== 2018-01-15 == * Set up SR2 rack * --(Get more 1-m power cables and connect up remaining boxes.)-- (No orange ones left - used yellow temporarily.) * Run LAN and power cables for stepper drivers. * --(Cable RM OSEMs to rack.)-- * --(Setup QPD and cable to rack.)-- * --(Fix links to OPLEVINF filter screen from chain screen.)-- * --(Initialize gains and matrix elements for SR2 OL.)-- * --(Wash parts for flying saucers.)-- * Test nuts for flying saucers. * Order more nuts for flying saucers. * Add DRIVEALIGN button to overview screen. * --(Check sizes and in-stock numbers of screws for geophones.)-- * 20 x M8*35 (need 3*16=48) * 35 x M8*30 (need 3*8=24) * 4 x Viton disks (need 4) * 123 M8 washers (need 3*24=72) * --(Do TFs from RM OSEMS to OL pitch/roll.)-- * --(Make IM OSEMs.)-- * --(Install load gauge adapter.)-- * --(Lift IM/RM/SR with LGA, check/adjust total mass and pitch/yaw balance.)-- * --(Crane in BF.)-- * --(Install BF-IRM rods and top plate of IRM.)-- * --(Install BF-IM rod with flying saucer.)-- * --(Hook IM.)-- * --(Route cables via flying saucer up to under BF.)-- |
==== Plan for week of 4/16 ==== * Move SF and BF for SRM out of the way. * Check results of gluing. * Build 1xRM * Calibrate OSEMs. * Start SR3 Hang * Reset assembly frame crossbars to correct heights. * Center the optical table. * Align the assembly frame vertically. * Install IM ring and IM. * Hang optic. * Hang RM. * Cable RM OSEMs. |
Line 48: | Line 35: |
== 2018-01-22 == * Test IM picos. * Prepare SR3 area for PI test. * Adjust IM/RM/SR total mass and pitch/roll balance. * Check BF yaw pico. == 2018-01-28 == * Install IRM. * Adjust IM OSEMs. * Cable IM OSEMs. * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. * Install pre-calculated BF trim mass. * Lift * Find in-vac cables: * 1 x Type 3-2m * 5 x Type 1-2m * Review Shoda-san's Guardian. * Decide if we're really going to renumber IP channels. * Review DIO stuff. * Review SR2 model (especially screens, macro text file). * Review DAC channel requests. |
==== Plan for week of 4/23 ==== * Clean parts (cable clamp bases, etc, etc; Hirata-san). * Observe KAGRA Phase 1 operations, assist if problems arise. * Continue SR3 hang. |
Line 74: | Line 43: |
* Replace temporary yellow DC power cables in SR2 rack with orange ones. | * Review Shoda-san's Guardian. * Review DIO stuff. * Review DAC channel requests. |
Line 77: | Line 48: |
* --(Cu O-rings for pod (two sizes).)-- * Viton O-ring for under geophone. * Screws for immobilizing geophone (M4?). |
|
Line 85: | Line 53: |
* Hassle Miyo-kun for stepper drivers. | |
Line 90: | Line 57: |
* Install SR2 booth thermometer and edit macro.txt file. | * Glue SR3. * Disassemble two top filters. * Rebuild three top filters. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
Plan for week of 4/16
- Move SF and BF for SRM out of the way.
- Check results of gluing.
- Build 1xRM
- Calibrate OSEMs.
- Start SR3 Hang
- Reset assembly frame crossbars to correct heights.
- Center the optical table.
- Align the assembly frame vertically.
- Install IM ring and IM.
- Hang optic.
- Hang RM.
- Cable RM OSEMs.
Plan for week of 4/23
- Clean parts (cable clamp bases, etc, etc; Hirata-san).
- Observe KAGRA Phase 1 operations, assist if problems arise.
- Continue SR3 hang.
SR Prep Tasks - To Be Scheduled
- Review Shoda-san's Guardian.
- Review DIO stuff.
- Review DAC channel requests.
- Find out (from Takahashi-san) specifications for geophone pod items:
- Screws for pod (cap-neck and neck-body).
- Screws for geophone to interface plate.
- Screws for interface plate to PI.
- Find or order geophone items.
- Get geophone circuit boards from Okutomi-san.
- Find fourth feedthrough
- Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
- Design final SF ballast masses (Fabian).
- Get safety bars moved.
- Get air hose connection moved.
- Glue SR3.
- Disassemble two top filters.
- Rebuild three top filters.