 * Wipe ladders.  * Wipe ladders, assembly frame.
Line 22: Line 22:
=== 2018-08-15 ===
==== SR3 ====
 * Controls work (Enzo and team).
 * Diagonalize OL (Terrence).
 * Do SF damper test (Hatoya-san).
 * Tune IP (Fujii-kun).
Line 23: Line 29:
=== 2018-07-02 ===
==== Main Sequence ====
 * Install, cable PI yaw stepper.
 * Decide whether to install ballast mass inside SF.
 * Install SF ballast mass inside or on top, less reserve for cables.
 * Route cables around SF up to flying saucer and PI.
 * Finalize SF trim mass.
 * Install and cable geophones.
 * Install arc weights.
 * Unclamp assembly frame at IM level.
 * Unlock and center IP.
 * Calibrate horizontal LVDTs.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Create software stepper drivers for SR3 and SRM and link to from STEP_MASTER.adl screen.
=== 2018-08-20 ===
==== SR3 ====
 * Hook LBB, add ballast mass.
 * Tune IP.
Line 38: Line 34:
==== F0/LBB Stuff ====
 * Characterize more blades?
 * Build filter in PI #1 for SR2.
 * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
==== SR2 ====
 * Adjust ballast/trim mass, with reserve for yaw stepper.
 * Cable/test PI items (LVDTs, steppers, geophones).
 * Set damper height.
 * Add arc weights, adjust IP.
 * Stage LBB damper rings in tank.
 
==== SRM ====
 * Check gluing result - redo if necessary.
 * Assemble RM.
 * Add IM ballast masses (we forgot this before).
 * Get parts from AOL and set up new pitch-setting OL.
 * Hang metal mass.
 * Hang RM.
Line 43: Line 49:
==== Software ====
 * Review/improve macro file fixes for split models; write klog; submit changes to SVN.
 * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
 * Create Python drivers for SR3_IM and SR3_BF steppers and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.


=== 2018-07-09 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
==== Software Etc ====
Line 57: Line 55:
 * Rebuild PI #2 F0 for SRM.
 * Retrieve BNC-Lemo cable from Nakano-kun.
 * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
 * Install, cable SR3 PI yaw stepper.
 * Correct flipped connections in SRM PI LVDTs.
Line 58: Line 61:
 * Get independent power supply for SR3 so SR2 can be powered back up.
Line 61: Line 63:
 * Rebuild filter in PI #1.
 * Install clamps on PI #1.
 * Install geophone plates on PI #3.
 * Install geophone plates on PI #1.
 * Install correct IP in PI #2.
 * Rebuild filter in PI #2.
 * Install clamps on PI #2.
 * Install LBB blade units on PI #2.
 * Install geophone plates on PI #2.
 * Install geophone plates on PI #1 for SR2.
 * Rebuild filter in PI #2 for SRM.
 * Install clamps on PI #2 for SRM.
 * Install LBB blade units on PI #2 for SRM.
 * Install geophone plates on PI #2 for SRM.
 * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Line 72: Line 71:
 * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
 * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
Line 76: Line 77:
 * Review Shoda-san's Guardian.
 * Review DIO stuff.

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders, assembly frame.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-08-15

SR3

  • Controls work (Enzo and team).
  • Diagonalize OL (Terrence).
  • Do SF damper test (Hatoya-san).
  • Tune IP (Fujii-kun).

2018-08-20

SR3

  • Hook LBB, add ballast mass.
  • Tune IP.

SR2

  • Adjust ballast/trim mass, with reserve for yaw stepper.
  • Cable/test PI items (LVDTs, steppers, geophones).
  • Set damper height.
  • Add arc weights, adjust IP.
  • Stage LBB damper rings in tank.

SRM

  • Check gluing result - redo if necessary.
  • Assemble RM.
  • Add IM ballast masses (we forgot this before).
  • Get parts from AOL and set up new pitch-setting OL.
  • Hang metal mass.
  • Hang RM.

Software Etc

SR Prep Tasks - To Be Scheduled

Tunnel

  • Rebuild PI #2 F0 for SRM.
  • Retrieve BNC-Lemo cable from Nakano-kun.
  • Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
  • Install, cable SR3 PI yaw stepper.
  • Correct flipped connections in SRM PI LVDTs.
  • Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
  • Check SR2, SR3 TM coil gains for magnet polarity compensation.
  • Calibrate last six IM OSEMs.
  • Install geophone plates on PI #1 for SR2.
  • Rebuild filter in PI #2 for SRM.
  • Install clamps on PI #2 for SRM.
  • Install LBB blade units on PI #2 for SRM.
  • Install geophone plates on PI #2 for SRM.
  • Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

Mitaka or remotely

  • Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
  • Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review DAC channel requests.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Split SRx real-time models?

Ordering

See ../WishList .