== Coming Weeks ==
=== 2018-04-23 ===
==== Main Sequence ====
 * Get 8xM8x40 screws for feedthroughs.
 * Attach feedthroughs to AF.
 * Get LVDT driver with one good and one bad card for Tanaka-san.
 * Start SR3 Hang
  * Find wires, wire clamp items.
  * Install winch system.
  * Move KOACH filters, mirror box and table to near AF.
  * Hang optic.
  * Set up OL.
  * Set optic pitch.
  * Hang RM.
  * Cable RM OSEMs.
Line 21: Line 36:
== 2018-01-15 ==
 * Set up SR2 rack
  * --(Get more 1-m power cables and connect up remaining boxes.)-- (No orange ones left - used yellow temporarily.)
  * Run LAN and power cables for stepper drivers.
 * --(Cable RM OSEMs to rack.)--
 * --(Setup QPD and cable to rack.)--
 * --(Fix links to OPLEVINF filter screen from chain screen.)--
 * --(Initialize gains and matrix elements for SR2 OL.)--
 * --(Wash parts for flying saucers.)--
 * --(Test nuts for flying saucers.)--
 * Order more nuts for flying saucers.
 * Add DRIVEALIGN button to overview screen.
 * --(Check sizes and in-stock numbers of screws for geophones.)--
  * 20 x M8*35 (need 3*16=48)
  * 35 x M8*30 (need 3*8=24)
  * 4 x Viton disks (need 4)
  * 123 M8 washers (need 3*24=72)
 * --(Do TFs from RM OSEMS to OL pitch/roll.)--
 * --(Make IM OSEMs.)--
 * --(Install load gauge adapter.)--
 * --(Lift IM/RM/SR with LGA, check/adjust total mass and pitch/yaw balance.)--
 * --(Crane in BF.)--
 * --(Install BF-IRM rods and top plate of IRM.)--
 * --(Install BF-IM rod with flying saucer.)--
 * --(Hook IM.)--
 * --(Route cables via flying saucer up to under BF.)--
==== F0/LBB Stuff ====
 * Clean parts (cable clamp bases, etc, etc; Hirata-san@Mitaka).
 * Top filter disassembly (if any spare time)
 * Prepare F0 workspace in SRM area (if any spare time)
Line 48: Line 41:
== 2018-01-22 ==
 * —(Debug keystone issue.)—
 * Cable yaw pico and LVDT on new BF.
 * Calibrate LVDT on new BF.
 * Adjust IM/RM/SR total mass and pitch/roll balance.
 * Test IM picos.
 * Prepare SR3 area for PI test.
 * Check BF yaw pico.
=== 2018-04-30 ===
 * Golden Week!
 * Uso!
 * BS TFs (4/30 or TBD).
 * Observe/assist with bKAGRA Phase 1.
Line 57: Line 47:
== 2018-01-28 ==
 * Install IRM.
 * Adjust IM OSEMs.
 * Cable IM OSEMs.
 * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
 * Install pre-calculated BF trim mass.
 * Lift
== 2018-05-07 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
 * Prepare F0 workspace in SRM area
 * Disassemble F0 #1 and #3
 * Temporarily raise F0 #3 (in SRM) and remove floor panel
 * Start characterization of LBB blades (should have by 4/30)
Line 65: Line 55:
 * Find in-vac cables:
  * 1 x Type 3-2m
  * 5 x Type 1-2m
 * Review Shoda-san's Guardian.
 * Decide if we're really going to renumber IP channels.
 * Review DIO stuff.
 * Review SR2 model (especially screens, macro text file).
 * Review DAC channel requests.
== 2018-05-14 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-05-21 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
 * Final prep for F0 prototype blade test (5/14)
 * F0 prototype blade test with Takahashi-san (5/15 or TBD)
== 2018-05-28 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-06-04 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-06-11 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-06-18 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-06-25 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-07-02 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-07-09 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-07-16 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-07-23 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
Line 77: Line 104:
 * Replace temporary yellow DC power cables in SR2 rack with orange ones.
 * Find out (from Takahashi-san) specifications for geophone pod items:
  * Screws for pod (cap-neck and neck-body).
  * --(Cu O-rings for pod (two sizes).)--
  * Viton O-ring for under geophone.
  * Screws for immobilizing geophone (M4?).
  * Screws for geophone to interface plate.
  * Screws for interface plate to PI.
 * Find or order geophone items.
 * Get geophone circuit boards from Okutomi-san.
 * Find fourth feedthrough
 * Hassle Miyo-kun for stepper drivers.
 * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
 * Design final SF ballast masses (Fabian).
 * Get safety bars moved.
 * Get air hose connection moved.
 * Install SR2 booth thermometer and edit macro.txt file.
=== Tunnel ===
 * Get SRM mushroom installed.
 * --(Find 4 more feedthroughs for SRM.)--
 * Install first set of LBB damper rings in SR2 (or SR3?) tank.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
 * Finish half-completed geophones.
 * Characterize top filter prototype blades.
 * Decide final top filter blade parameters and order.
 * Rebuild three top filters.
 * Do buoyancy calculation (see LIGO-T1100616).
=== Mitaka or remotely ===
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
 * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
 * Set up SR2 Guardian.
 * Install damping filters for SR2.
 * Review Shoda-san's Guardian.
 * Review DIO stuff.
 * Review DAC channel requests.
 * Set up SR2 and SR3 Guardian.
 * Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
 * Install damping filters for SR2.
=== Ordering ===
See ../WishList .

