Differences between revisions 44 and 46 (spanning 2 versions)
Revision 44 as of 2018-02-16 11:29:24
Size: 2371
Editor: MarkBarton
Comment:
Revision 46 as of 2018-03-02 15:25:59
Size: 1562
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 21: Line 21:
== 2018-02-13 ==
 * --(Test FR stepper.)--
 * --(Set up watchdog.)--
 * --(Calibrate FR actuation.)--
 * --(Calibrate LVDT actuation.)--
 * --(Add IRM side panels.)--
 * --(Add IM OSEMs and flags.)--
 * --(Adjust IRM and lateral position of OSEMs.)--
 * --(Cable IM OSEMs.)--
 * --(Set gains and offsets in IM OSEMINF screens.)--
 * --(Set OSEM2EUL matrices.)--
 * --(Center IM OSEMs in/out.)--

==== Plan for week of 2/19 ====
 * Recover from power outage.
 * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
 * Add BF cap.
 * Lift BF/... section with LGA.
 * Check/adjust total mass and balance.
 * Cable and test BF picos.
 * Anchor cables to BF cap.
 * Add AF crossbars for under SF.
 * Build up SS to SF ring.
 * Bring in SF.
 * Remove SF cap.
 * Hook BF/... section.
 * Route cables up to under SF.
 * Check/adjust total mass of BF/... section.
 * Cable SF LVDT.
==== Plan for week of 3/5 ====
 * See important pump down-related stuff at [[../ToDoBS]].
Line 52: Line 25:
 * Test/calibrate SF FR.
Line 54: Line 26:
 * Add Cu segments to SF cap.
Line 56: Line 27:
 * Get SRM mushroom installed.
 * Start BF rebuild.

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Plan for week of 3/5

  • See important pump down-related stuff at ../ToDoBS.

  • Calibrate SF LVDT.
  • Cable SF FR.
  • Add SF cap.
  • Lift SF/... with LGA and check weight/balance.
  • Get SRM mushroom installed.
  • Start BF rebuild.

SR Prep Tasks - To Be Scheduled

  • Review Shoda-san's Guardian.
  • Decide if we're really going to renumber IP channels.
  • Review DIO stuff.
  • Review SR2 model (especially screens, macro text file).
  • Review DAC channel requests.
  • Find out (from Takahashi-san) specifications for geophone pod items:
    • Screws for pod (cap-neck and neck-body).
    • Screws for geophone to interface plate.
    • Screws for interface plate to PI.
  • Find or order geophone items.
  • Get geophone circuit boards from Okutomi-san.
  • Find fourth feedthrough
  • Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
  • Design final SF ballast masses (Fabian).
  • Get safety bars moved.
  • Get air hose connection moved.
  • Glue SR3.
  • Set up SR3 rack.
  • Set up SRM rack.
  • Rebuild two BFs.
  • Disassemble two top filters.
  • Rebuild three top filters.

KAGRA/Subgroups/VIS/TypeB/ToDoSR (last edited 2019-01-04 15:25:56 by MarkBarton)