2308
Comment:
|
3435
|
Deletions are marked like this. | Additions are marked like this. |
Line 13: | Line 13: |
=== Facilities === | ==== Facilities ==== |
Line 15: | Line 15: |
* Wipe ladders. | * Wipe ladders, assembly frame. |
Line 20: | Line 20: |
== Coming Weeks == | |
Line 21: | Line 22: |
== 2018-02-05 == * --(Check PR3 area for Ø10x10 IM flag magnets.)-- * --(Make in-air pico adapter cables.)-- * --(Label in-air pico adapter cables.)-- * Cable IM picos through to driver. * --(Cable BF LVDT through to driver.)-- * --(Check LVDT resistances and inductances at various points from coils to rack.)-- * Cable BF FR stepper through to driver. * Calibrate LVDT. * Test IM picos and BF yaw pico. * Test FR. * Install ballast mass in BF. * Build IRM around IM. |
=== 2018-07-09 === ==== Main Sequence ==== * Find LBB damper rods and associated parts. * Set tank jacks to nominal height (50 mm). * Check/restore verticality of security structure. * Set SF damper magnet ring height. * Calibrate F0 LVDT actuation and FR. * Calibrate PI LVDTs and FRs. * Cable geophones (temporary routing OK). * Set up optical lever. * Check/restore alignment of payload, especially optic pitch. * Do token TFs (time permitting). * Reset all PI FRs to midrange. * Lock F0 keystone. * Lock suspension laterally except for SF level. * Add IM-RM safety bar? * Disconnect all cables at inside of feedthroughs. * Find LBB damper rods and associated parts. * Remove top of tank (including service ring). * Set tank jacks to nominal height (50 mm). * Lift suspension. * Install LBB damper rods. * Crane suspension into tank. * Hook LBB damper rods. * Replace tank lid and service ring. * Remove tank lid leaving service ring. * Move feedthroughs. * Move cables over. * Remove safety bar and unlock suspension. * Remove First Contact? * Restore payload alignment, especially pitch. * TFs! |
Line 35: | Line 55: |
== 2018-02-13 == * Cable/test/adjust IM OSEMs. * Cable IM OSEMs. * Adjust IM OSEMs. * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. * Install pre-calculated BF trim mass. |
==== F0/LBB/Tank Stuff ==== * Add LBB ballast masses. * Help Sato-san with swapping IP in PI #2. * Crane IP to second floor. * Rebuild PI #2 F0. |
Line 42: | Line 61: |
==== Plan for week of 2/19 ==== * Lift BF/... section and check total mass and balance. * Cable and test BF picos. * Add section of SS up to SF ring. * Bring in SF. * Add Cu segments to SF cap. * Hook BF/... section. * Route cables up to under SF. * Check/adjust total mass of BF/... section. |
==== Software Etc ==== |
Line 57: | Line 66: |
* Review Shoda-san's Guardian. * Decide if we're really going to renumber IP channels. * Review DIO stuff. * Review SR2 model (especially screens, macro text file). |
=== Tunnel === * Retrieve BNC-Lemo cable from Nakano-kun. * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function. * Install, cable SR3 PI yaw stepper. * Correct flipped connections in SR2 PI LVDTs. * Correct flipped connections in SRM PI LVDTs. * Grab and configure a picomotor driver as SR2_BF 10.68.150.25. * Get independent power supply for SR3 so SR2 can be powered back up. * Check SR2, SR3 TM coil gains for magnet polarity compensation. * Calibrate last six IM OSEMs. * Rebuild filter in PI #1. * Install clamps on PI #1. * Install geophone plates on PI #3. * Install geophone plates on PI #1. * Install correct IP in PI #2. * Rebuild filter in PI #2. * Install clamps on PI #2. * Install LBB blade units on PI #2. * Install geophone plates on PI #2. === Mitaka or remotely === * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually). * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass. * Set up SR2 Guardian. * Install damping filters for SR2. |
Line 62: | Line 94: |
* Find out (from Takahashi-san) specifications for geophone pod items: * Screws for pod (cap-neck and neck-body). * Screws for geophone to interface plate. * Screws for interface plate to PI. * Find or order geophone items. * Get geophone circuit boards from Okutomi-san. * Find fourth feedthrough * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done. * Design final SF ballast masses (Fabian). * Get safety bars moved. * Get air hose connection moved. * Glue SR3. * Set up SR3 rack. * Set up SRM rack. * Rebuild two BFs. * Disassemble two top filters. * Rebuild three top filters. |
* Set up SR2 Guardian. * Install damping filters for SR2. * Split SRx real-time models? === Ordering === See ../WishList . |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-07-09
Main Sequence
- Find LBB damper rods and associated parts.
- Set tank jacks to nominal height (50 mm).
- Check/restore verticality of security structure.
- Set SF damper magnet ring height.
- Calibrate F0 LVDT actuation and FR.
- Calibrate PI LVDTs and FRs.
- Cable geophones (temporary routing OK).
- Set up optical lever.
- Check/restore alignment of payload, especially optic pitch.
- Do token TFs (time permitting).
- Reset all PI FRs to midrange.
- Lock F0 keystone.
- Lock suspension laterally except for SF level.
- Add IM-RM safety bar?
- Disconnect all cables at inside of feedthroughs.
- Find LBB damper rods and associated parts.
- Remove top of tank (including service ring).
- Set tank jacks to nominal height (50 mm).
- Lift suspension.
- Install LBB damper rods.
- Crane suspension into tank.
- Hook LBB damper rods.
- Replace tank lid and service ring.
- Remove tank lid leaving service ring.
- Move feedthroughs.
- Move cables over.
- Remove safety bar and unlock suspension.
- Remove First Contact?
- Restore payload alignment, especially pitch.
- TFs!
F0/LBB/Tank Stuff
- Add LBB ballast masses.
- Help Sato-san with swapping IP in PI #2.
- Crane IP to second floor.
- Rebuild PI #2 F0.
Software Etc
SR Prep Tasks - To Be Scheduled
Tunnel
- Retrieve BNC-Lemo cable from Nakano-kun.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable SR3 PI yaw stepper.
- Correct flipped connections in SR2 PI LVDTs.
- Correct flipped connections in SRM PI LVDTs.
- Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
- Get independent power supply for SR3 so SR2 can be powered back up.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Calibrate last six IM OSEMs.
- Rebuild filter in PI #1.
- Install clamps on PI #1.
- Install geophone plates on PI #3.
- Install geophone plates on PI #1.
- Install correct IP in PI #2.
- Rebuild filter in PI #2.
- Install clamps on PI #2.
- Install LBB blade units on PI #2.
- Install geophone plates on PI #2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .