Size: 2276
Comment:
|
Size: 2379
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 20: | Line 20: |
== Coming Weeks == === 2018-05-14 === === Main Sequence === * Weigh IM/... section. * Do === F0/LBB Stuff === * Final prep for F0 prototype blade test (5/14) * F0 prototype blade test with Takahashi-san (5/15 or TBD) |
|
Line 21: | Line 30: |
==== Plan for week of 2018-04-16 ==== * Move SF and BF for SRM out of the way. * Check results of gluing. * Build 1xRM * Calibrate OSEMs. * Start SR3 Hang * Reset assembly frame crossbars to correct heights. * Center the optical table. * Align the assembly frame vertically. * Install IM ring and IM. * Hang optic. * Hang RM. * Cable RM OSEMs. |
== 2018-05-21 == === Main Sequence === === F0/LBB Stuff === == 2018-05-28 == === Main Sequence === === F0/LBB Stuff === |
Line 35: | Line 37: |
==== Plan for week of 2018-04-23 ==== * Clean parts (cable clamp bases, etc, etc; Hirata-san). * Observe KAGRA Phase 1 operations, assist if problems arise. * Continue SR3 hang. * Top filter disassembly |
== 2018-06-04 == === Main Sequence === === F0/LBB Stuff === |
Line 41: | Line 41: |
==== Plan for week of 2018-04-30 ==== * Golden Week! |
== 2018-06-11 == === Main Sequence === === F0/LBB Stuff === == 2018-06-18 == === Main Sequence === === F0/LBB Stuff === == 2018-06-25 == === Main Sequence === === F0/LBB Stuff === == 2018-07-02 == === Main Sequence === === F0/LBB Stuff === == 2018-07-09 == === Main Sequence === === F0/LBB Stuff === == 2018-07-16 == === Main Sequence === === F0/LBB Stuff === == 2018-07-23 == === Main Sequence === === F0/LBB Stuff === |
Line 48: | Line 74: |
* Get SRM mushroom installed. * --(Find 4 more feedthroughs for SRM.)-- * Install first set of LBB damper rings in SR2 (or SR3?) tank. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * Finish half-completed geophones. * Characterize top filter prototype blades. * Decide final top filter blade parameters and order. * Rebuild three top filters. * Do buoyancy calculation (see LIGO-T1100616). === Mitaka or remotely === |
|
Line 50: | Line 86: |
* Get SRM mushroom installed. * Install first set of LBB damper rings in SR2 (or SR3?) tank. * Set up SR2 and SR3 Guardian. * Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen. * Install damping filters for SR2. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * Do buoyancy calculation (see LIGO-T1100616). |
|
Line 62: | Line 91: |
* Order Cu O-rings for geophones (seems we have 3 of 4 150-mm ones and 4 of 80 mm ones) * Order rubber pieces for geophones. * Finish half-completed geophones. * Find fourth feedthrough for SR2, 8 more for SR3 and SRM. * Characterize top filter prototype blades. * Decide final top filter blade parameters and order. * Rebuild three top filters. * Do buoyancy calculation (see LIGO-T1100616). |
* Set up SR2 and SR3 Guardian. * Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen. * Install damping filters for SR2. === Ordering === See ../WishList . |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-05-14
Main Sequence
- Weigh IM/... section.
- Do
F0/LBB Stuff
- Final prep for F0 prototype blade test (5/14)
- F0 prototype blade test with Takahashi-san (5/15 or TBD)
2018-05-21
Main Sequence
F0/LBB Stuff
2018-05-28
Main Sequence
F0/LBB Stuff
2018-06-04
Main Sequence
F0/LBB Stuff
2018-06-11
Main Sequence
F0/LBB Stuff
2018-06-18
Main Sequence
F0/LBB Stuff
2018-06-25
Main Sequence
F0/LBB Stuff
2018-07-02
Main Sequence
F0/LBB Stuff
2018-07-09
Main Sequence
F0/LBB Stuff
2018-07-16
Main Sequence
F0/LBB Stuff
2018-07-23
Main Sequence
F0/LBB Stuff
SR Prep Tasks - To Be Scheduled
Tunnel
- Get SRM mushroom installed.
Find 4 more feedthroughs for SRM.
- Install first set of LBB damper rings in SR2 (or SR3?) tank.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- Finish half-completed geophones.
- Characterize top filter prototype blades.
- Decide final top filter blade parameters and order.
- Rebuild three top filters.
- Do buoyancy calculation (see LIGO-T1100616).
Mitaka or remotely
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review Shoda-san's Guardian.
- Review DIO stuff.
- Review DAC channel requests.
- Set up SR2 and SR3 Guardian.
- Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
- Install damping filters for SR2.
Ordering
See ../WishList .