary to modify the BS assembly frame to the SR2 assembly frame ==== Need Fabian's input ==== * Cable clamps for BF,SF and PI -> 方式を決める * Design change for the PI clamps, because the SR PIs are NIKHEF ones. * Ballast masses for BF and SF * 製作に2週間程度 * 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。 * 測定に必要な物品の準備 -> 月曜日に高橋さんと相談 ==== Need more discussion/checks ==== * Blade spring assembly for LBB * Check the load of the LBB and decide the design load of the springs * Correct the length * Scale the width of the current blades to design the new blades -> 高橋さんと相談 * SR用LBBの重さを確認 * Bread board damper rings * Need to check whether we can put a full ring into the chamber from the side flanges or not. -> need modification === Electronics === * Get cables/cards for SR3: * 5 DSub-37 cables (tent) * 5 DSub-15M to DSub-9M adapter cables (tent) * 3 DIO cards (tent) * 2 DSub-9 FF gender benders (for LVDTs) * extra ADC card(s)? * extra DAC card(s)? * BNC-LEMO adapter (for LVDTs) * etc |
=== Ordering === See ../WishList . |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-06-04
Main Sequence
- Debug stuff.
- IM BIO connection is wrong. V goes H and H goes V.
- Swap the LPCD to HPCD.
- Check the payload so that it gives us the correct TF.
- Debug IP BIO connection. (Debug BS IP at the same time.)
- Adjust BF trim mass.
- Route cables through SF-BF flying saucer up to bottom of SF.
- Adjust BF trim mass.
- Readjust payload.
- Take TFs.
- Add budgeted ballast mass to SF.
- Cable, test SF LVDT and FR.
- Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
- Set up software pico drivers for SR3_IM and SR3_BF.
F0/LBB Stuff
- Finish tuning F0 in PI #3.
- Park PI #1 in SR3 AF.
- Crane PI #3 behind SR3.
- Crane PI #1 to factory area.
- Build/tune F0 in PI #1.
- Wrap PI #1.
- Crane PI #1 to SR2 AF.
2018-06-18
Main Sequence
- SF/... TFs.
2018-06-25
Main Sequence
F0/LBB Stuff
2018-07-02
Main Sequence
F0/LBB Stuff
2018-07-09
Main Sequence
F0/LBB Stuff
2018-07-16
Main Sequence
F0/LBB Stuff
2018-07-23
Main Sequence
F0/LBB Stuff
SR Prep Tasks - To Be Scheduled
Tunnel
- Calibrate last six IM OSEMs.
- Install first set of LBB damper rings in SR3 tank.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- Finish half-completed geophones.
- Characterize final top filter blades (from 5/31).
- Rebuild filters in PIs #1 and #3.
- Install clamps on PIs #1 and #3.
- Install LBB units on PIs #1 and #3.
- Install correct IP in PI #3.
- Rebuild filter in PI #2.
- Install clamps on PI #2.
- Install LBB blade units on PI #2.
Mitaka or remotely
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review Shoda-san's Guardian.
- Review DIO stuff.
- Review DAC channel requests.
- Set up SR2 and SR3 Guardian.
- Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
- Install damping filters for SR2.
- Do buoyancy calculation (see LIGO-T1100616).
Ordering
See ../WishList .