Line 15: | Line 15: |
* Wipe ladders. | * Wipe ladders, assembly frame. |
Line 22: | Line 22: |
=== 2018-05-28 === | === 2018-07-17 === |
Line 24: | Line 24: |
* Modify and clean Promec masses at Mitaka (making threaded holes unthreaded to allow stacking). * Test LVDT driver repaired by Tanaka-san. * Cable and test BF cap picos. * Install internal ballast masses. * Install cap ballast masses. * Build up security structure to SF level. * Crane in SF and remove cap. * Hook BF and adjust total ballast. * Route cables through SF-BF flying saucer up to bottom of SF. * Adjust BF trim mass. |
* --(Find LBB damper rods and associated parts.)-- * --(Check/restore verticality of security structure.)-- * --(Set SF damper magnet ring height.)-- * --(Check/correct IP LVDT polarities.)-- * --(Calibrate IP FR sensing.)-- * --(Set safety screw and safety nut on F0 keystone; remove Kapton tape.)-- * --(Set up optical lever.)-- * --(Check/restore alignment of payload, especially optic pitch.)-- * --(Do token TFs (time permitting).)-- * --(Lock F0 keystone.)-- * --(Lock suspension laterally except for SF level.)-- * --(Add IM-RM safety bar.)-- * --(Disconnect all cables at inside of feedthroughs.)-- * --(Remove top of tank (including service ring).)-- * --(Set tank jacks to nominal height (50 mm).)-- * --(Lift suspension.)-- * --(Install LBB damper rods.)-- * --(Crane suspension into tank.)-- * --(Hook LBB damper rods.)-- * --(Replace tank lid and service ring.)-- * Remove tank lid leaving service ring. * Move feedthroughs. * Move cables over. * Test cables. * Calibrate PI LVDT and FR actuation. * Remove safety bar and unlock suspension. * Remove First Contact? * Restore payload alignment, especially pitch. * Cable geophones. * Calibrate IP LVDT and FR actuation. * TFs! |
Line 35: | Line 56: |
=== 2018-06-04 === ==== Main Sequence ==== * Readjust payload. * Take TFs. * Add budgeted ballast mass to SF. * Cable, test SF LVDT and FR. * Finish four half-assembled geophones. ==== F0/LBB Stuff ==== * Characterize final F0 blades. |
==== F0/LBB/Tank Stuff ==== * --(Help Sato-san with swapping IP in PI #2.)-- * --(Crane IP to second floor.)-- * Rebuild PI #2 F0. |
Line 45: | Line 61: |
=== 2018-06-11 === ==== Main Sequence ==== * SF/... TFs. ==== F0/LBB Stuff ==== * Rebuild F0 #3 for SR3. * Park F0 #1 (for SR2) in top of SR3 assembly frame. * Move F0 #3 behind SR3. * Make LBB blade sets (or at least 3 of 9). === 2018-06-18 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-06-25 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-02 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-09 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-16 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-23 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== |
==== Software Etc ==== |
Line 83: | Line 67: |
* Retrieve BNC-Lemo cable from Nakano-kun. * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function. * Install, cable SR3 PI yaw stepper. * Correct flipped connections in SR2 PI LVDTs. * Correct flipped connections in SRM PI LVDTs. * Grab and configure a picomotor driver as SR2_BF 10.68.150.25. * Get independent power supply for SR3 so SR2 can be powered back up. * Check SR2, SR3 TM coil gains for magnet polarity compensation. |
|
Line 84: | Line 76: |
* Install first set of LBB damper rings in SR3 tank. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * Finish half-completed geophones. * Characterize final top filter blades (from 5/31). * Rebuild filters in PIs #1 and #3. * Install clamps on PIs #1 and #3. * Install LBB units on PIs #1 and #3. * Install correct IP in PI #3. |
* Rebuild filter in PI #1. * Install clamps on PI #1. * Install geophone plates on PI #3. * Install geophone plates on PI #1. * Install correct IP in PI #2. |
Line 95: | Line 84: |
* Install geophone plates on PI #2. * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2. |
|
Line 96: | Line 88: |
* Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually). * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen. |
|
Line 100: | Line 94: |
* Review Shoda-san's Guardian. * Review DIO stuff. |
|
Line 103: | Line 95: |
* Set up SR2 and SR3 Guardian. * Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen. |
* Set up SR2 Guardian. |
Line 106: | Line 97: |
* Do buoyancy calculation (see LIGO-T1100616). | * Split SRx real-time models? |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-07-17
Main Sequence
Find LBB damper rods and associated parts.
Check/restore verticality of security structure.
Set SF damper magnet ring height.
Check/correct IP LVDT polarities.
Calibrate IP FR sensing.
Set safety screw and safety nut on F0 keystone; remove Kapton tape.
Set up optical lever.
Check/restore alignment of payload, especially optic pitch.
Do token TFs (time permitting).
Lock F0 keystone.
Lock suspension laterally except for SF level.
Add IM-RM safety bar.
Disconnect all cables at inside of feedthroughs.
Remove top of tank (including service ring).
Set tank jacks to nominal height (50 mm).
Lift suspension.
Install LBB damper rods.
Crane suspension into tank.
Hook LBB damper rods.
Replace tank lid and service ring.
- Remove tank lid leaving service ring.
- Move feedthroughs.
- Move cables over.
- Test cables.
- Calibrate PI LVDT and FR actuation.
- Remove safety bar and unlock suspension.
- Remove First Contact?
- Restore payload alignment, especially pitch.
- Cable geophones.
- Calibrate IP LVDT and FR actuation.
- TFs!
F0/LBB/Tank Stuff
Help Sato-san with swapping IP in PI #2.
Crane IP to second floor.
- Rebuild PI #2 F0.
Software Etc
SR Prep Tasks - To Be Scheduled
Tunnel
- Retrieve BNC-Lemo cable from Nakano-kun.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable SR3 PI yaw stepper.
- Correct flipped connections in SR2 PI LVDTs.
- Correct flipped connections in SRM PI LVDTs.
- Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
- Get independent power supply for SR3 so SR2 can be powered back up.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Calibrate last six IM OSEMs.
- Rebuild filter in PI #1.
- Install clamps on PI #1.
- Install geophone plates on PI #3.
- Install geophone plates on PI #1.
- Install correct IP in PI #2.
- Rebuild filter in PI #2.
- Install clamps on PI #2.
- Install LBB blade units on PI #2.
- Install geophone plates on PI #2.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .