=== 2018-07-17 === ==== Main Sequence ==== * --(Find LBB damper rods and associated parts.)-- * --(Check/restore verticality of security structure.)-- * --(Set SF damper magnet ring height.)-- * --(Check/correct IP LVDT polarities.)-- * --(Calibrate IP FR sensing.)-- * Calibrate F0 LVDT actuation and FR. * Set safety screw and safety nut on F0 keystone; remove Kapton tape. * Set up optical lever. * Check/restore alignment of payload, especially optic pitch. * Do token TFs (time permitting). * Reset all PI FRs to midrange. * Lock F0 keystone. * Lock suspension laterally except for SF level. * Add IM-RM safety bar? * Disconnect all cables at inside of feedthroughs. * Remove top of tank (including service ring). * Set tank jacks to nominal height (50 mm). * Lift suspension. * Install LBB damper rods. * Crane suspension into tank. * Hook LBB damper rods. * Replace tank lid and service ring. * Remove tank lid leaving service ring. * Move feedthroughs. * Move cables over. * Remove safety bar and unlock suspension. * Remove First Contact? * Restore payload alignment, especially pitch. * Cable geophones. * Calibrate IP LVDT and FR actuation. * TFs! |
=== 2018-11-05 === ==== SRM (top priority) ==== * LBB * Move KOACH filters * Put LBB damper rings in tank. * Set tank jacks to nominal height. * Main sequence * Prepare SF magnet ring. * Install #353 poles * Move NB-03 jacks down. * Crane PI into AF. * Install F0-SF rod (#331) and flying saucer. * Route SF/... cables up to underside of F0. * Do vertical height budget. * Adjust SF trim mass for balance and keystone height. ==== SR2 (low priority) ==== * Set up OL. |
Line 56: | Line 41: |
==== F0/LBB/Tank Stuff ==== * Add LBB ballast masses. * Help Sato-san with swapping IP in PI #2. * Crane IP to second floor. * Rebuild PI #2 F0. ==== Software Etc ==== |
=== 2018-11-12 === ==== SRM ==== * Main sequence * Cable/test IP LVDTs. * Cable/test IP FRs. * Unlock IP and center roughly. * Calibrate IP LVDTs. * Check/adjust alignment of SS. * Add arc weights and geophones (or extra mass equivalent to geophones). * Cable/test geophones. * Improve centering/tuning of IP and SS alignment. |
Line 68: | Line 57: |
* Retrieve BNC-Lemo cable from Nakano-kun. | * Check which LVDT cards are in which boxes. |
Line 70: | Line 59: |
* Install, cable SR3 PI yaw stepper. * Correct flipped connections in SR2 PI LVDTs. |
* Install, cable PI yaw steppers. |
Line 73: | Line 61: |
* Grab and configure a picomotor driver as SR2_BF 10.68.150.25. * Get independent power supply for SR3 so SR2 can be powered back up. |
|
Line 76: | Line 62: |
* Calibrate last six IM OSEMs. * Rebuild filter in PI #1. * Install clamps on PI #1. * Install geophone plates on PI #3. * Install geophone plates on PI #1. * Install correct IP in PI #2. * Rebuild filter in PI #2. * Install clamps on PI #2. * Install LBB blade units on PI #2. * Install geophone plates on PI #2. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-11-05
SRM (top priority)
- LBB
- Move KOACH filters
- Put LBB damper rings in tank.
- Set tank jacks to nominal height.
- Main sequence
- Prepare SF magnet ring.
- Install #353 poles
- Move NB-03 jacks down.
- Crane PI into AF.
- Install F0-SF rod (#331) and flying saucer.
- Route SF/... cables up to underside of F0.
- Do vertical height budget.
- Adjust SF trim mass for balance and keystone height.
SR2 (low priority)
- Set up OL.
2018-11-12
SRM
- Main sequence
- Cable/test IP LVDTs.
- Cable/test IP FRs.
- Unlock IP and center roughly.
- Calibrate IP LVDTs.
- Check/adjust alignment of SS.
- Add arc weights and geophones (or extra mass equivalent to geophones).
- Cable/test geophones.
- Improve centering/tuning of IP and SS alignment.
SR Prep Tasks - To Be Scheduled
Tunnel
- Check which LVDT cards are in which boxes.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable PI yaw steppers.
- Correct flipped connections in SRM PI LVDTs.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .