VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-07-17
Main Sequence
Find LBB damper rods and associated parts.
Check/restore verticality of security structure.
Set SF damper magnet ring height.
Check/correct IP LVDT polarities.
Calibrate IP FR sensing.
- Calibrate F0 LVDT actuation and FR.
- Set safety screw and safety nut on F0 keystone; remove Kapton tape.
- Set up optical lever.
- Check/restore alignment of payload, especially optic pitch.
- Do token TFs (time permitting).
- Reset all PI FRs to midrange.
- Lock F0 keystone.
- Lock suspension laterally except for SF level.
- Add IM-RM safety bar?
- Disconnect all cables at inside of feedthroughs.
- Remove top of tank (including service ring).
- Set tank jacks to nominal height (50 mm).
- Lift suspension.
- Install LBB damper rods.
- Crane suspension into tank.
- Hook LBB damper rods.
- Replace tank lid and service ring.
- Remove tank lid leaving service ring.
- Move feedthroughs.
- Move cables over.
- Remove safety bar and unlock suspension.
- Remove First Contact?
- Restore payload alignment, especially pitch.
- Cable geophones.
- Calibrate IP LVDT and FR actuation.
- TFs!
F0/LBB/Tank Stuff
- Add LBB ballast masses.
- Help Sato-san with swapping IP in PI #2.
- Crane IP to second floor.
- Rebuild PI #2 F0.
Software Etc
SR Prep Tasks - To Be Scheduled
Tunnel
- Retrieve BNC-Lemo cable from Nakano-kun.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable SR3 PI yaw stepper.
- Correct flipped connections in SR2 PI LVDTs.
- Correct flipped connections in SRM PI LVDTs.
- Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
- Get independent power supply for SR3 so SR2 can be powered back up.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Calibrate last six IM OSEMs.
- Rebuild filter in PI #1.
- Install clamps on PI #1.
- Install geophone plates on PI #3.
- Install geophone plates on PI #1.
- Install correct IP in PI #2.
- Rebuild filter in PI #2.
- Install clamps on PI #2.
- Install LBB blade units on PI #2.
- Install geophone plates on PI #2.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .