Differences between revisions 40 and 96 (spanning 56 versions)
Revision 40 as of 2018-02-09 08:30:38
Size: 2402
Editor: MarkBarton
Comment:
Revision 96 as of 2018-09-01 14:51:25
Size: 3353
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 13: Line 13:
=== Facilities === ==== Facilities ====
Line 15: Line 15:
 * Wipe ladders.  * Wipe ladders, assembly frame.
Line 20: Line 20:
== Coming Weeks ==
Line 21: Line 22:
== 2018-02-05 ==
 * --(Check PR3 area for Ø10x10 IM flag magnets.)--
 * --(Make in-air pico adapter cables.)--
 * --(Label in-air pico adapter cables.)--
 * --(Cable IM picos through to driver.)--
 * --(Cable BF LVDT through to driver.)--
 * --(Check LVDT resistances and inductances at various points from coils to rack.)--
 * Cable BF FR stepper through to driver.
 * --(Calibrate LVDT.)--
 * Test IM picos and BF yaw pico.
 * Test FR.
 * --(Install ballast mass in BF.)--
 * Remove stuff from changing area in preparation for installing SS sheet.
=== 2018-09-03 ===
==== Etc ====
 * Check SR2-SR3 duct (since Mirapro moved it) to see if we have adequate space at both ends.
 * Help crane inspectors on Monday and Wednesday mornings.
 * Shut down all electronics before leaving on Friday.
 * Update electronics items lists to reflect removed ADC stuff.
 * Inspect all crane slot curtains (SR, BS, PR), note which are missing, and decide which should be closed up immediately versus later. (For example, SR2 and SR3 have missing curtains that could be replaced semi-permanently because we probably don't need to crane stuff into those areas anymore.)
Line 35: Line 30:
== 2018-02-13 ==
 * Build IRM around IM.
 * Cable/test/adjust IM OSEMs.
 * Cable IM OSEMs.
 * Adjust IM OSEMs.
 * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
 * Install pre-calculated BF trim mass.
==== SR2 (highest priority) ====
 * Cable/test PI items (LVDTs, steppers, geophones).
 * Finish in-air cabling.
 * Do basic go/no-go test of electronic items.
 * Adjust ballast/trim mass of SF, with reserve for yaw stepper.
 * Check alignment of chain and security structure.
 * Center all IP FRs.
 * Add arc weights and geophones and center IP.
 * Set damper height.
 * Crane suspension into tank
 
==== SRM (as time permits) ====
 * Set up pitch-setting OL.
 * Add TM OSEM cables.
 * Set TM pitch and tighten clamps.
 * Set RM pitch and tighten clamps.
 * Remove winch system and restore items removed from top of IM.
 * Install feedthroughs on AF.
 * Fire up SRM rack.
Line 43: Line 50:
==== Plan for week of 2/19 ====
 * Lift BF/... section and check total mass and balance.
 * Cable and test BF picos.
 * Add section of SS up to SF ring.
 * Bring in SF.
 * Add Cu segments to SF cap.
 * Hook BF/... section.
 * Route cables up to under SF.
 * Check/adjust total mass of BF/... section.
==== SR3 ====
Line 58: Line 57:
 * Review Shoda-san's Guardian.
 * Decide if we're really going to renumber IP channels.
 * Review DIO stuff.
 * Review SR2 model (especially screens, macro text file).
=== Tunnel ===
 * Add SR3 LBB ballast mass.
 * Install SR3 LEN OL.
 * Rebuild PI #2 F0 for SRM.
 * Retrieve BNC-Lemo cable from Nakano-kun.
 * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
 * Install, cable SR3 PI yaw stepper.
 * Correct flipped connections in SRM PI LVDTs.
 * Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
 * Check SR2, SR3 TM coil gains for magnet polarity compensation.
 * Calibrate last six IM OSEMs.
 * Install geophone plates on PI #1 for SR2.
 * Rebuild filter in PI #2 for SRM.
 * Install clamps on PI #2 for SRM.
 * Install LBB blade units on PI #2 for SRM.
 * Install geophone plates on PI #2 for SRM.
 * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

=== Mitaka or remotely ===
 * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
 * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
 * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
 * Set up SR2 Guardian.
 * Install damping filters for SR2.
Line 63: Line 83:
 * Find out (from Takahashi-san) specifications for geophone pod items:
  * Screws for pod (cap-neck and neck-body).
  * Screws for geophone to interface plate.
  * Screws for interface plate to PI.
 * Find or order geophone items.
 * Get geophone circuit boards from Okutomi-san.
 * Find fourth feedthrough
 * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
 * Design final SF ballast masses (Fabian).
 * Get safety bars moved.
 * Get air hose connection moved.
 * Glue SR3.
 * Set up SR3 rack.
 * Set up SRM rack.
 * Rebuild two BFs.
 * Disassemble two top filters.
 * Rebuild three top filters.
 * Set up SR2 Guardian.
 * Install damping filters for SR2.
 * Split SRx real-time models?

=== Ordering ===
See ../WishList .

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders, assembly frame.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-09-03

Etc

  • Check SR2-SR3 duct (since Mirapro moved it) to see if we have adequate space at both ends.
  • Help crane inspectors on Monday and Wednesday mornings.
  • Shut down all electronics before leaving on Friday.
  • Update electronics items lists to reflect removed ADC stuff.
  • Inspect all crane slot curtains (SR, BS, PR), note which are missing, and decide which should be closed up immediately versus later. (For example, SR2 and SR3 have missing curtains that could be replaced semi-permanently because we probably don't need to crane stuff into those areas anymore.)

SR2 (highest priority)

  • Cable/test PI items (LVDTs, steppers, geophones).
  • Finish in-air cabling.
  • Do basic go/no-go test of electronic items.
  • Adjust ballast/trim mass of SF, with reserve for yaw stepper.
  • Check alignment of chain and security structure.
  • Center all IP FRs.
  • Add arc weights and geophones and center IP.
  • Set damper height.
  • Crane suspension into tank

SRM (as time permits)

  • Set up pitch-setting OL.
  • Add TM OSEM cables.
  • Set TM pitch and tighten clamps.
  • Set RM pitch and tighten clamps.
  • Remove winch system and restore items removed from top of IM.
  • Install feedthroughs on AF.
  • Fire up SRM rack.

SR3

SR Prep Tasks - To Be Scheduled

Tunnel

  • Add SR3 LBB ballast mass.
  • Install SR3 LEN OL.
  • Rebuild PI #2 F0 for SRM.
  • Retrieve BNC-Lemo cable from Nakano-kun.
  • Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
  • Install, cable SR3 PI yaw stepper.
  • Correct flipped connections in SRM PI LVDTs.
  • Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
  • Check SR2, SR3 TM coil gains for magnet polarity compensation.
  • Calibrate last six IM OSEMs.
  • Install geophone plates on PI #1 for SR2.
  • Rebuild filter in PI #2 for SRM.
  • Install clamps on PI #2 for SRM.
  • Install LBB blade units on PI #2 for SRM.
  • Install geophone plates on PI #2 for SRM.
  • Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

Mitaka or remotely

  • Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
  • Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review DAC channel requests.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Split SRx real-time models?

Ordering

See ../WishList .

KAGRA/Subgroups/VIS/TypeB/ToDoSR (last edited 2019-01-04 15:25:56 by MarkBarton)