Line 15: | Line 15: |
* Wipe ladders. | * Wipe ladders, assembly frame. |
Line 22: | Line 22: |
=== 2018-06-04 === | === 2018-07-09 === |
Line 24: | Line 24: |
* Debug stuff. * Finish debugging BS BIO. * Make SR3, SR2, SRM like BS. * IM BIO connection is wrong. V goes H and H goes V. * Swap the LPCD to HPCD. * Check the payload so that it gives us the correct TF. * Install L-brackets on BF and SF rings. * Add extra spacers under SF to give more jack range. * Suspend BF/... section. * Adjust BF trim mass. * Route cables through SF-BF flying saucer up to bottom of SF. * Adjust BF trim mass. * Readjust payload. * Take TFs. * Add budgeted ballast mass to SF. * Cable, test SF LVDT and FR. * Grab and configure a picomotor driver as SR2_BF 10.68.150.25. * Set up software pico drivers for SR3_IM and SR3_BF. * Replace ceramic thrust bearing in PI #3 with metal one (do PI #1 as well if time). |
* Get laser level, preferably the red Tajita one. * Put up second safety bar. * Retrieve BNC-Lemo cable from Nakano-kun. * Tune PI LVDT driver box. * Plug in spare sat amps. * Set up optical lever. * Check/restore alignment of payload, especially optic pitch. * Install and cable geophones. * Install arc weights. * Tune IP. * Install, cable PI yaw stepper. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. * Calibrate PI LVDTs and FRs. * Cabling, testing, TFs. |
Line 45: | Line 40: |
* Finish tuning F0 in PI #3. * Characterize more blades? * Park PI #1 in SR3 AF. * Crane PI #3 behind SR3. * Crane PI #1 to factory area. * Build/tune F0 in PI #1. |
* Finalize PI #1 for SR2; crane into SR2 cleanbooth. * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position. * Set tank jacks to nominal height. * Clear space for PI #2 (SRM) work. |
Line 52: | Line 45: |
==== Software ==== * Split SRx real-time models? * Fix white channels on BS screens (will probably be an issue for SRx models if/when split). === 2018-06-18 === ==== Main Sequence ==== * SF/... TFs. ==== F0/LBB Stuff ==== * Wrap PI #1. * Crane PI #1 to SR2 AF. * Crane PI #3 into SR3 AF. * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank. === 2018-06-25 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-02 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== === 2018-07-09 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== |
==== Software Etc ==== * Check S-numbers of BS sat amps and SR sat amps returned to Mozumi, and update electronic items lists. * Review/improve macro file fixes for split models; write klog; submit changes to SVN. * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function. * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually). * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen. |
Line 78: | Line 54: |
* Lock suspension. * Crane into tank. * Unlock suspension. * Rearrange cables. * Test. |
|
Line 79: | Line 60: |
=== 2018-07-23 === ==== Main Sequence ==== ==== F0/LBB Stuff ==== |
* Install correct IP in PI #2. * Crane PI #2 to second floor. * Rebuild top filter of PI #2. |
Line 89: | Line 68: |
* Grab and configure a picomotor driver as SR2_BF 10.68.150.25. * Get independent power supply for SR3 so SR2 can be powered back up. * Check SR2, SR3 TM coil gains for magnet polarity compensation. |
|
Line 90: | Line 72: |
* Install first set of LBB damper rings in SR3 tank. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * Finish half-completed geophones. * Characterize final top filter blades (from 5/31). * Rebuild filters in PIs #1 and #3. * Install clamps on PIs #1 and #3. * Install LBB units on PIs #1 and #3. * Install correct IP in PI #3. |
* Rebuild filter in PI #1. * Install clamps on PI #1. * Install geophone plates on PI #3. * Install geophone plates on PI #1. * Install correct IP in PI #2. |
Line 101: | Line 80: |
* Install geophone plates on PI #2. |
|
Line 109: | Line 90: |
* Set up SR2 and SR3 Guardian. * Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen. |
* Set up SR2 Guardian. |
Line 112: | Line 92: |
* Do buoyancy calculation (see LIGO-T1100616). | * Split SRx real-time models? |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-07-09
Main Sequence
- Get laser level, preferably the red Tajita one.
- Put up second safety bar.
- Retrieve BNC-Lemo cable from Nakano-kun.
- Tune PI LVDT driver box.
- Plug in spare sat amps.
- Set up optical lever.
- Check/restore alignment of payload, especially optic pitch.
- Install and cable geophones.
- Install arc weights.
- Tune IP.
- Install, cable PI yaw stepper.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM.
- Calibrate PI LVDTs and FRs.
- Cabling, testing, TFs.
F0/LBB Stuff
- Finalize PI #1 for SR2; crane into SR2 cleanbooth.
- Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
- Set tank jacks to nominal height.
- Clear space for PI #2 (SRM) work.
Software Etc
- Check S-numbers of BS sat amps and SR sat amps returned to Mozumi, and update electronic items lists.
- Review/improve macro file fixes for split models; write klog; submit changes to SVN.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
2018-07-16
Main Sequence
- Lock suspension.
- Crane into tank.
- Unlock suspension.
- Rearrange cables.
- Test.
F0/LBB Stuff
- Install correct IP in PI #2.
- Crane PI #2 to second floor.
- Rebuild top filter of PI #2.
SR Prep Tasks - To Be Scheduled
Tunnel
- Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
- Get independent power supply for SR3 so SR2 can be powered back up.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Calibrate last six IM OSEMs.
- Rebuild filter in PI #1.
- Install clamps on PI #1.
- Install geophone plates on PI #3.
- Install geophone plates on PI #1.
- Install correct IP in PI #2.
- Rebuild filter in PI #2.
- Install clamps on PI #2.
- Install LBB blade units on PI #2.
- Install geophone plates on PI #2.
Mitaka or remotely
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review Shoda-san's Guardian.
- Review DIO stuff.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .