Line 15: Line 15:
 * Wipe ladders.  * Wipe ladders, assembly frame.
Line 22: Line 22:
=== 2018-09-25 ===
==== Etc ====
Line 23: Line 25:
=== 2018-06-18 ===
==== Main Sequence ====
 * Tweak BF total trim masses.
 * SF/... TFs.
 * Add budgeted ballast mass to SF (or remove stuff!).
 * Cable, test SF FR.
 * Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
 * Check JGWDoc electronic item lists are up to date.
==== SR2 ====
 * Open tank and move feedthroughs.
 * Reconnect in-vacuum cables.
 * Move in-air cables, with priority on IM OSEMs, then IM picos and BF/SF GAS and FRs.
 * Remove IM-RM safety bar.
 * Unlock and realign SF/... section.
 * Add arc weights and geophones.
 * Unlock and center IP.
Line 32: Line 34:
==== F0/LBB Stuff ====
 * Finish tuning F0 in PI #3.
 * Replace ceramic thrust bearing in PI #3 with metal one (do PI #1 as well if time).
 * Characterize more blades?
 * Park PI #1 in SR3 AF.
 * Crane PI #3 behind SR3.
 * Crane PI #1 to factory area.
==== SRM ====
 * Add TM OSEM cables.
 * Set TM pitch and tighten clamps.
 * Set RM pitch and tighten clamps.
 * Remove winch system and restore items removed from top of IM.
 * Suspend and weigh IM/... section.
 * Add BF crossbars to SS.
 * Build up SS to BF level.
 * Suspend IM/... section and adjust ballast/trim masses.
 * Install feedthroughs on AF (3 available; need to get a 4th).
 * Arrange power to SRM rack and get it running.
 * Check the IRIG-B 9999xx fix has been applied (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php?r=6031||6031]]).
Line 40: Line 47:
==== Software ====
 * Review/improve macro file fixes for split models; write klog; submit changes to SVN.
 * Install AC bandpass filters in SR3 WD filters.
 * Check coil filter gains for compensation of magnet polarities (confirm SR3 IM, set and confirm SR2 and SR3 TM).
 * Create software stepper drivers for SR3 and SRM and link to from STEP_MASTER.adl screen.
==== SR3 ====
 * ''Don't even '''think''' about doing anything with SR3.''
Line 46: Line 50:
=== 2018-06-25 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
 * Build/tune F0 in PI #1.
 * Finish tuning PI #3.
 * Wrap PI #1.
 * Crane PI #1 to SR2 AF.
 * Crane PI #3 into SR3 AF.
==== Software/Remote ====

=== 2018-07-02 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-07-09 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-07-16 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-07-23 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 77: Line 55:
 * Get independent power supply for SR3 so SR2 can be powered back up.
 * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
 * Add SR3 LBB ballast mass.
 * Install SR3 LEN OL.
 * Rebuild PI #2 F0 for SRM.
 * Retrieve BNC-Lemo cable from Nakano-kun.
 * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
 * Install, cable SR3 PI yaw stepper.
 * Correct flipped connections in SRM PI LVDTs.
 * Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
Line 80: Line 64:
 * Calibrate last six IM OSEMs.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
 * Rebuild filter in PI #1.
 * Install clamps on PI #1.
 * Install geophone plates on PI #3.
 * Install geophone plates on PI #1.
 * Install correct IP in PI #2.
 * Rebuild filter in PI #2.
 * Install clamps on PI #2.
 * Install LBB blade units on PI #2.
 * Install geophone plates on PI #2.
 * Rebuild filter in PI #2 for SRM.
 * Clean/Replace yoke in PI #2 for SRM.
 * Install clamps on PI #2 for SRM.
 * Install LBB blade units on PI #2 for SRM.
 * Install geophone plates on PI #2 for SRM.
 * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Line 93: Line 72:
 * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
 * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
Line 97: Line 78:
 * Review Shoda-san's Guardian.
 * Review DIO stuff.
Line 100: Line 79:
 * Set up SR2 and SR3 Guardian.
 * Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
 * Set up SR2 Guardian.
Line 103: Line 81:
 * Do buoyancy calculation (see LIGO-T1100616).

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders, assembly frame.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-09-25

Etc

SR2

  • Open tank and move feedthroughs.
  • Reconnect in-vacuum cables.
  • Move in-air cables, with priority on IM OSEMs, then IM picos and BF/SF GAS and FRs.
  • Remove IM-RM safety bar.
  • Unlock and realign SF/... section.
  • Add arc weights and geophones.
  • Unlock and center IP.

SRM

  • Add TM OSEM cables.
  • Set TM pitch and tighten clamps.
  • Set RM pitch and tighten clamps.
  • Remove winch system and restore items removed from top of IM.
  • Suspend and weigh IM/... section.
  • Add BF crossbars to SS.
  • Build up SS to BF level.
  • Suspend IM/... section and adjust ballast/trim masses.
  • Install feedthroughs on AF (3 available; need to get a 4th).
  • Arrange power to SRM rack and get it running.
  • Check the IRIG-B 9999xx fix has been applied (klog http://klog.icrr.u-tokyo.ac.jp/osl/index.php?r=6031).

SR3

  • Don't even think about doing anything with SR3.

SR Prep Tasks - To Be Scheduled

Tunnel

  • Add SR3 LBB ballast mass.
  • Install SR3 LEN OL.
  • Rebuild PI #2 F0 for SRM.
  • Retrieve BNC-Lemo cable from Nakano-kun.
  • Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
  • Install, cable SR3 PI yaw stepper.
  • Correct flipped connections in SRM PI LVDTs.
  • Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
  • Check SR2, SR3 TM coil gains for magnet polarity compensation.
  • Rebuild filter in PI #2 for SRM.
  • Clean/Replace yoke in PI #2 for SRM.
  • Install clamps on PI #2 for SRM.
  • Install LBB blade units on PI #2 for SRM.
  • Install geophone plates on PI #2 for SRM.
  • Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

Mitaka or remotely

  • Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
  • Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review DAC channel requests.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Split SRx real-time models?

Ordering