Differences between revisions 46 and 67 (spanning 21 versions)
Revision 46 as of 2018-03-02 15:25:59
Size: 1562
Editor: MarkBarton
Comment:
Revision 67 as of 2018-06-14 15:51:10
Size: 3399
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 13: Line 13:
=== Facilities === ==== Facilities ====
Line 20: Line 20:
== Coming Weeks ==
Line 21: Line 22:
==== Plan for week of 3/5 ====
 * See important pump down-related stuff at [[../ToDoBS]].
 * Calibrate SF LVDT.
 * Cable SF FR.
 * Add SF cap.
 * Lift SF/... with LGA and check weight/balance.
 * Get SRM mushroom installed.
 * Start BF rebuild.
=== 2018-06-04 ===
==== Main Sequence ====
 * Debug stuff.
  * Finish debugging BS BIO.
  * Make SR3, SR2, SRM like BS.
  * IM BIO connection is wrong. V goes H and H goes V.
  * Swap the LPCD to HPCD.
  * Check the payload so that it gives us the correct TF.
 * Install L-brackets on BF and SF rings.
 * Add extra spacers under SF to give more jack range.
 * Suspend BF/... section.
 * Adjust BF trim mass.
 * Route cables through SF-BF flying saucer up to bottom of SF.
 * Adjust BF trim mass.
 * Readjust payload.
 * Take TFs.
 * Add budgeted ballast mass to SF.
 * Cable, test SF LVDT and FR.
 * Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
 * Set up software pico drivers for SR3_IM and SR3_BF.
 * Replace ceramic thrust bearing in PI #3 with metal one (do PI #1 as well if time).

==== F0/LBB Stuff ====
 * Finish tuning F0 in PI #3.
 * Characterize more blades?
 * Park PI #1 in SR3 AF.
 * Crane PI #3 behind SR3.
 * Crane PI #1 to factory area.
 * Build/tune F0 in PI #1.

==== Software ====
 * Split SRx real-time models?
 * Fix white channels on BS screens (will probably be an issue for SRx models if/when split).
=== 2018-06-18 ===
==== Main Sequence ====
 * SF/... TFs.
==== F0/LBB Stuff ====
 * Wrap PI #1.
 * Crane PI #1 to SR2 AF.
 * Crane PI #3 into SR3 AF.
 * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank.
 
=== 2018-06-25 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-07-02 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-07-09 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-07-16 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-07-23 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 33: Line 88:
=== Tunnel ===
 * Calibrate last six IM OSEMs.
 * Install first set of LBB damper rings in SR3 tank.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
 * Finish half-completed geophones.
 * Characterize final top filter blades (from 5/31).
 * Rebuild filters in PIs #1 and #3.
 * Install clamps on PIs #1 and #3.
 * Install LBB units on PIs #1 and #3.
 * Install correct IP in PI #3.
 * Rebuild filter in PI #2.
 * Install clamps on PI #2.
 * Install LBB blade units on PI #2.
=== Mitaka or remotely ===
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
 * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
 * Set up SR2 Guardian.
 * Install damping filters for SR2.
Line 34: Line 107:
 * Decide if we're really going to renumber IP channels.
Line 36: Line 108:
 * Review SR2 model (especially screens, macro text file).
Line 38: Line 109:
 * Find out (from Takahashi-san) specifications for geophone pod items:
  * Screws for pod (cap-neck and neck-body).
  * Screws for geophone to interface plate.
  * Screws for interface plate to PI.
 * Find or order geophone items.
 * Get geophone circuit boards from Okutomi-san.
 * Find fourth feedthrough
 * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
 * Design final SF ballast masses (Fabian).
 * Get safety bars moved.
 * Get air hose connection moved.
 * Glue SR3.
 * Set up SR3 rack.
 * Set up SRM rack.
 * Rebuild two BFs.
 * Disassemble two top filters.
 * Rebuild three top filters.
 * Set up SR2 and SR3 Guardian.
 * Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
 * Install damping filters for SR2.
 * Do buoyancy calculation (see LIGO-T1100616).

=== Ordering ===
See ../WishList .

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-06-04

Main Sequence

  • Debug stuff.
    • Finish debugging BS BIO.
    • Make SR3, SR2, SRM like BS.
    • IM BIO connection is wrong. V goes H and H goes V.
    • Swap the LPCD to HPCD.
    • Check the payload so that it gives us the correct TF.
  • Install L-brackets on BF and SF rings.
  • Add extra spacers under SF to give more jack range.
  • Suspend BF/... section.
  • Adjust BF trim mass.
  • Route cables through SF-BF flying saucer up to bottom of SF.
  • Adjust BF trim mass.
  • Readjust payload.
  • Take TFs.
  • Add budgeted ballast mass to SF.
  • Cable, test SF LVDT and FR.
  • Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
  • Set up software pico drivers for SR3_IM and SR3_BF.
  • Replace ceramic thrust bearing in PI #3 with metal one (do PI #1 as well if time).

F0/LBB Stuff

  • Finish tuning F0 in PI #3.
  • Characterize more blades?
  • Park PI #1 in SR3 AF.
  • Crane PI #3 behind SR3.
  • Crane PI #1 to factory area.
  • Build/tune F0 in PI #1.

Software

  • Split SRx real-time models?
  • Fix white channels on BS screens (will probably be an issue for SRx models if/when split).

2018-06-18

Main Sequence

  • SF/... TFs.

F0/LBB Stuff

  • Wrap PI #1.
  • Crane PI #1 to SR2 AF.
  • Crane PI #3 into SR3 AF.
  • Remove SR3 tank lid, crane LBB rings to top of lower half of the tank.

2018-06-25

Main Sequence

F0/LBB Stuff

2018-07-02

Main Sequence

F0/LBB Stuff

2018-07-09

Main Sequence

F0/LBB Stuff

2018-07-16

Main Sequence

F0/LBB Stuff

2018-07-23

Main Sequence

F0/LBB Stuff

SR Prep Tasks - To Be Scheduled

Tunnel

  • Calibrate last six IM OSEMs.
  • Install first set of LBB damper rings in SR3 tank.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • Finish half-completed geophones.
  • Characterize final top filter blades (from 5/31).
  • Rebuild filters in PIs #1 and #3.
  • Install clamps on PIs #1 and #3.
  • Install LBB units on PIs #1 and #3.
  • Install correct IP in PI #3.
  • Rebuild filter in PI #2.
  • Install clamps on PI #2.
  • Install LBB blade units on PI #2.

Mitaka or remotely

  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review Shoda-san's Guardian.
  • Review DIO stuff.
  • Review DAC channel requests.
  • Set up SR2 and SR3 Guardian.
  • Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
  • Install damping filters for SR2.
  • Do buoyancy calculation (see LIGO-T1100616).

Ordering

See ../WishList .

KAGRA/Subgroups/VIS/TypeB/ToDoSR (last edited 2019-01-04 15:25:56 by MarkBarton)