Line 20: Line 20:
== Coming Weeks ==
 
=== 2018-05-14 ===
=== Main Sequence ===
 * Crane in BF.
 * Add IRM top plate, maraging rod, flying saucer.
 * Suspend IM, check pitch, roll and vertical, adjust trim mass.
 * Cable and (re-)test TM OSEMs, IM picos, BF yaw pico, BF LVDT and FR.
=== F0/LBB Stuff ===
 * Final prep for F0 prototype blade test (5/14)
 * F0 prototype blade test with Takahashi-san (5/15 or TBD)
 * Start characterizing LBB blades.
Line 21: Line 33:
==== Plan for week of 2018-04-16 ====
 * Move SF and BF for SRM out of the way.
 * Check results of gluing.
 * Build 1xRM
 * Calibrate OSEMs.
 * Start SR3 Hang
  * Reset assembly frame crossbars to correct heights.
  * Center the optical table.
  * Align the assembly frame vertically.
  * Install IM ring and IM.
  * Hang optic.
  * Hang RM.
  * Cable RM OSEMs.
== 2018-05-21 ==
=== Main Sequence ===
 * Install IRM sides, and IM OSEMs.
 * Center IM OSEMs (in/out and laterally)
 * Route all cables to underneath BF.
 * Add BF internal ballast mass.
 * Add BF cap.
=== F0/LBB Stuff ===
 * Continue characterizing LBB blades.
== 2018-05-28 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
Line 35: Line 46:
==== Plan for week of 2018-04-23 ====
 * Clean parts (cable clamp bases, etc, etc; Hirata-san).
 * Observe KAGRA Phase 1 operations, assist if problems arise.
 * Continue SR3 hang.
 * Top filter disassembly
== 2018-06-04 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
Line 41: Line 50:
==== Plan for week of 2018-04-30 ====
 * Golden Week!
== 2018-06-11 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-06-18 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-06-25 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-07-02 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-07-09 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-07-16 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-07-23 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
Line 48: Line 83:
 * Get SRM mushroom installed.
 * --(Find 4 more feedthroughs for SRM.)--
 * Install first set of LBB damper rings in SR2 (or SR3?) tank.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
 * Finish half-completed geophones.
 * Characterize top filter prototype blades.
 * Decide final top filter blade parameters and order.
 * Rebuild three top filters.
 * Do buoyancy calculation (see LIGO-T1100616).
=== Mitaka or remotely ===
Line 50: Line 95:
 * Get SRM mushroom installed.
 * Install first set of LBB damper rings in SR2 (or SR3?) tank.
 * Set up SR2 Guardian.
 * Install damping filters for SR2.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
 * Do buoyancy calculation (see LIGO-T1100616).
Line 61: Line 100:
 * Order Cu O-rings for geophone.
 * Finish half-completed geophones.
 * Find fourth feedthrough for SR2, 8 more for SR3 and SRM.
 * Characterize top filter prototype blades.
 * Decide final top filter blade parameters and order.
 * Rebuild three top filters.
 * Do buoyancy calculation (see LIGO-T1100616).
 * Set up SR2 and SR3 Guardian.
 * Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
 * Install damping filters for SR2.
=== Ordering ===
See ../WishList .

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-05-14

Main Sequence

  • Crane in BF.
  • Add IRM top plate, maraging rod, flying saucer.
  • Suspend IM, check pitch, roll and vertical, adjust trim mass.
  • Cable and (re-)test TM OSEMs, IM picos, BF yaw pico, BF LVDT and FR.

F0/LBB Stuff

  • Final prep for F0 prototype blade test (5/14)
  • F0 prototype blade test with Takahashi-san (5/15 or TBD)
  • Start characterizing LBB blades.

2018-05-21

Main Sequence

  • Install IRM sides, and IM OSEMs.
  • Center IM OSEMs (in/out and laterally)
  • Route all cables to underneath BF.
  • Add BF internal ballast mass.
  • Add BF cap.

F0/LBB Stuff

  • Continue characterizing LBB blades.

2018-05-28

Main Sequence

F0/LBB Stuff

2018-06-04

Main Sequence

F0/LBB Stuff

2018-06-11

Main Sequence

F0/LBB Stuff

2018-06-18

Main Sequence

F0/LBB Stuff

2018-06-25

Main Sequence

F0/LBB Stuff

2018-07-02

Main Sequence

F0/LBB Stuff

2018-07-09

Main Sequence

F0/LBB Stuff

2018-07-16

Main Sequence

F0/LBB Stuff

2018-07-23

Main Sequence

F0/LBB Stuff

SR Prep Tasks - To Be Scheduled

Tunnel

  • Get SRM mushroom installed.
  • Find 4 more feedthroughs for SRM.

  • Install first set of LBB damper rings in SR2 (or SR3?) tank.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • Finish half-completed geophones.
  • Characterize top filter prototype blades.
  • Decide final top filter blade parameters and order.
  • Rebuild three top filters.
  • Do buoyancy calculation (see LIGO-T1100616).

Mitaka or remotely

  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review Shoda-san's Guardian.
  • Review DIO stuff.
  • Review DAC channel requests.
  • Set up SR2 and SR3 Guardian.
  • Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
  • Install damping filters for SR2.

Ordering

See ../WishList .