Differences between revisions 76 and 132 (spanning 56 versions)
Revision 76 as of 2018-07-06 14:08:26
Size: 2925
Editor: MarkBarton
Comment:
Revision 132 as of 2019-01-04 15:25:56
Size: 178
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
[[KAGRA/Subgroups/VIS/TypeB/ToDoOldSR|Archived To-Do Items]]
Line 4: Line 3:
[[#EveryWeek|Every Week]] This list has been merged into the common Type B list: [[../ToDo]].
Line 6: Line 5:
[[#ComingWeeks|Coming Weeks]]

[[#SRPrepTasks|Preparation for SR Installation]]

<<Anchor(EveryWeek)>>

== Every Week ==
==== Facilities ====
 * Vacuum and roll floor.
 * Wipe ladders.
 * Tidy tools, parts.
 * Get stuff from ../WishList

<<Anchor(ComingWeeks)>>
== Coming Weeks ==

=== 2018-07-09 ===
==== Main Sequence ====
 * Check/restore alignment of payload, especially optic pitch.
 * Install and cable geophones.
 * Install arc weights.
 * Tune IP.
 * Install, cable PI yaw stepper.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Calibrate PI LVDTs and FRs.
 * Cabling, testing, TFs.

==== F0/LBB Stuff ====
 * Finalize PI #1 for SR2; crane into SR2 cleanbooth.
 * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
 * Set tank jacks to nominal height.
 * Clear space for PI #2 (SRM) work.

==== Software Etc ====
 * Review/improve macro file fixes for split models; write klog; submit changes to SVN.
 * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
 * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
 * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.


=== 2018-07-16 ===
==== Main Sequence ====
 * Lock suspension.
 * Crane into tank.
 * Unlock suspension.
 * Rearrange cables.
 * Test.
==== F0/LBB Stuff ====
 * Install correct IP in PI #2.
 * Crane PI #2 to second floor.
 * Rebuild top filter of PI #2.

<<Anchor(SRPrepTasks)>>

== SR Prep Tasks - To Be Scheduled ==
=== Tunnel ===
 * Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
 * Get independent power supply for SR3 so SR2 can be powered back up.
 * Check SR2, SR3 TM coil gains for magnet polarity compensation.
 * Calibrate last six IM OSEMs.
 * Rebuild filter in PI #1.
 * Install clamps on PI #1.
 * Install geophone plates on PI #3.
 * Install geophone plates on PI #1.
 * Install correct IP in PI #2.
 * Rebuild filter in PI #2.
 * Install clamps on PI #2.
 * Install LBB blade units on PI #2.
 * Install geophone plates on PI #2.

=== Mitaka or remotely ===
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
 * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
 * Set up SR2 Guardian.
 * Install damping filters for SR2.
 * Review Shoda-san's Guardian.
 * Review DIO stuff.
 * Review DAC channel requests.
 * Set up SR2 Guardian.
 * Install damping filters for SR2.
 * Split SRx real-time models?

=== Ordering ===
See ../WishList .
[[KAGRA/Subgroups/VIS/TypeB/ToDoOldSR|Archived SR To-Do Items]]

VIS Type B SR Near Term To-Do List

This list has been merged into the common Type B list: ../ToDo.

Archived SR To-Do Items

KAGRA/Subgroups/VIS/TypeB/ToDoSR (last edited 2019-01-04 15:25:56 by MarkBarton)