2799
Comment:
|
2974
|
Deletions are marked like this. | Additions are marked like this. |
Line 13: | Line 13: |
=== Facilities === | ==== Facilities ==== |
Line 21: | Line 21: |
=== 2018-05-14 === === Main Sequence === * Crane in BF. * Add IRM top plate, maraging rod, flying saucer. * Suspend IM, check pitch, roll and vertical, adjust trim mass. * Cable and (re-)test TM OSEMs, IM picos, BF yaw pico, BF LVDT and FR. === F0/LBB Stuff === * Final prep for F0 prototype blade test (5/14) * F0 prototype blade test with Takahashi-san (5/15 or TBD) * Start characterizing LBB blades. |
|
Line 33: | Line 22: |
== 2018-05-21 == === Main Sequence === * Install IRM sides, and IM OSEMs. * Center IM OSEMs (in/out and laterally) * Route all cables to underneath BF. * Add BF internal ballast mass. * Add BF cap. === F0/LBB Stuff === * Continue characterizing LBB blades. == 2018-05-28 == === Main Sequence === === F0/LBB Stuff === |
=== 2018-06-04 === ==== Main Sequence ==== * Debug stuff. * IM BIO connection is wrong. V goes H and H goes V. * Swap the LPCD to HPCD. * Check the payload so that it gives us the correct TF. * Debug IP BIO connection. (Debug BS IP at the same time.) * Cable and test BF cap picos. * Build up security structure to SF level. * Crane in SF and remove cap. * Hook BF and adjust total ballast. * Route cables through SF-BF flying saucer up to bottom of SF. * Adjust BF trim mass. * Readjust payload. * Take TFs. * Add budgeted ballast mass to SF. * Cable, test SF LVDT and FR. |
Line 46: | Line 40: |
== 2018-06-04 == === Main Sequence === === F0/LBB Stuff === |
==== F0/LBB Stuff ==== * Characterize final F0 blades. |
Line 50: | Line 43: |
== 2018-06-11 == === Main Sequence === === F0/LBB Stuff === |
=== 2018-06-11 === ==== Main Sequence ==== * SF/... TFs. ==== F0/LBB Stuff ==== * Rebuild F0 #3 for SR3. * Park F0 #1 (for SR2) in top of SR3 assembly frame. * Move F0 #3 behind SR3. * Make LBB blade sets (or at least 3 of 9). |
Line 54: | Line 52: |
== 2018-06-18 == === Main Sequence === === F0/LBB Stuff === |
=== 2018-06-18 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== |
Line 58: | Line 56: |
== 2018-06-25 == === Main Sequence === === F0/LBB Stuff === |
=== 2018-06-25 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== |
Line 62: | Line 60: |
== 2018-07-02 == === Main Sequence === === F0/LBB Stuff === |
=== 2018-07-02 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== |
Line 66: | Line 64: |
== 2018-07-09 == === Main Sequence === === F0/LBB Stuff === |
=== 2018-07-09 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== |
Line 70: | Line 68: |
== 2018-07-16 == === Main Sequence === === F0/LBB Stuff === |
=== 2018-07-16 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== |
Line 74: | Line 72: |
== 2018-07-23 == === Main Sequence === === F0/LBB Stuff === |
=== 2018-07-23 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== |
Line 83: | Line 81: |
* Get SRM mushroom installed. * --(Find 4 more feedthroughs for SRM.)-- * Install first set of LBB damper rings in SR2 (or SR3?) tank. |
* Calibrate last six IM OSEMs. * Install first set of LBB damper rings in SR3 tank. |
Line 88: | Line 85: |
* Characterize top filter prototype blades. * Decide final top filter blade parameters and order. * Rebuild three top filters. * Do buoyancy calculation (see LIGO-T1100616). |
* Characterize final top filter blades (from 5/31). * Rebuild filters in PIs #1 and #3. * Install clamps on PIs #1 and #3. * Install LBB units on PIs #1 and #3. * Install correct IP in PI #3. * Rebuild filter in PI #2. * Install clamps on PI #2. * Install LBB blade units on PI #2. |
Line 103: | Line 104: |
* Do buoyancy calculation (see LIGO-T1100616). |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-06-04
Main Sequence
- Debug stuff.
- IM BIO connection is wrong. V goes H and H goes V.
- Swap the LPCD to HPCD.
- Check the payload so that it gives us the correct TF.
- Debug IP BIO connection. (Debug BS IP at the same time.)
- Cable and test BF cap picos.
- Build up security structure to SF level.
- Crane in SF and remove cap.
- Hook BF and adjust total ballast.
- Route cables through SF-BF flying saucer up to bottom of SF.
- Adjust BF trim mass.
- Readjust payload.
- Take TFs.
- Add budgeted ballast mass to SF.
- Cable, test SF LVDT and FR.
F0/LBB Stuff
- Characterize final F0 blades.
2018-06-11
Main Sequence
- SF/... TFs.
F0/LBB Stuff
- Rebuild F0 #3 for SR3.
- Park F0 #1 (for SR2) in top of SR3 assembly frame.
- Move F0 #3 behind SR3.
- Make LBB blade sets (or at least 3 of 9).
2018-06-18
Main Sequence
F0/LBB Stuff
2018-06-25
Main Sequence
F0/LBB Stuff
2018-07-02
Main Sequence
F0/LBB Stuff
2018-07-09
Main Sequence
F0/LBB Stuff
2018-07-16
Main Sequence
F0/LBB Stuff
2018-07-23
Main Sequence
F0/LBB Stuff
SR Prep Tasks - To Be Scheduled
Tunnel
- Calibrate last six IM OSEMs.
- Install first set of LBB damper rings in SR3 tank.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- Finish half-completed geophones.
- Characterize final top filter blades (from 5/31).
- Rebuild filters in PIs #1 and #3.
- Install clamps on PIs #1 and #3.
- Install LBB units on PIs #1 and #3.
- Install correct IP in PI #3.
- Rebuild filter in PI #2.
- Install clamps on PI #2.
- Install LBB blade units on PI #2.
Mitaka or remotely
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review Shoda-san's Guardian.
- Review DIO stuff.
- Review DAC channel requests.
- Set up SR2 and SR3 Guardian.
- Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
- Install damping filters for SR2.
- Do buoyancy calculation (see LIGO-T1100616).
Ordering
See ../WishList .