=== 2018-07-17 === ==== Main Sequence ==== * Find LBB damper rods and associated parts. * Set tank jacks to nominal height (50 mm). * --(Check/restore verticality of security structure.)-- * Set SF damper magnet ring height. * --(Check/correct IP LVDT polarities.)-- * Calibrate F0 LVDT actuation and FR. * Calibrate IP LVDTs and FRs. * Cable geophones (temporary routing OK). * Set up optical lever. * Check/restore alignment of payload, especially optic pitch. * Do token TFs (time permitting). * Reset all PI FRs to midrange. * Lock F0 keystone. * Lock suspension laterally except for SF level. * Add IM-RM safety bar? * Disconnect all cables at inside of feedthroughs. * Find LBB damper rods and associated parts. * Remove top of tank (including service ring). * Set tank jacks to nominal height (50 mm). * Lift suspension. * Install LBB damper rods. * Crane suspension into tank. * Hook LBB damper rods. * Replace tank lid and service ring. * Remove tank lid leaving service ring. * Move feedthroughs. * Move cables over. * Remove safety bar and unlock suspension. * Remove First Contact? * Restore payload alignment, especially pitch. * TFs! |
=== 2018-12-10 === ==== SRM high priority ==== * Get LBB damper rods ready. * Do final check of optic pitch and suspension health. * Lock suspension everywhere except SF level. * Install IM-RM safety bar. * Remove arc weights and geophones. * Blow dust off with airgun. * Remove all pink tape, Kapton tape and writing on items. * Disconnect cables. * Remove tank lid + service ring. * Crane suspension into tank, adding LBB damper rods and hooking LBB damper. * Add tank lid + service ring. * Put safety tape and/or crossbars on assembly frame. |
Line 56: | Line 37: |
==== F0/LBB/Tank Stuff ==== * Add LBB ballast masses. * Help Sato-san with swapping IP in PI #2. * Crane IP to second floor. * Rebuild PI #2 F0. |
==== SR3 ==== * Install/test new yaw mechanism. * Adjust height. * Realign OL. |
Line 62: | Line 42: |
==== Software Etc ==== | ==== SR2 ==== * Install/test new yaw adjuster. * Adjust height. * Get top plate reduced? * Set up OL cabling. * Set up OL. * Remove tape, writing etc on PI and PI items. === 2018-12-17 === ==== SRM ==== * Remove tank lid without service ring. * Remove First Contact. * Remove safety bar. * Unlock suspension (except for IP) and check alignment. * Move feedthroughs and in-air cabling over. * Test all electronics, starting with payload items. * Install/test new yaw mechanism. * Adjust height. * Check/adjust optic pitch; release LED to SR2. * Install Enomoto-kun's beam target plate (if available). * Install extension cord for pico drivers. * Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.) * Find one geophone cable ordered for SRM but missing. * Rearrange miswired geophone cable. * Rebuild defective geophone cable. * Seal geophones. * Install geophones and arc weights. * Center IP. ==== SR2 ==== * Add new feedthrough to lower part of tank (with Izumi-san-tachi)? * Install cable for MIF pico on LBB (with Izumi-san-tachi)? * Add ballast mass to LBB. |
Line 68: | Line 80: |
* Retrieve BNC-Lemo cable from Nakano-kun. | * Check which LVDT cards are in which boxes. |
Line 70: | Line 82: |
* Install, cable SR3 PI yaw stepper. * Correct flipped connections in SR2 PI LVDTs. * Correct flipped connections in SRM PI LVDTs. * Grab and configure a picomotor driver as SR2_BF 10.68.150.25. * Get independent power supply for SR3 so SR2 can be powered back up. |
|
Line 76: | Line 83: |
* Calibrate last six IM OSEMs. * Rebuild filter in PI #1. * Install clamps on PI #1. * Install geophone plates on PI #3. * Install geophone plates on PI #1. * Install correct IP in PI #2. * Rebuild filter in PI #2. * Install clamps on PI #2. * Install LBB blade units on PI #2. * Install geophone plates on PI #2. |
|
Line 90: | Line 87: |
* Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] |
|
Line 93: | Line 88: |
* Set up SR2 Guardian. | |
Line 96: | Line 90: |
* Set up SR2 Guardian. * Install damping filters for SR2. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-12-10
SRM high priority
- Get LBB damper rods ready.
- Do final check of optic pitch and suspension health.
- Lock suspension everywhere except SF level.
- Install IM-RM safety bar.
- Remove arc weights and geophones.
- Blow dust off with airgun.
- Remove all pink tape, Kapton tape and writing on items.
- Disconnect cables.
- Remove tank lid + service ring.
- Crane suspension into tank, adding LBB damper rods and hooking LBB damper.
- Add tank lid + service ring.
- Put safety tape and/or crossbars on assembly frame.
SR3
- Install/test new yaw mechanism.
- Adjust height.
- Realign OL.
SR2
- Install/test new yaw adjuster.
- Adjust height.
- Get top plate reduced?
- Set up OL cabling.
- Set up OL.
- Remove tape, writing etc on PI and PI items.
2018-12-17
SRM
- Remove tank lid without service ring.
- Remove First Contact.
- Remove safety bar.
- Unlock suspension (except for IP) and check alignment.
- Move feedthroughs and in-air cabling over.
- Test all electronics, starting with payload items.
- Install/test new yaw mechanism.
- Adjust height.
- Check/adjust optic pitch; release LED to SR2.
- Install Enomoto-kun's beam target plate (if available).
- Install extension cord for pico drivers.
- Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.)
- Find one geophone cable ordered for SRM but missing.
- Rearrange miswired geophone cable.
- Rebuild defective geophone cable.
- Seal geophones.
- Install geophones and arc weights.
- Center IP.
SR2
- Add new feedthrough to lower part of tank (with Izumi-san-tachi)?
- Install cable for MIF pico on LBB (with Izumi-san-tachi)?
- Add ballast mass to LBB.
SR Prep Tasks - To Be Scheduled
Tunnel
- Check which LVDT cards are in which boxes.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Install damping filters for SR2.
- Review DAC channel requests.
- Split SRx real-time models?
Ordering
See ../WishList .