Line 15: Line 15:
 * Wipe ladders.  * Wipe ladders, assembly frame.
Line 22: Line 22:
=== 2018-09-03 ===
==== Etc ====
 * Check SR2-SR3 duct (since Mirapro moved it) to see if we have adequate space at both ends.
 * Help crane inspectors on Monday and Wednesday mornings.
 * Shut down all electronics before leaving on Friday.
 * Update electronics items lists to reflect removed ADC stuff.
 * Inspect all crane slot curtains (SR, BS, PR), note which are missing, and decide which should be closed up immediately versus later. (For example, SR2 and SR3 have missing curtains that could be replaced semi-permanently because we probably don't need to crane stuff into those areas anymore.)
Line 23: Line 30:
=== 2018-07-02 ===
==== Main Sequence ====
 * Install, cable PI yaw stepper.
 * Decide whether to install ballast mass inside SF.
 * Install SF ballast mass inside or on top, less reserve for cables.
 * Route cables around SF up to flying saucer and PI.
 * Finalize SF trim mass.
 * Install and cable geophones.
 * Install arc weights.
 * Unclamp assembly frame at IM level.
 * Unlock and center IP.
 * Calibrate horizontal LVDTs.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Create software stepper drivers for SR3 and SRM and link to from STEP_MASTER.adl screen.
==== SR2 ====
 * Cable/test PI items (LVDTs, steppers, geophones).
 * Finish in-air cabling.
 * Do basic go/no-go test of electronic items.
 * Adjust ballast/trim mass of SF, with reserve for yaw stepper.
 * Check alignment of chain and security structure.
 * Center all IP FRs.
 * Add arc weights and geophones and center IP.
 * Set damper height.
 * Crane suspension into tank
 
==== SRM ====
 * Set up pitch-setting OL.
 * Add TM OSEM cables.
 * Set TM pitch and tighten clamps.
 * Set RM pitch and tighten clamps.
 * Remove winch system and restore items removed from top of IM.
 * Install feedthroughs on AF.
 * Fire up SRM rack.
Line 38: Line 50:
==== F0/LBB Stuff ====
 * Characterize more blades?
 * Build filter in PI #1 for SR2.
 * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
==== SR3 ====
Line 43: Line 52:
==== Software ====
 * Review/improve macro file fixes for split models; write klog; submit changes to SVN.
 * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
 * Create Python drivers for SR3_IM and SR3_BF steppers and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.


=== 2018-07-09 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
 
Line 57: Line 58:
 * Add SR3 LBB ballast mass.
 * Install SR3 LEN OL.
 * Rebuild PI #2 F0 for SRM.
 * Retrieve BNC-Lemo cable from Nakano-kun.
 * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
 * Install, cable SR3 PI yaw stepper.
 * Correct flipped connections in SRM PI LVDTs.
Line 58: Line 66:
 * Get independent power supply for SR3 so SR2 can be powered back up.
Line 61: Line 68:
 * Rebuild filter in PI #1.
 * Install clamps on PI #1.
 * Install geophone plates on PI #3.
 * Install geophone plates on PI #1.
 * Install correct IP in PI #2.
 * Rebuild filter in PI #2.
 * Install clamps on PI #2.
 * Install LBB blade units on PI #2.
 * Install geophone plates on PI #2.
 * Install geophone plates on PI #1 for SR2.
 * Rebuild filter in PI #2 for SRM.
 * Install clamps on PI #2 for SRM.
 * Install LBB blade units on PI #2 for SRM.
 * Install geophone plates on PI #2 for SRM.
 * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Line 72: Line 76:
 * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
 * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
Line 76: Line 82:
 * Review Shoda-san's Guardian.
 * Review DIO stuff.

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders, assembly frame.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-09-03

Etc

  • Check SR2-SR3 duct (since Mirapro moved it) to see if we have adequate space at both ends.
  • Help crane inspectors on Monday and Wednesday mornings.
  • Shut down all electronics before leaving on Friday.
  • Update electronics items lists to reflect removed ADC stuff.
  • Inspect all crane slot curtains (SR, BS, PR), note which are missing, and decide which should be closed up immediately versus later. (For example, SR2 and SR3 have missing curtains that could be replaced semi-permanently because we probably don't need to crane stuff into those areas anymore.)

SR2

  • Cable/test PI items (LVDTs, steppers, geophones).
  • Finish in-air cabling.
  • Do basic go/no-go test of electronic items.
  • Adjust ballast/trim mass of SF, with reserve for yaw stepper.
  • Check alignment of chain and security structure.
  • Center all IP FRs.
  • Add arc weights and geophones and center IP.
  • Set damper height.
  • Crane suspension into tank

SRM

  • Set up pitch-setting OL.
  • Add TM OSEM cables.
  • Set TM pitch and tighten clamps.
  • Set RM pitch and tighten clamps.
  • Remove winch system and restore items removed from top of IM.
  • Install feedthroughs on AF.
  • Fire up SRM rack.

SR3

SR Prep Tasks - To Be Scheduled

Tunnel

  • Add SR3 LBB ballast mass.
  • Install SR3 LEN OL.
  • Rebuild PI #2 F0 for SRM.
  • Retrieve BNC-Lemo cable from Nakano-kun.
  • Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
  • Install, cable SR3 PI yaw stepper.
  • Correct flipped connections in SRM PI LVDTs.
  • Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
  • Check SR2, SR3 TM coil gains for magnet polarity compensation.
  • Calibrate last six IM OSEMs.
  • Install geophone plates on PI #1 for SR2.
  • Rebuild filter in PI #2 for SRM.
  • Install clamps on PI #2 for SRM.
  • Install LBB blade units on PI #2 for SRM.
  • Install geophone plates on PI #2 for SRM.
  • Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

Mitaka or remotely

  • Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
  • Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review DAC channel requests.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Split SRx real-time models?

Ordering

See ../WishList .