Line 22: Line 22:
=== 2018-07-17 ===
==== Main Sequence ====
 * --(Find LBB damper rods and associated parts.)--
 * --(Check/restore verticality of security structure.)--
 * --(Set SF damper magnet ring height.)--
 * --(Check/correct IP LVDT polarities.)--
 * --(Calibrate IP FR sensing.)--
 * Calibrate F0 LVDT actuation and FR.
 * Set safety screw and safety nut on F0 keystone; remove Kapton tape.
 * Set up optical lever.
 * Check/restore alignment of payload, especially optic pitch.
 * Do token TFs (time permitting).
 * Reset all PI FRs to midrange.
 * Lock F0 keystone.
 * Lock suspension laterally except for SF level.
 * Add IM-RM safety bar?
 * Disconnect all cables at inside of feedthroughs.
 * Remove top of tank (including service ring).
 * Set tank jacks to nominal height (50 mm).
 * Lift suspension.
 * Install LBB damper rods.
 * Crane suspension into tank.
 * Hook LBB damper rods.
 * Replace tank lid and service ring.
 * Remove tank lid leaving service ring.
 * Move feedthroughs.
 * Move cables over.
 * Remove safety bar and unlock suspension.
 * Remove First Contact?
 * Restore payload alignment, especially pitch.
 * Cable geophones.
 * Calibrate IP LVDT and FR actuation.
 * TFs!
=== 2018-09-25 ===
==== Etc ====
Line 56: Line 25:
==== F0/LBB/Tank Stuff ====
 * Add LBB ballast masses.
 * Help Sato-san with swapping IP in PI #2.
 * Crane IP to second floor.
 * Rebuild PI #2 F0.
==== SR2 ====
 * Open tank and move feedthroughs.
 * Reconnect in-vacuum cables.
 * Move in-air cables, with priority on IM OSEMs, then IM picos and BF/SF GAS and FRs.
 * Remove IM-RM safety bar.
 * Unlock and realign SF/... section.
 * Add arc weights and geophones.
 * Unlock and center IP.
Line 62: Line 34:
==== Software Etc ==== ==== SRM ====
 * Add TM OSEM cables.
 * Set TM pitch and tighten clamps.
 * Set RM pitch and tighten clamps.
 * Remove winch system and restore items removed from top of IM.
 * Suspend and weigh IM/... section.
 * Add BF crossbars to SS.
 * Build up SS to BF level.
 * Suspend IM/... section and adjust ballast/trim masses.
 * Install feedthroughs on AF (3 available; need to get a 4th).
 * Arrange power to SRM rack and get it running.
 * Check the IRIG-B 9999xx fix has been applied (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php?r=6031||6031]]).

==== SR3 ====
 * ''Don't even '''think''' about doing anything with SR3.''
 
Line 68: Line 55:
 * Add SR3 LBB ballast mass.
 * Install SR3 LEN OL.
 * Rebuild PI #2 F0 for SRM.
Line 71: Line 61:
 * Correct flipped connections in SR2 PI LVDTs.
Line 74: Line 63:
 * Get independent power supply for SR3 so SR2 can be powered back up.
Line 76: Line 64:
 * Calibrate last six IM OSEMs.
 * Rebuild filter in PI #1.
 * Install clamps on PI #1.
 * Install geophone plates on PI #3.
 * Install geophone plates on PI #1.
 * Install correct IP in PI #2.
 * Rebuild filter in PI #2.
 * Install clamps on PI #2.
 * Install LBB blade units on PI #2.
 * Install geophone plates on PI #2.
 * Rebuild filter in PI #2 for SRM.
 * Clean/Replace yoke in PI #2 for SRM.
 * Install clamps on PI #2 for SRM.
 * Install LBB blade units on PI #2 for SRM.
 * Install geophone plates on PI #2 for SRM.

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders, assembly frame.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-09-25

Etc

SR2

  • Open tank and move feedthroughs.
  • Reconnect in-vacuum cables.
  • Move in-air cables, with priority on IM OSEMs, then IM picos and BF/SF GAS and FRs.
  • Remove IM-RM safety bar.
  • Unlock and realign SF/... section.
  • Add arc weights and geophones.
  • Unlock and center IP.

SRM

  • Add TM OSEM cables.
  • Set TM pitch and tighten clamps.
  • Set RM pitch and tighten clamps.
  • Remove winch system and restore items removed from top of IM.
  • Suspend and weigh IM/... section.
  • Add BF crossbars to SS.
  • Build up SS to BF level.
  • Suspend IM/... section and adjust ballast/trim masses.
  • Install feedthroughs on AF (3 available; need to get a 4th).
  • Arrange power to SRM rack and get it running.
  • Check the IRIG-B 9999xx fix has been applied (klog http://klog.icrr.u-tokyo.ac.jp/osl/index.php?r=6031).

SR3

  • Don't even think about doing anything with SR3.

SR Prep Tasks - To Be Scheduled

Tunnel

  • Add SR3 LBB ballast mass.
  • Install SR3 LEN OL.
  • Rebuild PI #2 F0 for SRM.
  • Retrieve BNC-Lemo cable from Nakano-kun.
  • Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
  • Install, cable SR3 PI yaw stepper.
  • Correct flipped connections in SRM PI LVDTs.
  • Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
  • Check SR2, SR3 TM coil gains for magnet polarity compensation.
  • Rebuild filter in PI #2 for SRM.
  • Clean/Replace yoke in PI #2 for SRM.
  • Install clamps on PI #2 for SRM.
  • Install LBB blade units on PI #2 for SRM.
  • Install geophone plates on PI #2 for SRM.
  • Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

Mitaka or remotely

  • Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
  • Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review DAC channel requests.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Split SRx real-time models?

Ordering

See ../WishList .

KAGRA/Subgroups/VIS/TypeB/ToDoSR (last edited 2019-01-04 15:25:56 by MarkBarton)