Line 13: | Line 13: |
=== Facilities === | ==== Facilities ==== |
Line 15: | Line 15: |
* Wipe ladders. | * Wipe ladders, assembly frame. |
Line 20: | Line 20: |
== Coming Weeks == | |
Line 21: | Line 22: |
== 2018-01-15 == * Set up SR2 rack * --(Get more 1-m power cables and connect up remaining boxes.)-- (No orange ones left - used yellow temporarily.) * Run LAN and power cables for stepper drivers. * --(Cable RM OSEMs to rack.)-- * --(Setup QPD and cable to rack.)-- * --(Fix links to OPLEVINF filter screen from chain screen.)-- * --(Initialize gains and matrix elements for SR2 OL.)-- * --(Wash parts for flying saucers.)-- * Test nuts for flying saucers. * Order more nuts for flying saucers. * Add DRIVEALIGN button to overview screen. * --(Check sizes and in-stock numbers of screws for geophones.)-- * 20 x M8*35 (need 3*16=48) * 35 x M8*30 (need 3*8=24) * 4 x Viton disks (need 4) * 123 M8 washers (need 3*24=72) * --(Do TFs from RM OSEMS to OL pitch/roll.)-- * --(Make IM OSEMs.)-- * --(Install load gauge adapter.)-- * --(Lift IM/RM/SR with LGA, check/adjust total mass and pitch/yaw balance.)-- * --(Crane in BF.)-- * --(Install BF-IRM rods and top plate of IRM.)-- * --(Install BF-IM rod with flying saucer.)-- * --(Hook IM.)-- * --(Route cables via flying saucer up to under BF.)-- |
=== 2018-07-17 === ==== Main Sequence ==== * --(Find LBB damper rods and associated parts.)-- * --(Check/restore verticality of security structure.)-- * --(Set SF damper magnet ring height.)-- * --(Check/correct IP LVDT polarities.)-- * --(Calibrate IP FR sensing.)-- * --(Set safety screw and safety nut on F0 keystone; remove Kapton tape.)-- * --(Set up optical lever.)-- * --(Check/restore alignment of payload, especially optic pitch.)-- * --(Do token TFs (time permitting).)-- * --(Lock F0 keystone.)-- * --(Lock suspension laterally except for SF level.)-- * --(Add IM-RM safety bar.)-- * --(Disconnect all cables at inside of feedthroughs.)-- * --(Remove top of tank (including service ring).)-- * --(Set tank jacks to nominal height (50 mm).)-- * --(Lift suspension.)-- * --(Install LBB damper rods.)-- * --(Crane suspension into tank.)-- * --(Hook LBB damper rods.)-- * --(Replace tank lid and service ring.)-- * Remove tank lid leaving service ring. * Move feedthroughs. * Move cables over. * Test cables. * Calibrate PI LVDT and FR actuation. * Remove safety bar and unlock suspension. * Remove First Contact? * Restore payload alignment, especially pitch. * Cable geophones. * Calibrate IP LVDT and FR actuation. * TFs! |
Line 48: | Line 56: |
== 2018-01-22 == * Debug keystone issue. * Adjust IM/RM/SR total mass and pitch/roll balance. * Test IM picos. * Prepare SR3 area for PI test. * Check BF yaw pico. |
==== F0/LBB/Tank Stuff ==== * --(Help Sato-san with swapping IP in PI #2.)-- * --(Crane IP to second floor.)-- * Rebuild PI #2 F0. |
Line 55: | Line 61: |
== 2018-01-28 == * Install IRM. * Adjust IM OSEMs. * Cable IM OSEMs. * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. * Install pre-calculated BF trim mass. * Lift * Find in-vac cables: * 1 x Type 3-2m * 5 x Type 1-2m * Review Shoda-san's Guardian. * Decide if we're really going to renumber IP channels. * Review DIO stuff. * Review SR2 model (especially screens, macro text file). * Review DAC channel requests. |
==== Software Etc ==== |
Line 75: | Line 66: |
