VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2018-02-13
- Put down sticky mat in genkan.
Test FR stepper.
Set up watchdog.
Calibrate FR actuation.
- Calibrate LVDT actuation.
- Add IRM side panels.
- Add IM OSEMs and flags.
- Adjust IRM and lateral position of OSEMs.
- Cable IM OSEMs.
- Set gains and offsets in IM OSEMINF screens.
- Center IM OSEMs in/out.
- Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
Plan for week of 2/19
- Add BF cap.
- Lift BF/... section with LGA.
- Check/adjust total mass and balance.
- Cable and test BF picos.
- Anchor cables to BF cap.
- Add AF crossbars for under SF.
- Build up SS to SF ring.
- Bring in SF.
- Remove SF cap.
- Hook BF/... section.
- Route cables up to under SF.
- Check/adjust total mass of BF/... section.
- Cable SF LVDT.
- Calibrate SF LVDT.
- Cable SF FR.
- Test/calibrate SF FR.
- Add SF cap.
- Add Cu segments to SF cap.
- Lift SF/... with LGA and check weight/balance.
SR Prep Tasks - To Be Scheduled
- Review Shoda-san's Guardian.
- Decide if we're really going to renumber IP channels.
- Review DIO stuff.
- Review SR2 model (especially screens, macro text file).
- Review DAC channel requests.
- Find out (from Takahashi-san) specifications for geophone pod items:
- Screws for pod (cap-neck and neck-body).
- Screws for geophone to interface plate.
- Screws for interface plate to PI.
- Find or order geophone items.
- Get geophone circuit boards from Okutomi-san.
- Find fourth feedthrough
- Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
- Design final SF ballast masses (Fabian).
- Get safety bars moved.
- Get air hose connection moved.
- Glue SR3.
- Set up SR3 rack.
- Set up SRM rack.
- Rebuild two BFs.
- Disassemble two top filters.
- Rebuild three top filters.