3291
Comment:
|
1713
|
Deletions are marked like this. | Additions are marked like this. |
Line 21: | Line 21: |
== 2017-11-20 == * Do mass budget for SR2/SR3/SRM (Fabian) - mostly done. * Design final SF ballast masses (Fabian). |
==== Plan for week of 3/5 ==== * --(Grab rack for SRM.)-- * --(See important pump down-related stuff at [[../ToDoBS]].)-- * --(Calibrate SF LVDT.)-- * --(Cable/test SF FR.)-- * --(Add SF cap.)-- * Lift SF/... with LGA and check weight/balance. * Start BF rebuild. |
Line 25: | Line 30: |
== 2017-11-27 == * Move SR2 rack into position. * Run cables to assembly frame. * Find and attach feedthroughs. * Install new jack receptacles on load gauge adapter. * Find mirror gluing items. * Prism micrometer stages * Prism jigs * Lenses for inspecting scribe lines * Procedure document. * Do mirror gluing. == 2017-12-04 == * Assemble SR2 IP. * Set up for testing IP with BS pico driver. * Make pico cable. * Assemble IP. * Test IP picos. * Adjust verticality of assembly frame; center and immobilize optical table. |
==== Plan for week of 3/12 ==== * Get SRM mushroom installed. * Set up SR3 and SRM racks. * Lay SR3 in-air cabling. |
Line 48: | Line 38: |
* Bring SR2 into tunnel. | * Review Shoda-san's Guardian. * Decide if we're really going to renumber IP channels. * Review DIO stuff. * Review SR2 model (especially screens, macro text file). * Review DAC channel requests. * Find out (from Takahashi-san) specifications for geophone pod items: * Screws for pod (cap-neck and neck-body). * Screws for geophone to interface plate. * Screws for interface plate to PI. * Find or order geophone items. * Get geophone circuit boards from Okutomi-san. * Find fourth feedthrough * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done. * Design final SF ballast masses (Fabian). |
Line 51: | Line 54: |
* Add L-brackets to new whitening filter and two HPCDs (one in BS rack). === Design/Purchasing === ==== Order now ==== * Bread boards for SR -> Orderd. delivery date:10/18-20 * Include installation work in the contract * Total budget = 5MJPY * PEEK collet for "Small hexagon"(cable clamp) -> need modification. ==== Need simple design changes ==== * SUS wires(3 types) for the LBB * Change the length -> Orderd. delivery date:10/ * Receptacles for Bread board damper * There is a mistake in the PROMEC drawing. * Hirata-san will make a new 2D drawing * IM wire clamps for SR * Need to change the height -> watiting second quote. * SR assembly frame -> Ordered. delivery date:9/27-29 * Mark is checking the design from Fabian * We should order the parts necessary to modify the BS assembly frame to the SR2 assembly frame ==== Need Fabian's input ==== * Cable clamps for BF,SF and PI -> 方式を決める * Design change for the PI clamps, because the SR PIs are NIKHEF ones. * Ballast masses for BF and SF * 製作に2週間程度 * 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。 * 測定に必要な物品の準備 -> 月曜日に高橋さんと相談 ==== Need more discussion/checks ==== * Blade spring assembly for LBB * Check the load of the LBB and decide the design load of the springs * Correct the length * Scale the width of the current blades to design the new blades -> 高橋さんと相談 * SR用LBBの重さを確認 * Bread board damper rings * Need to check whether we can put a full ring into the chamber from the side flanges or not. -> need modification === Electronics === * Get cables/cards for SR3: * 5 DSub-37 cables (tent) * 5 DSub-15M to DSub-9M adapter cables (tent) * 3 DIO cards (tent) * 2 DSub-9 FF gender benders (for LVDTs) * extra ADC card(s)? * extra DAC card(s)? * BNC-LEMO adapter (for LVDTs) * etc |
* Glue SR3. * Set up SR3 rack. * Set up SRM rack. * Rebuild two BFs. * Disassemble two top filters. * Rebuild three top filters. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
Plan for week of 3/5
Grab rack for SRM.
See important pump down-related stuff at ../ToDoBS.
Calibrate SF LVDT.
Cable/test SF FR.
Add SF cap.
- Lift SF/... with LGA and check weight/balance.
- Start BF rebuild.
Plan for week of 3/12
- Get SRM mushroom installed.
- Set up SR3 and SRM racks.
- Lay SR3 in-air cabling.
SR Prep Tasks - To Be Scheduled
- Review Shoda-san's Guardian.
- Decide if we're really going to renumber IP channels.
- Review DIO stuff.
- Review SR2 model (especially screens, macro text file).
- Review DAC channel requests.
- Find out (from Takahashi-san) specifications for geophone pod items:
- Screws for pod (cap-neck and neck-body).
- Screws for geophone to interface plate.
- Screws for interface plate to PI.
- Find or order geophone items.
- Get geophone circuit boards from Okutomi-san.
- Find fourth feedthrough
- Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
- Design final SF ballast masses (Fabian).
- Get safety bars moved.
- Get air hose connection moved.
- Glue SR3.
- Set up SR3 rack.
- Set up SRM rack.
- Rebuild two BFs.
- Disassemble two top filters.
- Rebuild three top filters.