* Wipe ladders. | * Wipe ladders, assembly frame. |
Line 22: | Line 22: |
=== 2018-07-09 === ==== Main Sequence ==== * Retrieve BNC-Lemo cable from Nakano-kun. * Check/restore alignment of payload, especially optic pitch. * Install and cable geophones. * Install arc weights. * Tune IP. * Install, cable PI yaw stepper. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. * Calibrate PI LVDTs and FRs. * Cabling, testing, TFs. |
=== 2018-08-27 === ==== SR3 ==== * Hook LBB, add ballast mass (Hirata-san++). * Tune IP (Fujii-kun). * Install LEN OL. |
Line 34: | Line 28: |
==== F0/LBB Stuff ==== * Finalize PI #1 for SR2; crane into SR2 cleanbooth. * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position. * Set tank jacks to nominal height. * Clear space for PI #2 (SRM) work. |
==== SR2 ==== * Adjust ballast/trim mass, with reserve for yaw stepper. * Cable/test PI items (LVDTs, steppers, geophones; Kozu-kun++). * Set damper height. * Add arc weights, adjust IP. ==== SRM ==== * --(Get feedthroughs)--. * Get arc weights. * Install feedthroughs on AF. * Set up pitch-setting OL. * Add TM OSEM cables. * Set TM pitch and tighten clamps. * Set RM pitch and tighten clamps. * Remove winch system and restore items removed from top of IM. * Fire up SRM rack. * ==== Etc ==== |
Line 40: | Line 47: |
==== Software Etc ==== * Review/improve macro file fixes for split models; write klog; submit changes to SVN. * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function. * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually). * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen. === 2018-07-16 === ==== Main Sequence ==== * Lock suspension. * Crane into tank. * Unlock suspension. * Rearrange cables. * Test. ==== F0/LBB Stuff ==== * Install correct IP in PI #2. * Crane PI #2 to second floor. * Rebuild top filter of PI #2. |
* Update electronics items lists to reflect removed ADC stuff. |
Line 63: | Line 53: |
* Rebuild PI #2 F0 for SRM. * Retrieve BNC-Lemo cable from Nakano-kun. * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function. * Install, cable SR3 PI yaw stepper. * Correct flipped connections in SRM PI LVDTs. |
|
Line 64: | Line 59: |
* Get independent power supply for SR3 so SR2 can be powered back up. | |
Line 67: | Line 61: |
* Rebuild filter in PI #1. * Install clamps on PI #1. * Install geophone plates on PI #3. * Install geophone plates on PI #1. * Install correct IP in PI #2. * Rebuild filter in PI #2. * Install clamps on PI #2. * Install LBB blade units on PI #2. * Install geophone plates on PI #2. |
* Install geophone plates on PI #1 for SR2. * Rebuild filter in PI #2 for SRM. * Install clamps on PI #2 for SRM. * Install LBB blade units on PI #2 for SRM. * Install geophone plates on PI #2 for SRM. * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2. |
Line 78: | Line 69: |
* Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually). * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen. |
|
Line 82: | Line 75: |
* Review Shoda-san's Guardian. * Review DIO stuff. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-08-27
SR3
- Hook LBB, add ballast mass (Hirata-san++).
- Tune IP (Fujii-kun).
- Install LEN OL.
SR2
- Adjust ballast/trim mass, with reserve for yaw stepper.
- Cable/test PI items (LVDTs, steppers, geophones; Kozu-kun++).
- Set damper height.
- Add arc weights, adjust IP.
SRM
Get feedthroughs.
- Get arc weights.
- Install feedthroughs on AF.
- Set up pitch-setting OL.
- Add TM OSEM cables.
- Set TM pitch and tighten clamps.
- Set RM pitch and tighten clamps.
- Remove winch system and restore items removed from top of IM.
- Fire up SRM rack.
Etc
- Update electronics items lists to reflect removed ADC stuff.
SR Prep Tasks - To Be Scheduled
Tunnel
- Rebuild PI #2 F0 for SRM.
- Retrieve BNC-Lemo cable from Nakano-kun.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable SR3 PI yaw stepper.
- Correct flipped connections in SRM PI LVDTs.
- Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Calibrate last six IM OSEMs.
- Install geophone plates on PI #1 for SR2.
- Rebuild filter in PI #2 for SRM.
- Install clamps on PI #2 for SRM.
- Install LBB blade units on PI #2 for SRM.
- Install geophone plates on PI #2 for SRM.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering