Line 13: Line 13:
=== Facilities === ==== Facilities ====
Line 15: Line 15:
 * Wipe ladders.  * Wipe ladders, assembly frame.
Line 20: Line 20:
== Coming Weeks ==
Line 21: Line 22:
== 2018-01-15 ==
 * Set up SR2 rack
  * --(Get more 1-m power cables and connect up remaining boxes.)-- (No orange ones left - used yellow temporarily.)
  * Run LAN and power cables for stepper drivers.
 * --(Cable RM OSEMs to rack.)--
 * --(Setup QPD and cable to rack.)--
 * --(Fix links to OPLEVINF filter screen from chain screen.)--
 * --(Initialize gains and matrix elements for SR2 OL.)--
 * --(Wash parts for flying saucers.)--
 * Test nuts for flying saucers.
 * Order more nuts for flying saucers.
 * Add DRIVEALIGN button to overview screen.
 * --(Check sizes and in-stock numbers of screws for geophones.)--
  * 20 x M8*35 (need 3*16=48)
  * 35 x M8*30 (need 3*8=24)
  * 4 x Viton disks (need 4)
  * 123 M8 washers (need 3*24=72)
 * --(Do TFs from RM OSEMS to OL pitch/roll.)--
 * --(Make IM OSEMs.)--
 * --(Install load gauge adapter.)--
 * --(Lift IM/RM/SR with LGA, check/adjust total mass and pitch/yaw balance.)--
 * --(Crane in BF.)--
 * --(Install BF-IRM rods and top plate of IRM.)--
 * --(Install BF-IM rod with flying saucer.)--
 * --(Hook IM.)--
 * --(Route cables via flying saucer up to under BF.)--
=== 2018-12-17 ===
==== SRM ====
 * Install/test new yaw mechanism.
 * Adjust height.
 * Check/adjust optic pitch; release LED to SR2.
 * Install Enomoto-kun's beam target plate (if available).
 * Install extension cord for pico drivers.
 * Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.)
 * Find one geophone cable ordered for SRM but missing.
 * Rearrange miswired geophone cable.
 * Rebuild defective geophone cable.
 * Seal geophones.
 * Install geophones and arc weights.
 * Center IP.
==== SR3 ====
 * Install/test new yaw mechanism.
 * Adjust height.
 * Realign OL.
Line 48: Line 41:
== 2018-01-22 ==
 * Test IM picos.
 * Prepare SR3 area for PI test.
 * Adjust IM/RM/SR total mass and pitch/roll balance.
 * Check BF yaw pico.

== 2018-01-28 ==
 * Install IRM.
 * Adjust IM OSEMs.
 * Cable IM OSEMs.
 * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
 * Install pre-calculated BF trim mass.
 * Lift
 
 * Find in-vac cables:
  * 1 x Type 3-2m
  * 5 x Type 1-2m
 * Review Shoda-san's Guardian.
 * Decide if we're really going to renumber IP channels.
 * Review DIO stuff.
 * Review SR2 model (especially screens, macro text file).
 * Review DAC channel requests.
==== SR2 ====
 * Install/test new yaw adjuster.
 * Adjust height.
 * Get top plate reduced?
 * Set up OL cabling.
 * Set up OL.
 * Remove tape, writing etc on PI and PI items.
 * Add new feedthrough to lower part of tank (with Izumi-san-tachi)?
 * Install cable for MIF pico on LBB (with Izumi-san-tachi)?
 * Add ballast mass to LBB.
Line 74: Line 55:
 * Replace temporary yellow DC power cables in SR2 rack with orange ones.
 * Find out (from Takahashi-san) specifications for geophone pod items:
  * Screws for pod (cap-neck and neck-body).
  * --(Cu O-rings for pod (two sizes).)--
  * Viton O-ring for under geophone.
  * Screws for immobilizing geophone (M4?).
  * Screws for geophone to interface plate.
  * Screws for interface plate to PI.
 * Find or order geophone items.
 * Get geophone circuit boards from Okutomi-san.
 * Find fourth feedthrough
 * Hassle Miyo-kun for stepper drivers.
 * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
 * Design final SF ballast masses (Fabian).
 * Get safety bars moved.
 * Get air hose connection moved.
 * Install SR2 booth thermometer and edit macro.txt file.
=== Tunnel ===
 * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
 * Check SR2, SR3 TM coil gains for magnet polarity compensation.
 * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

=== Mitaka or remotely ===
 * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
 * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
 * Install damping filters for SR2.
 * Review DAC channel requests.
 * Split SRx real-time models?

=== Ordering ===
See ../WishList .

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders, assembly frame.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-12-17

SRM

  • Install/test new yaw mechanism.
  • Adjust height.
  • Check/adjust optic pitch; release LED to SR2.
  • Install Enomoto-kun's beam target plate (if available).
  • Install extension cord for pico drivers.
  • Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.)
  • Find one geophone cable ordered for SRM but missing.
  • Rearrange miswired geophone cable.
  • Rebuild defective geophone cable.
  • Seal geophones.
  • Install geophones and arc weights.
  • Center IP.

SR3

  • Install/test new yaw mechanism.
  • Adjust height.
  • Realign OL.

SR2

  • Install/test new yaw adjuster.
  • Adjust height.
  • Get top plate reduced?
  • Set up OL cabling.
  • Set up OL.
  • Remove tape, writing etc on PI and PI items.
  • Add new feedthrough to lower part of tank (with Izumi-san-tachi)?
  • Install cable for MIF pico on LBB (with Izumi-san-tachi)?
  • Add ballast mass to LBB.

SR Prep Tasks - To Be Scheduled

Tunnel

  • Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
  • Check SR2, SR3 TM coil gains for magnet polarity compensation.
  • Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

Mitaka or remotely

  • Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Install damping filters for SR2.
  • Review DAC channel requests.
  • Split SRx real-time models?

Ordering

See ../WishList .