Line 21: | Line 21: |
== 2018-01-15 == * Set up SR2 rack * --(Get more 1-m power cables and connect up remaining boxes.)-- (No orange ones left - used yellow temporarily.) * Run LAN and power cables for stepper drivers. * --(Cable RM OSEMs to rack.)-- * --(Setup QPD and cable to rack.)-- * --(Fix links to OPLEVINF filter screen from chain screen.)-- * --(Initialize gains and matrix elements for SR2 OL.)-- * --(Wash parts for flying saucers.)-- * --(Test nuts for flying saucers.)-- * Order more nuts for flying saucers. * Add DRIVEALIGN button to overview screen. * --(Check sizes and in-stock numbers of screws for geophones.)-- * 20 x M8*35 (need 3*16=48) * 35 x M8*30 (need 3*8=24) * 4 x Viton disks (need 4) * 123 M8 washers (need 3*24=72) * --(Do TFs from RM OSEMS to OL pitch/roll.)-- * --(Make IM OSEMs.)-- * --(Install load gauge adapter.)-- * --(Lift IM/RM/SR with LGA, check/adjust total mass and pitch/yaw balance.)-- * --(Crane in BF.)-- * --(Install BF-IRM rods and top plate of IRM.)-- * --(Install BF-IM rod with flying saucer.)-- * --(Hook IM.)-- * --(Route cables via flying saucer up to under BF.)-- |
== 2018-02-13 == * --(Test FR stepper.)-- * --(Set up watchdog.)-- * --(Calibrate FR actuation.)-- * --(Calibrate LVDT actuation.)-- * --(Add IRM side panels.)-- * --(Add IM OSEMs and flags.)-- * --(Adjust IRM and lateral position of OSEMs.)-- * --(Cable IM OSEMs.)-- * --(Set gains and offsets in IM OSEMINF screens.)-- * --(Set OSEM2EUL matrices.)-- * --(Center IM OSEMs in/out.)-- * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. -> next week |
Line 48: | Line 35: |
== 2018-01-22 == * —(Debug keystone issue.)— * Cable yaw pico and LVDT on new BF. * Calibrate LVDT on new BF. * Adjust IM/RM/SR total mass and pitch/roll balance. * Test IM picos. * Prepare SR3 area for PI test. * Check BF yaw pico. |
==== Plan for week of 2/19 ==== * Recover from power outage. * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. * Add BF cap. * Lift BF/... section with LGA. * Check/adjust total mass and balance. * Cable and test BF picos. * Anchor cables to BF cap. * Add AF crossbars for under SF. * Build up SS to SF ring. * Bring in SF. * Remove SF cap. * Hook BF/... section. * Route cables up to under SF. * Check/adjust total mass of BF/... section. * Cable SF LVDT. * Calibrate SF LVDT. * Cable SF FR. * Test/calibrate SF FR. * Add SF cap. * Add Cu segments to SF cap. * Lift SF/... with LGA and check weight/balance. |
Line 57: | Line 58: |
== 2018-01-28 == * Install IRM. * Adjust IM OSEMs. * Cable IM OSEMs. * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. * Install pre-calculated BF trim mass. * Lift * Find in-vac cables: * 1 x Type 3-2m * 5 x Type 1-2m |
<<Anchor(SRPrepTasks)>> == SR Prep Tasks - To Be Scheduled == |
Line 73: | Line 66: |
<<Anchor(SRPrepTasks)>> == SR Prep Tasks - To Be Scheduled == * Replace temporary yellow DC power cables in SR2 rack with orange ones. |
|
Line 80: | Line 68: |
* --(Cu O-rings for pod (two sizes).)-- * Viton O-ring for under geophone. * Screws for immobilizing geophone (M4?). |
|
Line 88: | Line 73: |
* Hassle Miyo-kun for stepper drivers. | |
Line 93: | Line 77: |
* Install SR2 booth thermometer and edit macro.txt file. | * Glue SR3. * Set up SR3 rack. * Set up SRM rack. * Rebuild two BFs. * Disassemble two top filters. * Rebuild three top filters. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2018-02-13
Test FR stepper.
Set up watchdog.
Calibrate FR actuation.
Calibrate LVDT actuation.
Add IRM side panels.
Add IM OSEMs and flags.
Adjust IRM and lateral position of OSEMs.
Cable IM OSEMs.
Set gains and offsets in IM OSEMINF screens.
Set OSEM2EUL matrices.
Center IM OSEMs in/out.
Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. -> next week
Plan for week of 2/19
- Recover from power outage.
- Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
- Add BF cap.
- Lift BF/... section with LGA.
- Check/adjust total mass and balance.
- Cable and test BF picos.
- Anchor cables to BF cap.
- Add AF crossbars for under SF.
- Build up SS to SF ring.
- Bring in SF.
- Remove SF cap.
- Hook BF/... section.
- Route cables up to under SF.
- Check/adjust total mass of BF/... section.
- Cable SF LVDT.
- Calibrate SF LVDT.
- Cable SF FR.
- Test/calibrate SF FR.
- Add SF cap.
- Add Cu segments to SF cap.
- Lift SF/... with LGA and check weight/balance.
SR Prep Tasks - To Be Scheduled
- Review Shoda-san's Guardian.
- Decide if we're really going to renumber IP channels.
- Review DIO stuff.
- Review SR2 model (especially screens, macro text file).
- Review DAC channel requests.
- Find out (from Takahashi-san) specifications for geophone pod items:
- Screws for pod (cap-neck and neck-body).
- Screws for geophone to interface plate.
- Screws for interface plate to PI.
- Find or order geophone items.
- Get geophone circuit boards from Okutomi-san.
- Find fourth feedthrough
- Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
- Design final SF ballast masses (Fabian).
- Get safety bars moved.
- Get air hose connection moved.
- Glue SR3.
- Set up SR3 rack.
- Set up SRM rack.
- Rebuild two BFs.
- Disassemble two top filters.
- Rebuild three top filters.