* Replace temporary yellow DC power cables in SR2 rack with orange ones. * Find out (from Takahashi-san) specifications for geophone pod items: * Screws for pod (cap-neck and neck-body). * --(Cu O-rings for pod (two sizes).)-- * Viton O-ring for under geophone. * Screws for immobilizing geophone (M4?). * Screws for geophone to interface plate. * Screws for interface plate to PI. * Find or order geophone items. * Get geophone circuit boards from Okutomi-san. * Find fourth feedthrough * Hassle Miyo-kun for stepper drivers. * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done. * Design final SF ballast masses (Fabian). * Get safety bars moved. * Get air hose connection moved. * Install SR2 booth thermometer and edit macro.txt file. |
=== Tunnel === * Retrieve BNC-Lemo cable from Nakano-kun. * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function. * Install, cable SR3 PI yaw stepper. * Correct flipped connections in SR2 PI LVDTs. * Correct flipped connections in SRM PI LVDTs. * Grab and configure a picomotor driver as SR2_BF 10.68.150.25. * Get independent power supply for SR3 so SR2 can be powered back up. * Check SR2, SR3 TM coil gains for magnet polarity compensation. * Calibrate last six IM OSEMs. * Rebuild filter in PI #1. * Install clamps on PI #1. * Install geophone plates on PI #3. * Install geophone plates on PI #1. * Install correct IP in PI #2. * Rebuild filter in PI #2. * Install clamps on PI #2. * Install LBB blade units on PI #2. * Install geophone plates on PI #2. * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2. === Mitaka or remotely === * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually). * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass. * Set up SR2 Guardian. * Install damping filters for SR2. * Review DAC channel requests. * Set up SR2 Guardian. * Install damping filters for SR2. * Split SRx real-time models? === Ordering === See ../WishList . |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-07-17
Main Sequence
Find LBB damper rods and associated parts.
Check/restore verticality of security structure.
Set SF damper magnet ring height.
Check/correct IP LVDT polarities.
Calibrate IP FR sensing.
Set safety screw and safety nut on F0 keystone; remove Kapton tape.
Set up optical lever.
Check/restore alignment of payload, especially optic pitch.
Do token TFs (time permitting).
Lock F0 keystone.
Lock suspension laterally except for SF level.
Add IM-RM safety bar.
Disconnect all cables at inside of feedthroughs.
Remove top of tank (including service ring).
Set tank jacks to nominal height (50 mm).
Lift suspension.
Install LBB damper rods.
Crane suspension into tank.
Hook LBB damper rods.
Replace tank lid and service ring.
- Remove tank lid leaving service ring.
- Move feedthroughs.
- Move cables over.
- Test cables.
- Calibrate PI LVDT and FR actuation.
- Remove safety bar and unlock suspension.
- Remove First Contact?
- Restore payload alignment, especially pitch.
- Cable geophones.
- Calibrate IP LVDT and FR actuation.
- TFs!
F0/LBB/Tank Stuff
Help Sato-san with swapping IP in PI #2.
Crane IP to second floor.
- Rebuild PI #2 F0.
Software Etc
SR Prep Tasks - To Be Scheduled
Tunnel
- Retrieve BNC-Lemo cable from Nakano-kun.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable SR3 PI yaw stepper.
- Correct flipped connections in SR2 PI LVDTs.
- Correct flipped connections in SRM PI LVDTs.
- Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
- Get independent power supply for SR3 so SR2 can be powered back up.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Calibrate last six IM OSEMs.
- Rebuild filter in PI #1.
- Install clamps on PI #1.
- Install geophone plates on PI #3.
- Install geophone plates on PI #1.
- Install correct IP in PI #2.
- Rebuild filter in PI #2.
- Install clamps on PI #2.
- Install LBB blade units on PI #2.
- Install geophone plates on PI #2.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .