Differences between revisions 55 and 57 (spanning 2 versions)
Revision 55 as of 2018-05-11 12:01:11
Size: 2379
Editor: MarkBarton
Comment:
Revision 57 as of 2018-05-17 12:48:03
Size: 2778
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 13: Line 13:
=== Facilities === ==== Facilities ====
Line 21: Line 21:
  === 2018-05-14 ===
=== Main Sequence ===
 * Weigh IM/... section.
 * Do
=== F0/LBB Stuff ===
 * Final prep for F0 prototype blade test (5/14)
 * F0 prototype blade test with Takahashi-san (5/15 or TBD)
Line 30: Line 22:
== 2018-05-21 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
== 2018-05-28 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-05-21 ===
==== Main Sequence ====
 * Cable and (re-)test TM OSEMs, IM picos, BF yaw pico, BF LVDT and FR.
 * Install IRM sides, and IM OSEMs.
 * Center IM OSEMs (in/out and laterally)
 * Route all cables to underneath BF.
 * Add BF internal ballast mass.
 * Add BF cap.
==== F0/LBB Stuff ====
 * Create LBB blade sets (if screws are available)
 * Install LBB blade sets on PIs #1 and #3 (if possible).
 * Install cable clamps on PIs #1 and #3.
 * Put LBB damper rings in SR3 tank.
Line 37: Line 36:
== 2018-06-04 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-05-28 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 41: Line 40:
== 2018-06-11 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-06-04 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 45: Line 44:
== 2018-06-18 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-06-11 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 49: Line 48:
== 2018-06-25 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-06-18 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 53: Line 52:
== 2018-07-02 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-06-25 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 57: Line 56:
== 2018-07-09 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-07-02 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 61: Line 60:
== 2018-07-16 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-07-09 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 65: Line 64:
== 2018-07-23 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-07-16 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-07-23 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 74: Line 77:
 * Get SRM mushroom installed.
 * --(Find 4 more feedthroughs for SRM.)--

 * Install first set of LBB damper rings in SR2 (or SR3?) tank.
 * Calibrate last six IM OSEMs.
 * Install first set of LBB damper rings in SR3 tank.
Line 79: Line 81:
 * Characterize top filter prototype blades.
 * Decide final top filter blade parameters and order.
 * Rebuild three top filters.
 * Do buoyancy calculation (see LIGO-T1100616).
 * Characterize final top filter blades (from 5/31).
 * Rebuild filters in PIs #1 and #3.
 * Install clamps on PIs #1 and #3.
 * Install LBB units on PIs #1 and #3.
 * Install correct IP in PI #3.
 * Rebuild filter in PI #2.
 * Install clamps on PI #2.
 * Install LBB blade units on PI #2.
Line 94: Line 100:
 * Do buoyancy calculation (see LIGO-T1100616).

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-05-21

Main Sequence

  • Cable and (re-)test TM OSEMs, IM picos, BF yaw pico, BF LVDT and FR.
  • Install IRM sides, and IM OSEMs.
  • Center IM OSEMs (in/out and laterally)
  • Route all cables to underneath BF.
  • Add BF internal ballast mass.
  • Add BF cap.

F0/LBB Stuff

  • Create LBB blade sets (if screws are available)
  • Install LBB blade sets on PIs #1 and #3 (if possible).
  • Install cable clamps on PIs #1 and #3.
  • Put LBB damper rings in SR3 tank.

2018-05-28

Main Sequence

F0/LBB Stuff

2018-06-04

Main Sequence

F0/LBB Stuff

2018-06-11

Main Sequence

F0/LBB Stuff

2018-06-18

Main Sequence

F0/LBB Stuff

2018-06-25

Main Sequence

F0/LBB Stuff

2018-07-02

Main Sequence

F0/LBB Stuff

2018-07-09

Main Sequence

F0/LBB Stuff

2018-07-16

Main Sequence

F0/LBB Stuff

2018-07-23

Main Sequence

F0/LBB Stuff

SR Prep Tasks - To Be Scheduled

Tunnel

  • Calibrate last six IM OSEMs.
  • Install first set of LBB damper rings in SR3 tank.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • Finish half-completed geophones.
  • Characterize final top filter blades (from 5/31).
  • Rebuild filters in PIs #1 and #3.
  • Install clamps on PIs #1 and #3.
  • Install LBB units on PIs #1 and #3.
  • Install correct IP in PI #3.
  • Rebuild filter in PI #2.
  • Install clamps on PI #2.
  • Install LBB blade units on PI #2.

Mitaka or remotely

  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review Shoda-san's Guardian.
  • Review DIO stuff.
  • Review DAC channel requests.
  • Set up SR2 and SR3 Guardian.
  • Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
  • Install damping filters for SR2.
  • Do buoyancy calculation (see LIGO-T1100616).

Ordering

See ../WishList .

KAGRA/Subgroups/VIS/TypeB/ToDoSR (last edited 2019-01-04 15:25:56 by MarkBarton)