VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2018-01-15
- Cable RM OSEMs to rack.
- Setup QPD and do temporary cables to rack.
- Do TFs from RM OSEMS to OL pitch/roll.
- Make IM OSEMs.
- Install load gauge adapter.
- Lift IM/RM/SR, check/adjust total mass and pitch/yaw balance.
- Test IM picos.
- Crane in BF.
- Hook IM.
- Route cables via flying saucer up to under BF.
- Recheck total mass and pitch/roll balance.
- Check BF yaw pico.
- Install IRM.
- Adjust OSEMs.
- Cable IM OSEMs.
- Install pre-calculated BF trim mass.
- Lift
- Find in-vac cables:
- 1 x Type 3-2m
- 5 x Type 1-2m
- Set up SR2 rack
- Get more 1-m power cables and connect up remaining boxes.
- Run LAN and power cables for stepper drivers.
- Review Shoda-san's Guardian.
- Decide if we're really going to renumber IP channels.
- Review DIO stuff.
- Review SR2 model (especially screens, macro text file).
- Review DAC channel requests.
SR Prep Tasks - To Be Scheduled
- Find out (from Takahashi-san) specifications for geophone pod items:
- Screws for pod (cap-neck and neck-body).
Cu O-rings for pod (two sizes).
- Viton O-ring for under geophone.
- Screws for immobilizing geophone (M4?).
- Screws for geophone to interface plate.
- Screws for interface plate to PI.
- Find or order geophone items.
- Get geophone circuit boards from Okutomi-san.
- Find fourth feedthrough
- Hassle Miyo-kun for stepper drivers.
- Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
- Design final SF ballast masses (Fabian).
- Get safety bars moved.
- Get air hose connection moved.