Differences between revisions 97 and 117 (spanning 20 versions)
Revision 97 as of 2018-09-01 14:52:09
Size: 3413
Editor: MarkBarton
Comment:
Revision 117 as of 2018-10-27 14:18:02
Size: 2854
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 22: Line 22:
=== 2018-09-03 ===
==== Etc ====
 * Check SR2-SR3 duct (since Mirapro moved it) to see if we have adequate space at both ends.
 * Help crane inspectors on Monday and Wednesday mornings.
 * Shut down all electronics before leaving on Friday.
 * Update electronics items lists to reflect removed ADC stuff.
 * Inspect all crane slot curtains (SR, BS, PR), note which are missing, and decide which should be closed up immediately versus later. (For example, SR2 and SR3 have missing curtains that could be replaced semi-permanently because we probably don't need to crane stuff into those areas anymore.)
=== 2018-10-29 ===
==== SRM (top priority) ====
 * PI
  * Finalize tuning.
  * Add more cable clamps.
  * Prepare SF magnet ring.
 * Main sequence
  * Cable/test SF LVDT and FR.
  * Decide and install SF internal ballast mass (probably 1 Promec).
  * Reinstall SF cap.
  * Weigh SF/... section.
  * Install #353 poles
  * Move NB-03 jacks down.
  * Crane PI into AF.
  * Install F0-SF rod (#331) and flying saucer.
  * Route SF/... cables up to underside of F0.
  * Do vertical height budget.
  * Adjust SF trim mass for balance and keystone height.
  
==== SR2 ====
 * Set up OL (Terrence).
 * More TFs
 * Add more arc weights?
 * Do control filter design and installation.
 * Do measurement of yaw torque required for F0 yaw adjustment?
Line 30: Line 48:
==== SR2 (highest priority) ====
 * Cable/test PI items (LVDTs, steppers, geophones).
 * Finish in-air cabling.
 * Do basic go/no-go test of electronic items.
 * Adjust ballast/trim mass of SF, with reserve for yaw stepper.
 * Check alignment of chain and security structure.
 * Center all IP FRs.
 * Add arc weights and geophones and center IP.
 * Set damper height.
 * Crane suspension into tank
 
==== SRM (as time permits) ====
 * Set up pitch-setting OL.
 * Add TM OSEM cables.
 * Set TM pitch and tighten clamps.
 * Set RM pitch and tighten clamps.
 * Remove winch system and restore items removed from top of IM.
 * Install feedthroughs on AF.
 * Fire up SRM rack.
=== 2018-11-05 ===
==== SRM ====
 * Main sequence
  * Cable/test IP LVDTs.
  * Cable/test IP FRs.
  * Unlock IP and center roughly.
  * Calibrate IP LVDTs.
  * Check/adjust alignment of SS.
  * Add arc weights and geophones (or extra mass equivalent to geophones).
  * Cable/test geophones.
  * Improve centering/tuning of IP and SS alignment.
 * LBB
  * Move KOACH filters
  * Put LBB damper rings in tank.
  * Set tank jacks to nominal height.
Line 50: Line 64:
==== SR3 ====
 * ''Don't even '''think''' about doing anything with SR3.''
 
=== 2018-11-12 ===
==== SRM ====
 *
Line 58: Line 72:
 * Add SR3 LBB ballast mass.
 * Install SR3 LEN OL.
 * Rebuild PI #2 F0 for SRM.
 * Retrieve BNC-Lemo cable from Nakano-kun.
Line 63: Line 73:
 * Install, cable SR3 PI yaw stepper.  * Install, cable PI yaw steppers.
Line 65: Line 75:
 * Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
Line 67: Line 76:
 * Calibrate last six IM OSEMs.
 * Install geophone plates on PI #1 for SR2.
 * Rebuild filter in PI #2 for SRM.
 * Install clamps on PI #2 for SRM.
 * Install LBB blade units on PI #2 for SRM.
 * Install geophone plates on PI #2 for SRM.

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders, assembly frame.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-10-29

SRM (top priority)

  • PI
    • Finalize tuning.
    • Add more cable clamps.
    • Prepare SF magnet ring.
  • Main sequence
    • Cable/test SF LVDT and FR.
    • Decide and install SF internal ballast mass (probably 1 Promec).
    • Reinstall SF cap.
    • Weigh SF/... section.
    • Install #353 poles
    • Move NB-03 jacks down.
    • Crane PI into AF.
    • Install F0-SF rod (#331) and flying saucer.
    • Route SF/... cables up to underside of F0.
    • Do vertical height budget.
    • Adjust SF trim mass for balance and keystone height.

SR2

  • Set up OL (Terrence).
  • More TFs
  • Add more arc weights?
  • Do control filter design and installation.
  • Do measurement of yaw torque required for F0 yaw adjustment?

2018-11-05

SRM

  • Main sequence
    • Cable/test IP LVDTs.
    • Cable/test IP FRs.
    • Unlock IP and center roughly.
    • Calibrate IP LVDTs.
    • Check/adjust alignment of SS.
    • Add arc weights and geophones (or extra mass equivalent to geophones).
    • Cable/test geophones.
    • Improve centering/tuning of IP and SS alignment.
  • LBB
    • Move KOACH filters
    • Put LBB damper rings in tank.
    • Set tank jacks to nominal height.

2018-11-12

SRM

SR Prep Tasks - To Be Scheduled

Tunnel

  • Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
  • Install, cable PI yaw steppers.
  • Correct flipped connections in SRM PI LVDTs.
  • Check SR2, SR3 TM coil gains for magnet polarity compensation.
  • Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

Mitaka or remotely

  • Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
  • Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review DAC channel requests.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Split SRx real-time models?

Ordering

See ../WishList .

KAGRA/Subgroups/VIS/TypeB/ToDoSR (last edited 2019-01-04 15:25:56 by MarkBarton)