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-04-23

Main Sequence

  • Get 8xM8x40 screws for feedthroughs.
  • Attach feedthroughs to AF.
  • Get LVDT driver with one good and one bad card for Tanaka-san.
  • Start SR3 Hang
    • Find wires, wire clamp items.
    • Install winch system.
    • Move KOACH filters, mirror box and table to near AF.
    • Hang optic.
    • Set up OL.
    • Set optic pitch.
    • Hang RM.
    • Cable RM OSEMs.

F0/LBB Stuff

  • Clean parts (cable clamp bases, etc, etc; Hirata-san@Mitaka).
  • Top filter disassembly (if any spare time)
  • Prepare F0 workspace in SRM area (if any spare time)

2018-04-30

  • Golden Week!
  • Uso!
  • BS TFs (4/30 or TBD).
  • Observe/assist with bKAGRA Phase 1.

2018-05-07

Main Sequence

F0/LBB Stuff

  • Prepare F0 workspace in SRM area
  • Disassemble F0 #1 and #3
  • Temporarily raise F0 #3 (in SRM) and remove floor panel
  • Start characterization of LBB blades (should have by 4/30)

2018-05-14

Main Sequence

F0/LBB Stuff

2018-05-21

Main Sequence

F0/LBB Stuff

  • Final prep for F0 prototype blade test (5/14)
  • F0 prototype blade test with Takahashi-san (5/15 or TBD)

2018-05-28

Main Sequence

F0/LBB Stuff

2018-06-04

Main Sequence

F0/LBB Stuff

2018-06-11

Main Sequence

F0/LBB Stuff

2018-06-18

Main Sequence

F0/LBB Stuff

2018-06-25

Main Sequence

F0/LBB Stuff

2018-07-02

Main Sequence

F0/LBB Stuff

2018-07-09

Main Sequence

F0/LBB Stuff

2018-07-16

Main Sequence

F0/LBB Stuff

2018-07-23

Main Sequence

F0/LBB Stuff

SR Prep Tasks - To Be Scheduled

Tunnel

  • Get SRM mushroom installed.
  • Find 4 more feedthroughs for SRM.

  • Install first set of LBB damper rings in SR2 (or SR3?) tank.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • Finish half-completed geophones.
  • Characterize top filter prototype blades.
  • Decide final top filter blade parameters and order.
  • Rebuild three top filters.
  • Do buoyancy calculation (see LIGO-T1100616).

Mitaka or remotely

  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review Shoda-san's Guardian.
  • Review DIO stuff.
  • Review DAC channel requests.
  • Set up SR2 and SR3 Guardian.
  • Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
  • Install damping filters for SR2.

Ordering

See ../WishList .