3112
Comment:
|
3282
|
Deletions are marked like this. | Additions are marked like this. |
Line 25: | Line 25: |
* Finish debugging BS BIO. * Make SR3, SR2, SRM like BS. |
|
Line 28: | Line 30: |
* Debug IP BIO connection. (Debug BS IP at the same time.) * Cable and test BF cap picos. * Build up security structure to SF level. * Crane in SF and remove cap. * Hook BF and adjust total ballast. |
* Install L-brackets on BF and SF rings. * Add extra spacers under SF to give more jack range. * Suspend BF/... section. * Adjust BF trim mass. |
Line 40: | Line 41: |
* Get Miyo-kun to set up software pico drivers for SR3_IM and SR3_BF. | * Set up software pico drivers for SR3_IM and SR3_BF. |
Line 43: | Line 44: |
* Characterize final F0 blades. | * Finish tuning F0 in PI #3. * Park PI #1 in SR3 AF. * Crane PI #3 behind SR3. * Crane PI #1 to factory area. * Build/tune F0 in PI #1. |
Line 45: | Line 50: |
=== 2018-06-11 === | ==== Software ==== * Split SRx real-time models? * Fix white channels on BS screens (will probably be an issue for SRx models if/when split). === 2018-06-18 === |
Line 49: | Line 57: |
* Rebuild F0 #3 for SR3. * Park F0 #1 (for SR2) in top of SR3 assembly frame. * Move F0 #3 behind SR3. * Make LBB blade sets (or at least 3 of 9). === 2018-06-18 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== |
* Wrap PI #1. * Crane PI #1 to SR2 AF. * Crane PI #3 into SR3 AF. * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-06-04
Main Sequence
- Debug stuff.
- Finish debugging BS BIO.
- Make SR3, SR2, SRM like BS.
- IM BIO connection is wrong. V goes H and H goes V.
- Swap the LPCD to HPCD.
- Check the payload so that it gives us the correct TF.
- Install L-brackets on BF and SF rings.
- Add extra spacers under SF to give more jack range.
- Suspend BF/... section.
- Adjust BF trim mass.
- Route cables through SF-BF flying saucer up to bottom of SF.
- Adjust BF trim mass.
- Readjust payload.
- Take TFs.
- Add budgeted ballast mass to SF.
- Cable, test SF LVDT and FR.
- Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
- Set up software pico drivers for SR3_IM and SR3_BF.
F0/LBB Stuff
- Finish tuning F0 in PI #3.
- Park PI #1 in SR3 AF.
- Crane PI #3 behind SR3.
- Crane PI #1 to factory area.
- Build/tune F0 in PI #1.
Software
- Split SRx real-time models?
- Fix white channels on BS screens (will probably be an issue for SRx models if/when split).
2018-06-18
Main Sequence
- SF/... TFs.
F0/LBB Stuff
- Wrap PI #1.
- Crane PI #1 to SR2 AF.
- Crane PI #3 into SR3 AF.
- Remove SR3 tank lid, crane LBB rings to top of lower half of the tank.
2018-06-25
Main Sequence
F0/LBB Stuff
2018-07-02
Main Sequence
F0/LBB Stuff
2018-07-09
Main Sequence
F0/LBB Stuff
2018-07-16
Main Sequence
F0/LBB Stuff
2018-07-23
Main Sequence
F0/LBB Stuff
SR Prep Tasks - To Be Scheduled
Tunnel
- Calibrate last six IM OSEMs.
- Install first set of LBB damper rings in SR3 tank.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- Finish half-completed geophones.
- Characterize final top filter blades (from 5/31).
- Rebuild filters in PIs #1 and #3.
- Install clamps on PIs #1 and #3.
- Install LBB units on PIs #1 and #3.
- Install correct IP in PI #3.
- Rebuild filter in PI #2.
- Install clamps on PI #2.
- Install LBB blade units on PI #2.
Mitaka or remotely
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review Shoda-san's Guardian.
- Review DIO stuff.
- Review DAC channel requests.
- Set up SR2 and SR3 Guardian.
- Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
- Install damping filters for SR2.
- Do buoyancy calculation (see LIGO-T1100616).
Ordering
See ../WishList .