Line 22: Line 22:
=== 2018-07-09 ===
 * Put up second safety bar.
 * Retrieve BNC-Lemo cable from Nakano-kun.
==== Main Sequence ====
 * Find LBB damper rods and associated parts.
 * Set tank jacks to nominal height (50 mm).
 * Check/restore verticality of security structure.
 * Set SF damper magnet ring height.
 * Calibrate F0 LVDT actuation and FR.
 * Calibrate PI LVDTs and FRs.
 * Cable geophones (temporary routing OK).
 * Set up optical lever.
 * Check/restore alignment of payload, especially optic pitch.
 * Do token TFs (time permitting).
 * Reset all PI FRs to midrange.
 * Lock F0 keystone.
 * Lock suspension laterally except for SF level.
 * Add IM-RM safety bar?
 * Disconnect all cables at inside of feedthroughs.
 * Find LBB damper rods and associated parts.
 * Remove top of tank (including service ring).
 * Set tank jacks to nominal height (50 mm).
 * Lift suspension.
 * Install LBB damper rods.
 * Crane suspension into tank.
 * Hook LBB damper rods.
 * Replace tank lid and service ring.
 * Remove tank lid leaving service ring.
 * Move feedthroughs.
 * Move cables over.
 * Remove safety bar and unlock suspension.
 * Remove First Contact?
 * Restore payload alignment, especially pitch.
 * TFs!
=== 2018-09-03 ===
==== Etc ====
 * Check SR2-SR3 duct (since Mirapro moved it) to see if we have adequate space at both ends.
 * Help crane inspectors on Monday and Wednesday mornings.
 * Shut down all electronics before leaving on Friday.
 * Update electronics items lists to reflect removed ADC stuff.
 * Inspect all crane slot curtains (SR, BS, PR), note which are missing, and decide which should be closed up immediately versus later. (For example, SR2 and SR3 have missing curtains that could be replaced semi-permanently because we probably don't need to crane stuff into those areas anymore.)
Line 57: Line 30:
==== F0/LBB/Tank Stuff ====
 * Add LBB ballast masses.
 * Help Sato-san with swapping IP in PI #2.
 * Crane IP to second floor.
 * Rebuild PI #2 F0.
==== SR2 (highest priority) ====
 * Cable/test PI items (LVDTs, steppers, geophones).
 * Finish in-air cabling.
 * Do basic go/no-go test of electronic items.
 * Adjust ballast/trim mass of SF, with reserve for yaw stepper.
 * Check alignment of chain and security structure.
 * Center all IP FRs.
 * Add arc weights and geophones and center IP.
 * Set damper height.
 * Crane suspension into tank
 
==== SRM (as time permits) ====
 * Set up pitch-setting OL.
 * Add TM OSEM cables.
 * Set TM pitch and tighten clamps.
 * Set RM pitch and tighten clamps.
 * Remove winch system and restore items removed from top of IM.
 * Install feedthroughs on AF.
 * Fire up SRM rack.
Line 63: Line 50:
==== Software Etc ==== ==== SR3 ====

 
Line 69: Line 58:
 * Add SR3 LBB ballast mass.
 * Install SR3 LEN OL.
 * Rebuild PI #2 F0 for SRM.
 * Retrieve BNC-Lemo cable from Nakano-kun.
Line 71: Line 64:
 * Correct flipped connections in SR2 PI LVDTs.
Line 74: Line 66:
 * Get independent power supply for SR3 so SR2 can be powered back up.
Line 77: Line 68:
 * Rebuild filter in PI #1.
 * Install clamps on PI #1.
 * Install geophone plates on PI #3.
 * Install geophone plates on PI #1.
 * Install correct IP in PI #2.
 * Rebuild filter in PI #2.
 * Install clamps on PI #2.
 * Install LBB blade units on PI #2.
 * Install geophone plates on PI #2.
 * Install geophone plates on PI #1 for SR2.
 * Rebuild filter in PI #2 for SRM.
 * Install clamps on PI #2 for SRM.
 * Install LBB blade units on PI #2 for SRM.
 * Install geophone plates on PI #2 for SRM.
 * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders, assembly frame.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-09-03

Etc

  • Check SR2-SR3 duct (since Mirapro moved it) to see if we have adequate space at both ends.
  • Help crane inspectors on Monday and Wednesday mornings.
  • Shut down all electronics before leaving on Friday.
  • Update electronics items lists to reflect removed ADC stuff.
  • Inspect all crane slot curtains (SR, BS, PR), note which are missing, and decide which should be closed up immediately versus later. (For example, SR2 and SR3 have missing curtains that could be replaced semi-permanently because we probably don't need to crane stuff into those areas anymore.)

SR2 (highest priority)

  • Cable/test PI items (LVDTs, steppers, geophones).
  • Finish in-air cabling.
  • Do basic go/no-go test of electronic items.
  • Adjust ballast/trim mass of SF, with reserve for yaw stepper.
  • Check alignment of chain and security structure.
  • Center all IP FRs.
  • Add arc weights and geophones and center IP.
  • Set damper height.
  • Crane suspension into tank

SRM (as time permits)

  • Set up pitch-setting OL.
  • Add TM OSEM cables.
  • Set TM pitch and tighten clamps.
  • Set RM pitch and tighten clamps.
  • Remove winch system and restore items removed from top of IM.
  • Install feedthroughs on AF.
  • Fire up SRM rack.

SR3

SR Prep Tasks - To Be Scheduled

Tunnel

  • Add SR3 LBB ballast mass.
  • Install SR3 LEN OL.
  • Rebuild PI #2 F0 for SRM.
  • Retrieve BNC-Lemo cable from Nakano-kun.
  • Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
  • Install, cable SR3 PI yaw stepper.
  • Correct flipped connections in SRM PI LVDTs.
  • Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
  • Check SR2, SR3 TM coil gains for magnet polarity compensation.
  • Calibrate last six IM OSEMs.
  • Install geophone plates on PI #1 for SR2.
  • Rebuild filter in PI #2 for SRM.
  • Install clamps on PI #2 for SRM.
  • Install LBB blade units on PI #2 for SRM.
  • Install geophone plates on PI #2 for SRM.
  • Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

Mitaka or remotely

  • Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
  • Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review DAC channel requests.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Split SRx real-time models?