Line 15: | Line 15: |
* Wipe ladders. | * Wipe ladders, assembly frame. |
Line 22: | Line 22: |
=== 2018-10-14 === ==== SRM (top priority) ==== * Main sequence * Cable and test BF LVDT and FR. * Adjust OSEMs laterally and in/out. * Weigh BF/... section and adjust trim mass to fix pitch/roll. * Anchor cables to BF cap. * Install SF crossbars. * Build up SS to SF ring. * Bring in SF. * Hook BF/... . * PI * Compress blades. * Choose and install CuBe spring. * Replace yoke in F0. * Install clamps on PI . * Install LBB blade units on PI. * Install geophone plates on PI. |
|
Line 23: | Line 41: |
=== 2018-06-04 === ==== Main Sequence ==== * Cable and test BF cap picos. * Build up security structure to SF level. * Crane in SF and remove cap. * Hook BF and adjust total ballast. * Route cables through SF-BF flying saucer up to bottom of SF. * Adjust BF trim mass. * Readjust payload. * Take TFs. * Add budgeted ballast mass to SF. * Cable, test SF LVDT and FR. ==== F0/LBB Stuff ==== * Characterize final F0 blades. === 2018-06-11 === ==== Main Sequence ==== * SF/... TFs. ==== F0/LBB Stuff ==== * Rebuild F0 #3 for SR3. * Park F0 #1 (for SR2) in top of SR3 assembly frame. * Move F0 #3 behind SR3. * Make LBB blade sets (or at least 3 of 9). === 2018-06-18 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-06-25 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-02 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-09 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-16 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-23 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== |
==== SR2 (low priority) ==== * Add arc weights and geophones. (Might have to reserve one geophone for Fujii-Fun - check.) * Test IP items. * Geophones * LVDTs * Steppers * Unlock and center IP. * More TFs. |
Line 77: | Line 54: |
* Calibrate last six IM OSEMs. * Install first set of LBB damper rings in SR3 tank. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * Finish half-completed geophones. * Characterize final top filter blades (from 5/31). * Rebuild filters in PIs #1 and #3. * Install clamps on PIs #1 and #3. * Install LBB units on PIs #1 and #3. * Install correct IP in PI #3. * Rebuild filter in PI #2. * Install clamps on PI #2. * Install LBB blade units on PI #2. |
* Add SR3 LBB ballast mass. * Install SR3 LEN OL. * Retrieve BNC-Lemo cable from Nakano-kun. * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function. * Install, cable SR3 PI yaw stepper. * Correct flipped connections in SRM PI LVDTs. * Check SR2, SR3 TM coil gains for magnet polarity compensation. * Clean/Replace yoke in PI #2 for SRM. * Install clamps on PI #2 for SRM. * Install LBB blade units on PI #2 for SRM. * Install geophone plates on PI #2 for SRM. * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2. |
Line 90: | Line 68: |
* Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually). * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen. |
|
Line 94: | Line 74: |
* Review Shoda-san's Guardian. * Review DIO stuff. |
|
Line 97: | Line 75: |
* Set up SR2 and SR3 Guardian. * Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen. |
* Set up SR2 Guardian. |
Line 100: | Line 77: |
* Do buoyancy calculation (see LIGO-T1100616). | * Split SRx real-time models? |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-10-14
SRM (top priority)
- Main sequence
- Cable and test BF LVDT and FR.
- Adjust OSEMs laterally and in/out.
- Weigh BF/... section and adjust trim mass to fix pitch/roll.
- Anchor cables to BF cap.
- Install SF crossbars.
- Build up SS to SF ring.
- Bring in SF.
- Hook BF/... .
- PI
- Compress blades.
Choose and install CuBe spring.
- Replace yoke in F0.
- Install clamps on PI .
- Install LBB blade units on PI.
- Install geophone plates on PI.
SR2 (low priority)
- Add arc weights and geophones. (Might have to reserve one geophone for Fujii-Fun - check.)
- Test IP items.
- Geophones
- LVDTs
- Steppers
- Unlock and center IP.
- More TFs.
SR Prep Tasks - To Be Scheduled
Tunnel
- Add SR3 LBB ballast mass.
- Install SR3 LEN OL.
- Retrieve BNC-Lemo cable from Nakano-kun.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable SR3 PI yaw stepper.
- Correct flipped connections in SRM PI LVDTs.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Clean/Replace yoke in PI #2 for SRM.
- Install clamps on PI #2 for SRM.
- Install LBB blade units on PI #2 for SRM.
- Install geophone plates on PI #2 for SRM.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .