Differences between revisions 55 and 58 (spanning 3 versions)
Revision 55 as of 2018-05-11 12:01:11
Size: 2379
Editor: MarkBarton
Comment:
Revision 58 as of 2018-05-25 14:27:05
Size: 3052
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 13: Line 13:
=== Facilities === ==== Facilities ====
Line 21: Line 21:
  === 2018-05-14 ===
=== Main Sequence ===
 * Weigh IM/... section.
 * Do
=== F0/LBB Stuff ===
 * Final prep for F0 prototype blade test (5/14)
 * F0 prototype blade test with Takahashi-san (5/15 or TBD)
Line 30: Line 22:
== 2018-05-21 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
== 2018-05-28 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-05-28 ===
==== Main Sequence ====
 * Modify and clean Promec masses at Mitaka (making threaded holes unthreaded to allow stacking).
 * Test LVDT driver repaired by Tanaka-san.
 * Cable and test BF cap picos.
 * Install internal ballast masses.
 * Install cap ballast masses.
 * Build up security structure to SF level.
 * Crane in SF and remove cap.
 * Hook BF and adjust total ballast.
 * Route cables through SF-BF flying saucer up to bottom of SF.
 * Adjust BF trim mass.
Line 37: Line 35:
== 2018-06-04 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-06-04 ===
==== Main Sequence ====
 * Readjust payload.
 * Take TFs.
 * Add budgeted ballast mass to SF.
 * Cable, test SF LVDT and FR.
 * Finish four half-assembled geophones.
==== F0/LBB Stuff ====
 * Characterize final F0 blades.
Line 41: Line 45:
== 2018-06-11 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-06-11 ===
==== Main Sequence ====
 * SF/... TFs.
==== F0/LBB Stuff ====
 * Rebuild F0 #3 for SR3.
 * Park F0 #1 (for SR2) in top of SR3 assembly frame.
 * Move F0 #3 behind SR3.
 * Make LBB blade sets (or at least 3 of 9).
Line 45: Line 54:
== 2018-06-18 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-06-18 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 49: Line 58:
== 2018-06-25 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-06-25 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 53: Line 62:
== 2018-07-02 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-07-02 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 57: Line 66:
== 2018-07-09 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-07-09 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 61: Line 70:
== 2018-07-16 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-07-16 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 65: Line 74:
== 2018-07-23 ==
=== Main Sequence ===
=== F0/LBB Stuff ===
=== 2018-07-23 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 74: Line 83:
 * Get SRM mushroom installed.
 * --(Find 4 more feedthroughs for SRM.)--

 * Install first set of LBB damper rings in SR2 (or SR3?) tank.
 * Calibrate last six IM OSEMs.
 * Install first set of LBB damper rings in SR3 tank.
Line 79: Line 87:
 * Characterize top filter prototype blades.
 * Decide final top filter blade parameters and order.
 * Rebuild three top filters.
 * Do buoyancy calculation (see LIGO-T1100616).
 * Characterize final top filter blades (from 5/31).
 * Rebuild filters in PIs #1 and #3.
 * Install clamps on PIs #1 and #3.
 * Install LBB units on PIs #1 and #3.
 * Install correct IP in PI #3.
 * Rebuild filter in PI #2.
 * Install clamps on PI #2.
 * Install LBB blade units on PI #2.
Line 94: Line 106:
 * Do buoyancy calculation (see LIGO-T1100616).

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-05-28

Main Sequence

  • Modify and clean Promec masses at Mitaka (making threaded holes unthreaded to allow stacking).
  • Test LVDT driver repaired by Tanaka-san.
  • Cable and test BF cap picos.
  • Install internal ballast masses.
  • Install cap ballast masses.
  • Build up security structure to SF level.
  • Crane in SF and remove cap.
  • Hook BF and adjust total ballast.
  • Route cables through SF-BF flying saucer up to bottom of SF.
  • Adjust BF trim mass.

2018-06-04

Main Sequence

  • Readjust payload.
  • Take TFs.
  • Add budgeted ballast mass to SF.
  • Cable, test SF LVDT and FR.
  • Finish four half-assembled geophones.

F0/LBB Stuff

  • Characterize final F0 blades.

2018-06-11

Main Sequence

  • SF/... TFs.

F0/LBB Stuff

  • Rebuild F0 #3 for SR3.
  • Park F0 #1 (for SR2) in top of SR3 assembly frame.
  • Move F0 #3 behind SR3.
  • Make LBB blade sets (or at least 3 of 9).

2018-06-18

Main Sequence

F0/LBB Stuff

2018-06-25

Main Sequence

F0/LBB Stuff

2018-07-02

Main Sequence

F0/LBB Stuff

2018-07-09

Main Sequence

F0/LBB Stuff

2018-07-16

Main Sequence

F0/LBB Stuff

2018-07-23

Main Sequence

F0/LBB Stuff

SR Prep Tasks - To Be Scheduled

Tunnel

  • Calibrate last six IM OSEMs.
  • Install first set of LBB damper rings in SR3 tank.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • Finish half-completed geophones.
  • Characterize final top filter blades (from 5/31).
  • Rebuild filters in PIs #1 and #3.
  • Install clamps on PIs #1 and #3.
  • Install LBB units on PIs #1 and #3.
  • Install correct IP in PI #3.
  • Rebuild filter in PI #2.
  • Install clamps on PI #2.
  • Install LBB blade units on PI #2.

Mitaka or remotely

  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review Shoda-san's Guardian.
  • Review DIO stuff.
  • Review DAC channel requests.
  • Set up SR2 and SR3 Guardian.
  • Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
  • Install damping filters for SR2.
  • Do buoyancy calculation (see LIGO-T1100616).

Ordering

See ../WishList .

KAGRA/Subgroups/VIS/TypeB/ToDoSR (last edited 2019-01-04 15:25:56 by MarkBarton)