Line 12: | Line 12: |
== DEBUG PLEASE == SR3 * IM BIO connection is wrong. V goes H and H goes V. * Swap the LPCD to HPCD. * Check the payload so that it gives us the correct TF. * Check IP BIO connection. |
|
Line 13: | Line 20: |
=== Facilities === | ==== Facilities ==== |
Line 20: | Line 27: |
== Coming Weeks == | |
Line 21: | Line 29: |
==== Plan for week of 3/5 ==== * --(Grab rack for SRM.)-- * --(See important pump down-related stuff at [[../ToDoBS]].)-- * --(Calibrate SF LVDT.)-- * --(Cable/test SF FR.)-- * --(Add SF cap.)-- * Lift SF/... with LGA and check weight/balance. * Start BF rebuild. |
|
Line 30: | Line 30: |
==== Plan for week of 3/12 ==== * Get SRM mushroom installed. * Set up SR3 and SRM racks. * Lay SR3 in-air cabling. |
=== 2018-06-04 === ==== Main Sequence ==== * Cable and test BF cap picos. * Build up security structure to SF level. * Crane in SF and remove cap. * Hook BF and adjust total ballast. * Route cables through SF-BF flying saucer up to bottom of SF. * Adjust BF trim mass. * Readjust payload. * Take TFs. * Add budgeted ballast mass to SF. * Cable, test SF LVDT and FR. ==== F0/LBB Stuff ==== * Characterize final F0 blades. === 2018-06-11 === ==== Main Sequence ==== * SF/... TFs. ==== F0/LBB Stuff ==== * Rebuild F0 #3 for SR3. * Park F0 #1 (for SR2) in top of SR3 assembly frame. * Move F0 #3 behind SR3. * Make LBB blade sets (or at least 3 of 9). === 2018-06-18 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-06-25 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-02 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-09 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-16 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-23 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== |
Line 38: | Line 83: |
=== Tunnel === * Calibrate last six IM OSEMs. * Install first set of LBB damper rings in SR3 tank. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * Finish half-completed geophones. * Characterize final top filter blades (from 5/31). * Rebuild filters in PIs #1 and #3. * Install clamps on PIs #1 and #3. * Install LBB units on PIs #1 and #3. * Install correct IP in PI #3. * Rebuild filter in PI #2. * Install clamps on PI #2. * Install LBB blade units on PI #2. === Mitaka or remotely === * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass. * Set up SR2 Guardian. * Install damping filters for SR2. |
|
Line 39: | Line 102: |
* Decide if we're really going to renumber IP channels. | |
Line 41: | Line 103: |
* Review SR2 model (especially screens, macro text file). | |
Line 43: | Line 104: |
* Find out (from Takahashi-san) specifications for geophone pod items: * Screws for pod (cap-neck and neck-body). * Screws for geophone to interface plate. * Screws for interface plate to PI. * Find or order geophone items. * Get geophone circuit boards from Okutomi-san. * Find fourth feedthrough * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done. * Design final SF ballast masses (Fabian). * Get safety bars moved. * Get air hose connection moved. * Glue SR3. * Set up SR3 rack. * Set up SRM rack. * Rebuild two BFs. * Disassemble two top filters. * Rebuild three top filters. |
* Set up SR2 and SR3 Guardian. * Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen. * Install damping filters for SR2. * Do buoyancy calculation (see LIGO-T1100616). === Ordering === See ../WishList . |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
DEBUG PLEASE
SR3
- IM BIO connection is wrong. V goes H and H goes V.
- Swap the LPCD to HPCD.
- Check the payload so that it gives us the correct TF.
- Check IP BIO connection.
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-06-04
Main Sequence
- Cable and test BF cap picos.
- Build up security structure to SF level.
- Crane in SF and remove cap.
- Hook BF and adjust total ballast.
- Route cables through SF-BF flying saucer up to bottom of SF.
- Adjust BF trim mass.
- Readjust payload.
- Take TFs.
- Add budgeted ballast mass to SF.
- Cable, test SF LVDT and FR.
F0/LBB Stuff
- Characterize final F0 blades.
2018-06-11
Main Sequence
- SF/... TFs.
F0/LBB Stuff
- Rebuild F0 #3 for SR3.
- Park F0 #1 (for SR2) in top of SR3 assembly frame.
- Move F0 #3 behind SR3.
- Make LBB blade sets (or at least 3 of 9).
2018-06-18
Main Sequence
F0/LBB Stuff
2018-06-25
Main Sequence
F0/LBB Stuff
2018-07-02
Main Sequence
F0/LBB Stuff
2018-07-09
Main Sequence
F0/LBB Stuff
2018-07-16
Main Sequence
F0/LBB Stuff
2018-07-23
Main Sequence
F0/LBB Stuff
SR Prep Tasks - To Be Scheduled
Tunnel
- Calibrate last six IM OSEMs.
- Install first set of LBB damper rings in SR3 tank.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- Finish half-completed geophones.
- Characterize final top filter blades (from 5/31).
- Rebuild filters in PIs #1 and #3.
- Install clamps on PIs #1 and #3.
- Install LBB units on PIs #1 and #3.
- Install correct IP in PI #3.
- Rebuild filter in PI #2.
- Install clamps on PI #2.
- Install LBB blade units on PI #2.
Mitaka or remotely
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review Shoda-san's Guardian.
- Review DIO stuff.
- Review DAC channel requests.
- Set up SR2 and SR3 Guardian.
- Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
- Install damping filters for SR2.
- Do buoyancy calculation (see LIGO-T1100616).
Ordering
See ../WishList .