Line 13: | Line 13: |
=== Facilities === | ==== Facilities ==== |
Line 15: | Line 15: |
* Wipe ladders. | * Wipe ladders, assembly frame. |
Line 20: | Line 20: |
== Coming Weeks == | |
Line 21: | Line 22: |
== 2018-02-05 == * --(Make in-air pico adapter cables.)-- * Label in-air pico adapter cables. * Cable IM picos through to driver. * Cable GAS LVDT through to driver. * Check LVDT resistances and inductances at various points from coils to rack. * Cable BF FR stepper through to driver. * Calibrate LVDT. * Test IM picos and BF yaw pico. * Test FR. * Install ballast mass in BF. * Build IRM around IM. * Check PR3 area for Ø10x10 IM flag magnets. |
=== 2018-11-12 === ==== SRM ==== * Characterize geophones. * Go/no-go test of all electronics items, especially SF/... section. * Do vertical height budget. * Disconnect SS from AF. * Raise PI on jacks. * Remove any remaining cable ties from SRM IP * Unlock IP and center roughly. * Check/adjust alignment of SS. * Calibrate IP LVDTs. * Add arc weights and geophones. * Test geophones. * Improve centering/tuning of IP and SS alignment. * Disconnect cables. * Crane into tank. |
Line 35: | Line 39: |
== 2018-02-13 == * Cable/test/adjust IM OSEMs. * Cable IM OSEMs. * Adjust IM OSEMs. * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. * Install pre-calculated BF trim mass. |
==== SR2 (low priority) ==== * Set up OL pillar, shelf and viewports (with Akutsu-san, Tue evening, 11/20). * Set up OL cabling. * Set up OL. * Assist MIF team with pico cables, LBB ballast. |
Line 42: | Line 45: |
==== Plan for week of 2/19 ==== * Lift BF/... section and check total mass and balance. * Cable and test BF picos. * Add section of SS up to SF ring. * Bring in SF. * Add Cu segments to SF cap. * Hook BF/... section. * Route cables up to under SF. * Check/adjust total mass of BF/... section. |
=== 2018-11-19 === ==== SRM ==== * Make new geophones. * Cable/test geophones. * Disconnect cables. * Remove crossbars. * Crane suspension into tank. |
Line 52: | Line 53: |
==== SR2 (not so low priority) ==== * Set up OL pillar and shelf (with Akutsu-san). * Set up OL cabling. * Set up OL. * Add more arc weights and tweak IP centering. * Replace two borrowed geophones. * Remove tape, writing etc on PI and PI items. * Add new feedthrough to lower part of tank (with Izumi-san-tachi). * Install cable for MIF pico on LBB (with Izumi-san-tachi). * Add ballast mass to LBB. * Install manual yaw adjuster. * Get top plate reduced? |
|
Line 57: | Line 69: |
* Review Shoda-san's Guardian. * Decide if we're really going to renumber IP channels. * Review DIO stuff. * Review SR2 model (especially screens, macro text file). |
=== Tunnel === * Check which LVDT cards are in which boxes. * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function. * Install, cable PI yaw steppers. * Correct flipped connections in SRM PI LVDTs. * Check SR2, SR3 TM coil gains for magnet polarity compensation. * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2. === Mitaka or remotely === * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually). * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass. * Install damping filters for SR2. |
Line 62: | Line 84: |
* Find out (from Takahashi-san) specifications for geophone pod items: * Screws for pod (cap-neck and neck-body). * Screws for geophone to interface plate. * Screws for interface plate to PI. * Find or order geophone items. * Get geophone circuit boards from Okutomi-san. * Find fourth feedthrough * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done. * Design final SF ballast masses (Fabian). * Get safety bars moved. * Get air hose connection moved. * Glue SR3. * Set up SR3 rack. * Set up SRM rack. * Rebuild two BFs. * Disassemble two top filters. * Rebuild three top filters. |
* Set up SR2 Guardian. * Install damping filters for SR2. * Split SRx real-time models? === Ordering === See ../WishList . |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-11-12
SRM
- Characterize geophones.
- Go/no-go test of all electronics items, especially SF/... section.
- Do vertical height budget.
- Disconnect SS from AF.
- Raise PI on jacks.
- Remove any remaining cable ties from SRM IP
- Unlock IP and center roughly.
- Check/adjust alignment of SS.
- Calibrate IP LVDTs.
- Add arc weights and geophones.
- Test geophones.
- Improve centering/tuning of IP and SS alignment.
- Disconnect cables.
- Crane into tank.
SR2 (low priority)
- Set up OL pillar, shelf and viewports (with Akutsu-san, Tue evening, 11/20).
- Set up OL cabling.
- Set up OL.
- Assist MIF team with pico cables, LBB ballast.
2018-11-19
SRM
- Make new geophones.
- Cable/test geophones.
- Disconnect cables.
- Remove crossbars.
- Crane suspension into tank.
SR2 (not so low priority)
- Set up OL pillar and shelf (with Akutsu-san).
- Set up OL cabling.
- Set up OL.
- Add more arc weights and tweak IP centering.
- Replace two borrowed geophones.
- Remove tape, writing etc on PI and PI items.
- Add new feedthrough to lower part of tank (with Izumi-san-tachi).
- Install cable for MIF pico on LBB (with Izumi-san-tachi).
- Add ballast mass to LBB.
- Install manual yaw adjuster.
- Get top plate reduced?
SR Prep Tasks - To Be Scheduled
Tunnel
- Check which LVDT cards are in which boxes.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable PI yaw steppers.
- Correct flipped connections in SRM PI LVDTs.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .