Differences between revisions 36 and 122 (spanning 86 versions)
Revision 36 as of 2018-02-02 10:54:10
Size: 2032
Editor: MarkBarton
Comment:
Revision 122 as of 2018-11-08 16:59:25
Size: 3411
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 13: Line 13:
=== Facilities === ==== Facilities ====
Line 15: Line 15:
 * Wipe ladders.  * Wipe ladders, assembly frame.
Line 20: Line 20:
== Coming Weeks ==
Line 21: Line 22:
== 2018-02-05 ==
 * Make in-air pico adapter cables.
 * Cable yaw pico and LVDT on new BF.
 * Calibrate LVDT.
 * Test IM picos and BF yaw pico.
 * Test FR.
 * Install ballast mass in BF.
 * Build IRM around IM.
=== 2018-11-05 ===
==== SRM (top priority) ====
 * Etc
  * --(Solder more cables.)--
  * --(Ultrasonically clean more cables.)--
  * --(Work out optimum LPCD output resistance; get one box modified.)--
  * Work out how to change LPCD watchdog threshold; get one box modified.
 * LBB
  * --(Lay out LBB damper ring pieces near tank.)--
  * Put magnets on LBB magnet ring.
  * Move KOACH filters
  * Put LBB damper rings in tank.
 * Main sequence
  * --(Run DC power and network to SRM_IP stepper driver.)--
  * --(Add all steppers and picos to driver list and MEDM screens.)--
  * --(Prepare SF magnet ring.)--
  * --(Install #353 poles)--
  * --(Move NB-03 jacks down; disassemble top of AF.)--
  * --(Crane PI into AF.)--
  * --(Install F0-SF rod (#331) and flying saucer.)--
  * --(Route SF/... cables up to underside of F0.)--
  * --(Install weaker CuBe spring.)--
  * --(Add SF trim mass to leave 1.2 kg margin.)--
  * --(Tweak BF trim mass to compensate for new cables.)--
  * --(Measure bounce frequencies.)--
  * Do vertical height budget.
  
==== SR2 (low priority) ====
 * --(Unclamp LBB ring sandwich.)--
 * --(Set LBB receptacles to CAD positions.)--
 * --(Remove spacers; get LBB hanging.)--
Line 30: Line 54:
== 2018-02-13 ==
 * Cable/test/adjust IM OSEMs.
 * Cable IM OSEMs.
 * Adjust IM OSEMs.
 * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
 * Install pre-calculated BF trim mass.

==== Plan for week of 2/19 ====
 * Lift BF/... section and check total mass and balance.
 * Cable and test BF picos.
 * Add section of SS up to SF ring.
 * Bring in SF.
 * Add Cu segments to SF cap.
 * Hook BF/... section.
 * Route cables up to under SF.
 * Check/adjust total mass of BF/... section.

 
=== 2018-11-12 ===
==== SRM ====
 * LBB
  * Crane LBB ring sandwich to top of tank.
  * Set tank jacks to nominal height.
 * Main sequence
  * Cable/test IP LVDTs.
  * Cable/test IP FRs.
  * Unlock IP and center roughly.
  * Calibrate IP LVDTs.
  * Check/adjust alignment of SS.
  * Add arc weights and geophones (or extra mass equivalent to geophones).
  * Cable/test geophones.
  * Improve centering/tuning of IP and SS alignment.
==== SR2 (low priority) ====
 * Set up OL pillar and shelf (with Akutsu-san).
 * Set up OL cabling.
 * Set up OL.
Line 52: Line 76:
 * Review Shoda-san's Guardian.
 * Decide if we're really going to renumber IP channels.
 * Review DIO stuff.
 * Review SR2 model (especially screens, macro text file).
=== Tunnel ===
  * Check which LVDT cards are in which boxes.
 * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
 * Install, cable PI yaw steppers.
 * Correct flipped connections in SRM PI LVDTs.
 * Check SR2, SR3 TM coil gains for magnet polarity compensation.
 * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

=== Mitaka or remotely ===
 * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
 * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
 * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
 * Install damping filters for SR2.
Line 57: Line 91:
 * Find out (from Takahashi-san) specifications for geophone pod items:
  * Screws for pod (cap-neck and neck-body).
  * Screws for geophone to interface plate.
  * Screws for interface plate to PI.
 * Find or order geophone items.
 * Get geophone circuit boards from Okutomi-san.
 * Find fourth feedthrough
 * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
 * Design final SF ballast masses (Fabian).
 * Get safety bars moved.
 * Get air hose connection moved.
 * Glue SR3.
 * Set up SR3 rack.
 * Set up SRM rack.
 * Rebuild two BFs.
 * Disassemble two top filters.
 * Rebuild three top filters.
 * Set up SR2 Guardian.
 * Install damping filters for SR2.
 * Split SRx real-time models?

=== Ordering ===
See ../WishList .

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders, assembly frame.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-11-05

SRM (top priority)

  • Etc
    • Solder more cables.

    • Ultrasonically clean more cables.

    • Work out optimum LPCD output resistance; get one box modified.

    • Work out how to change LPCD watchdog threshold; get one box modified.
  • LBB
    • Lay out LBB damper ring pieces near tank.

    • Put magnets on LBB magnet ring.
    • Move KOACH filters
    • Put LBB damper rings in tank.
  • Main sequence
    • Run DC power and network to SRM_IP stepper driver.

    • Add all steppers and picos to driver list and MEDM screens.

    • Prepare SF magnet ring.

    • Install #353 poles

    • Move NB-03 jacks down; disassemble top of AF.

    • Crane PI into AF.

    • Install F0-SF rod (#331) and flying saucer.

    • Route SF/... cables up to underside of F0.

    • Install weaker CuBe spring.

    • Add SF trim mass to leave 1.2 kg margin.

    • Tweak BF trim mass to compensate for new cables.

    • Measure bounce frequencies.

    • Do vertical height budget.

SR2 (low priority)

  • Unclamp LBB ring sandwich.

  • Set LBB receptacles to CAD positions.

  • Remove spacers; get LBB hanging.

2018-11-12

SRM

  • LBB
    • Crane LBB ring sandwich to top of tank.
    • Set tank jacks to nominal height.
  • Main sequence
    • Cable/test IP LVDTs.
    • Cable/test IP FRs.
    • Unlock IP and center roughly.
    • Calibrate IP LVDTs.
    • Check/adjust alignment of SS.
    • Add arc weights and geophones (or extra mass equivalent to geophones).
    • Cable/test geophones.
    • Improve centering/tuning of IP and SS alignment.

SR2 (low priority)

  • Set up OL pillar and shelf (with Akutsu-san).
  • Set up OL cabling.
  • Set up OL.

SR Prep Tasks - To Be Scheduled

Tunnel

  • Check which LVDT cards are in which boxes.
  • Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
  • Install, cable PI yaw steppers.
  • Correct flipped connections in SRM PI LVDTs.
  • Check SR2, SR3 TM coil gains for magnet polarity compensation.
  • Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

Mitaka or remotely

  • Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
  • Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Install damping filters for SR2.
  • Review DAC channel requests.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Split SRx real-time models?

Ordering

See ../WishList .

KAGRA/Subgroups/VIS/TypeB/ToDoSR (last edited 2019-01-04 15:25:56 by MarkBarton)