Line 13: Line 13:
=== Facilities === ==== Facilities ====
Line 21: Line 21:
=== 2018-04-23 ===

=== 2018-06-18 ===
Line 23: Line 25:
 * Get 8xM8x40 screws for feedthroughs.
 * Attach feedthroughs to AF.
 * Get LVDT driver with one good and one bad card for Tanaka-san.
 * Start SR3 Hang
  * Find wires, wire clamp items.
  * Install winch system.
  * Move KOACH filters, mirror box and table to near AF.
  * Hang optic.
  * Set up OL.
  * Set optic pitch.
  * Hang RM.
  * Cable RM OSEMs.
 * Tweak BF total trim masses.
 * SF/... TFs.
 * Add budgeted ballast mass to SF (or remove stuff!).
 * Cable, test SF FR.
 * Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
 * Check JGWDoc electronic item lists are up to date.
Line 37: Line 33:
 * Clean parts (cable clamp bases, etc, etc; Hirata-san@Mitaka).
 * Top filter disassembly (if any spare time)
 * Prepare F0 workspace in SRM area (if any spare time)
 * Finish tuning F0 in PI #3.
 * Replace ceramic thrust bearing in PI #3 with metal one (do PI #1 as well if time).
 * Characterize more blades?
 * Park PI #1 in SR3 AF.
 * Crane PI #3 behind SR3.
 * Crane PI #1 to factory area.
Line 41: Line 40:
=== 2018-04-30 ===
 * Golden Week!
 * Uso!
 * BS TFs (4/30 or TBD).
 * Observe/assist with bKAGRA Phase 1.
==== Software ====
 * Review/improve macro file fixes for split models; write klog; submit changes to SVN.
 * Install AC bandpass filters in SR3 WD filters.
 * Check coil filter gains for compensation of magnet polarities (confirm SR3 IM, set and confirm SR2 and SR3 TM).
 * Create software stepper drivers for SR3 and SRM and link to from STEP_MASTER.adl screen.
 
=== 2018-06-25 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
 * Build/tune F0 in PI #1.
 * Finish tuning PI #3.
 * Wrap PI #1.
 * Crane PI #1 to SR2 AF.
 * Crane PI #3 into SR3 AF.
==== Software/Remote ====
Line 47: Line 56:
== 2018-05-07 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
 * Prepare F0 workspace in SRM area
 * Disassemble F0 #1 and #3
 * Temporarily raise F0 #3 (in SRM) and remove floor panel
 * Start characterization of LBB blades (should have by 4/30)
 
== 2018-05-14 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-07-02 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 59: Line 60:
== 2018-05-21 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
 * Final prep for F0 prototype blade test (5/14)
 * F0 prototype blade test with Takahashi-san (5/15 or TBD)
== 2018-05-28 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-07-09 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 68: Line 64:
== 2018-06-04 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-07-16 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 72: Line 68:
== 2018-06-11 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-06-18 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-06-25 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-07-02 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-07-09 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-07-16 ==
=== Main Sequence ===
=== F0/LBB Stuff ===

== 2018-07-23 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-07-23 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 105: Line 77:
 * Get SRM mushroom installed.
 * --(Find 4 more feedthroughs for SRM.)--
 * Install first set of LBB damper rings in SR2 (or SR3?) tank.
 * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
 * Check SR2, SR3 TM coil gains for magnet polarity compensation.
 * Calibrate last six IM OSEMs.
Line 109: Line 81:
 * Finish half-completed geophones.
 * Characterize top filter prototype blades.
 * Decide final top filter blade parameters and order.
 * Rebuild three top filters.
 * Do buoyancy calculation (see LIGO-T1100616).
 * Rebuild filter in PI #1.
 * Install clamps on PIs #1?
 * Install correct IP in PI #2.
 * Rebuild filter in PI #2.
 * Install clamps on PI #2.
 * Install LBB blade units on PI #2.
Line 125: Line 98:
 * Do buoyancy calculation (see LIGO-T1100616).
 * Split SRx real-time models?

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-06-18

Main Sequence

  • Tweak BF total trim masses.
  • SF/... TFs.
  • Add budgeted ballast mass to SF (or remove stuff!).
  • Cable, test SF FR.
  • Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
  • Check JGWDoc electronic item lists are up to date.

F0/LBB Stuff

  • Finish tuning F0 in PI #3.
  • Replace ceramic thrust bearing in PI #3 with metal one (do PI #1 as well if time).
  • Characterize more blades?
  • Park PI #1 in SR3 AF.
  • Crane PI #3 behind SR3.
  • Crane PI #1 to factory area.

Software

  • Review/improve macro file fixes for split models; write klog; submit changes to SVN.
  • Install AC bandpass filters in SR3 WD filters.
  • Check coil filter gains for compensation of magnet polarities (confirm SR3 IM, set and confirm SR2 and SR3 TM).
  • Create software stepper drivers for SR3 and SRM and link to from STEP_MASTER.adl screen.

2018-06-25

Main Sequence

F0/LBB Stuff

  • Build/tune F0 in PI #1.
  • Finish tuning PI #3.
  • Wrap PI #1.
  • Crane PI #1 to SR2 AF.
  • Crane PI #3 into SR3 AF.

Software/Remote

2018-07-02

Main Sequence

F0/LBB Stuff

2018-07-09

Main Sequence

F0/LBB Stuff

2018-07-16

Main Sequence

F0/LBB Stuff

2018-07-23

Main Sequence

F0/LBB Stuff

SR Prep Tasks - To Be Scheduled

Tunnel

  • Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
  • Check SR2, SR3 TM coil gains for magnet polarity compensation.
  • Calibrate last six IM OSEMs.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • Rebuild filter in PI #1.
  • Install clamps on PIs #1?
  • Install correct IP in PI #2.
  • Rebuild filter in PI #2.
  • Install clamps on PI #2.
  • Install LBB blade units on PI #2.

Mitaka or remotely

  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review Shoda-san's Guardian.
  • Review DIO stuff.
  • Review DAC channel requests.
  • Set up SR2 and SR3 Guardian.
  • Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
  • Install damping filters for SR2.
  • Do buoyancy calculation (see LIGO-T1100616).
  • Split SRx real-time models?

Ordering

See ../WishList .

KAGRA/Subgroups/VIS/TypeB/ToDoSR (last edited 2019-01-04 15:25:56 by MarkBarton)