Line 24: Line 24:
 * Glue new metal prism on SR3 to replace one with failed bond.
 * Build 1xRM
 * Calibrate OSEMs.
 * --(Glue new metal prism on SR3 to replace one with failed bond.)--
 * --(Build 1xRM)--
 * --(Calibrate OSEMs.)--
Line 28: Line 28:
  * Reset assembly frame crossbars to correct heights.
  * Center the optical table.
  * Align the assembly frame vertically.
  * Install IM ring and IM.
  * --(Reset assembly frame crossbars to correct heights.)--
  * --(Center the optical table.)--
  * --(Align the assembly frame vertically.)--
  * --(Install IM ring and IM.)--

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Plan for week of 2018-04-16

  • Move SF and BF for SRM out of the way.

  • Check results of gluing.

  • Glue new metal prism on SR3 to replace one with failed bond.

  • Build 1xRM

  • Calibrate OSEMs.

  • Start SR3 Hang
    • Reset assembly frame crossbars to correct heights.

    • Center the optical table.

    • Align the assembly frame vertically.

    • Install IM ring and IM.

    • Hang optic.
    • Hang RM.
    • Cable RM OSEMs.
  • Find fourth feedthrough for SR2, 4 more for SR3.

Plan for week of 2018-04-23

  • Clean parts (cable clamp bases, etc, etc; Hirata-san).
  • Observe KAGRA Phase 1 operations, assist if problems arise.
  • Continue SR3 hang.
  • Top filter disassembly

Plan for week of 2018-04-30

  • Golden Week!

SR Prep Tasks - To Be Scheduled

Tunnel

  • Get SRM mushroom installed.
  • Find 4 more feedthroughs for SRM.
  • Install first set of LBB damper rings in SR2 (or SR3?) tank.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • Finish half-completed geophones.
  • Characterize top filter prototype blades.
  • Decide final top filter blade parameters and order.
  • Rebuild three top filters.
  • Do buoyancy calculation (see LIGO-T1100616).

Mitaka or remotely

  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review Shoda-san's Guardian.
  • Review DIO stuff.
  • Review DAC channel requests.
  • Set up SR2 and SR3 Guardian.
  • Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
  • Install damping filters for SR2.

Ordering

See ../WishList .