Line 22: Line 22:
=== 2018-06-04 ===
=== 2018-06-18 ===
Line 24: Line 25:
 * Debug stuff.
  * --(Finish debugging BS BIO.)--
  * --(Make SR3, SR2, SRM like BS.)--
  * --(Swap the LPCD to HPCD.)--
  * --(Fix IM coil gains to compensate magnet polarities.)--
  * Check the payload so that it gives us the correct TF.
 * --(Install L-brackets on BF and SF rings.)--
 * --(Add extra spacers under SF to give more jack range.)--
 * --(Suspend BF/... section.)--
 * --(Adjust BF trim mass.)--
 * --(Route cables through SF-BF flying saucer up to bottom of SF.)--
 * Readjust BF trim mass.
 * Readjust payload.
 * Take TFs.
 * --(Add Cu ring, cable clamps to SF cap.)--
 * Add budgeted ballast mass to SF.
 * Cable, test SF LVDT and FR.
 * Tweak BF total trim masses.
 * SF/... TFs.
 * Add budgeted ballast mass to SF (or remove stuff!).
 * Cable, test SF FR.
Line 42: Line 30:
 * Set up software pico drivers for SR3_IM and SR3_BF.
 * Replace ceramic thrust bearing in PI #3 with metal one (do PI #1 as well if time).
 * Check JGWDoc electronic item lists are up to date.
Line 47: Line 34:
 * Replace ceramic thrust bearing in PI #3 with metal one (do PI #1 as well if time).
Line 51: Line 39:
 * Build/tune F0 in PI #1.
Line 54: Line 41:
 * Split SRx real-time models?
 * Fix white channels on BS screens (will probably be an issue for SRx models if/when split).
=== 2018-06-18 ===
 * Review/improve macro file fixes for split models; write klog; submit changes to SVN.
 * --(Install AC bandpass filters in SR3 WD filters.)--
 * --(Check coil filter gains for compensation of magnet polarities (confirm SR3 IM, set and confirm SR2 and SR3 TM).)--
 * Create software stepper drivers for SR3 and SRM and link to from STEP_MASTER.adl screen.
 * --(Fix link to SUS_CUS_BSFM_BIO.adl in VIS_CUST_TYPEB_OVERALL.adl.)--
 * --(Rename VIS_CUST_BS_BIO.adl screen to VIS_CUST_TYPEB_BIO.adl and adjust links.)--
 * --(Fix hardwiring to BS in VIS_CUST_TYPEB_IP_WD_AC_BANDLIM.adl (ACC H2 and ACC H3 sections).)--
 * --(Fix broken CD State field in VIS_CUST_TYPEB_OVERALL.adl.)--

=== 2018-06-25 ===
Line 58: Line 52:
 * SF/... TFs.
Line 60: Line 53:
 * Build/tune F0 in PI #1.
 * Finish tuning PI #3.
Line 63: Line 58:
 * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank.
 
=== 2018-06-25 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
==== Software/Remote ====
Line 90: Line 81:
 * Get independent power supply for SR3 so SR2 can be powered back up.
 * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
Line 92: Line 85:
 * Install first set of LBB damper rings in SR3 tank.
Line 94: Line 86:
 * Finish half-completed geophones.
 * Characterize final top filter blades (from 5/31).
* Rebuild filters in PIs #1 and #3.
 * Install clamps on PIs #1 and #3.
 * Install LBB units on PIs #1 and #3.
 * Install correct IP in PI #3.
 * Rebuild filter in PI #1.
 * Install clamps on PI #1.
* Install geophone plates on PI #3.
 * Install geophone plates on PI #1.
 * Install correct IP in PI #2.
Line 103: Line 94:
 * Install geophone plates on PI #2.
Line 115: Line 108:
 * Split SRx real-time models?

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-06-18

Main Sequence

  • Tweak BF total trim masses.
  • SF/... TFs.
  • Add budgeted ballast mass to SF (or remove stuff!).
  • Cable, test SF FR.
  • Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
  • Check JGWDoc electronic item lists are up to date.

F0/LBB Stuff

  • Finish tuning F0 in PI #3.
  • Replace ceramic thrust bearing in PI #3 with metal one (do PI #1 as well if time).
  • Characterize more blades?
  • Park PI #1 in SR3 AF.
  • Crane PI #3 behind SR3.
  • Crane PI #1 to factory area.

Software

  • Review/improve macro file fixes for split models; write klog; submit changes to SVN.
  • Install AC bandpass filters in SR3 WD filters.

  • Check coil filter gains for compensation of magnet polarities (confirm SR3 IM, set and confirm SR2 and SR3 TM).

  • Create software stepper drivers for SR3 and SRM and link to from STEP_MASTER.adl screen.
  • Fix link to SUS_CUS_BSFM_BIO.adl in VIS_CUST_TYPEB_OVERALL.adl.

  • Rename VIS_CUST_BS_BIO.adl screen to VIS_CUST_TYPEB_BIO.adl and adjust links.

  • Fix hardwiring to BS in VIS_CUST_TYPEB_IP_WD_AC_BANDLIM.adl (ACC H2 and ACC H3 sections).

  • Fix broken CD State field in VIS_CUST_TYPEB_OVERALL.adl.

2018-06-25

Main Sequence

F0/LBB Stuff

  • Build/tune F0 in PI #1.
  • Finish tuning PI #3.
  • Wrap PI #1.
  • Crane PI #1 to SR2 AF.
  • Crane PI #3 into SR3 AF.

Software/Remote

2018-07-02

Main Sequence

F0/LBB Stuff

2018-07-09

Main Sequence

F0/LBB Stuff

2018-07-16

Main Sequence

F0/LBB Stuff

2018-07-23

Main Sequence

F0/LBB Stuff

SR Prep Tasks - To Be Scheduled

Tunnel

  • Get independent power supply for SR3 so SR2 can be powered back up.
  • Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
  • Check SR2, SR3 TM coil gains for magnet polarity compensation.
  • Calibrate last six IM OSEMs.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • Rebuild filter in PI #1.
  • Install clamps on PI #1.
  • Install geophone plates on PI #3.
  • Install geophone plates on PI #1.
  • Install correct IP in PI #2.
  • Rebuild filter in PI #2.
  • Install clamps on PI #2.
  • Install LBB blade units on PI #2.
  • Install geophone plates on PI #2.

Mitaka or remotely

  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review Shoda-san's Guardian.
  • Review DIO stuff.
  • Review DAC channel requests.
  • Set up SR2 and SR3 Guardian.
  • Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
  • Install damping filters for SR2.
  • Do buoyancy calculation (see LIGO-T1100616).
  • Split SRx real-time models?

Ordering

See ../WishList .