VIS Meeting on 2015/11/5

2015/11/5 After the NAOJ GWPO Meeting (14:00 - 17:00)

Kamioka NAOJ Room + SeeVogh

Participants: Shoda, Takahashi, Fujii, Ohishi, Michimura, Raffaele, Okutomi, Mark, Tatsumi, Akutsu, Manuel, Hirata, Fabian, Ishizaki, Aso

Schedule

  • Schedule Plan (Aso)
    • Latest schedule chart

    • Control test: are the transfer function measurements necessary ?
      • Remote measurement is a possibility.
      • Change "control test" -> "signal checking" (not including TF measurement)

      • We need to come up with a way to make the working hour longer (two teams taking shifts ?)

PR

  • Test Hanging Status (Shoda)
    • Galled screws (Takahashi)
      • Galled screw was cut.
      • Another screws almost galled, but we were able to remove them.
      • By using turn backles, we lifted the security interface plate horizontall and were able to put the screw without galling.
  • Production of new EQ stop screws (Takahashi)
    • Need to make new EQ stop rods because of the screw galling.
    • We had 6 sets. Now we lost 1set. We need 4 sets for iKAGRA. No need to hurry up in producing them.
  • Digital system (Shoda, Okutomi, Fujii)
    • A simple model with only one filter is available
    • Sattelite box and coil drivers are ready
    • Need to check the OSEM (Tue)
    • Where to put the satellite box ? Grounding ? -> Mark

    • Digital system preparation (confirm that the model works) -> Okutomi

  • Cleaning of the chamber (Okutomi)
    • Will consider to out source. Aso will talk with Saito-san.

  • Cable status (Takahashi)
    • 1st set will be delivered in the next Monday.
    • 2nd set at the end of the next week
    • Remaining ones in the following weeks.
    • Call for shift for cable checking ? Need to establish the checking procedure first. Then call for shift (Takahashi)

  • Additional PR mirror box (Tatsumi)
    • Order was placed.
    • Delivery before 1st Dec.
  • Production of additional PR winches (Akutsu)
    • Ordered all the parts. Delivery before 1st Dec.
    • Assembly work needs to be scheduled

  • PR Optical Bench (Akutsu)
    • Ordered the required screws. Delivery in 10 days.
    • Height adjustment will be done at the time as the preparation work for PR3 installation.
  • RM compensation mass: do we have enough of them ? (Fabian)
    • Having some problem with screw model in CAD (density was wrong). Hirata-san is fixing it.
    • We should order compensation masses with various thickness (Takahashi)

    • Lock nuts may have to be changed to cope with the changed length of the EQ stop screws. -> probably this is not so important.

  • RM EQ stop screw position (Akutsu, Shoda)
    • A stop screw will penetrate an opening in the RM.
    • Hirata-san will check if we can move the screw holes up or down to solve the problem.

  • Next week (from 11/9) plan (Aso)
    • Mechanical Assembly (Takahashi, Shoda, Mark, Fabian, Fujii)
      • Mon: Put BF
      • Tue: OSEM signal check
      • Wed: Hang IM
      • Thu - Fri: Assemble IMRM
    • Digital system preparation (Okutomi): Try to run the simple model on the computer near the PR3
    • Cleaning: discuss with Hirose-san, Nakano-kun to establish the procedure
    • Travel plan
      • Takahashi: Mon-Thu
      • Shoda: full week
      • Fujii: Wed - Fri.
      • Okutomi: full week
      • Fabian: Wed - Fri.
      • Mark: Mon-Tue
      • Ohishi: Mitaka on Wed. Thu.
      • Aso: Mitaka on Mon.

BS

  • BS Assembly Frame Design (Aso, Hirata)
    • We need to discuss the IM alignment mechanism for hanging frame part -> Change the scews to ball point ones: Takahashi-san already bought them.

    • Since the frame is very tall, we need a step or intermediate height floor safe work. Mark will give us prefered height

      -> Mark will send us the drawing with possible step heights.

  • BS magnet size (Michimura)
    • Recomendation from the special meeting: reduce the size of the magnet by a factor of 30.
    • Paired magnets for reducing the magnetic field noise
    • IM magnet size: needs to be checked -> Shimoda, Michimura

  • BS gluing jigs (Tatsumi)
    • We haven't placed order yet. But the company has started some manufacturing.
    • Can we wait 10 days for order until we have the thermal noise result ?
  • Not enough crane height problem (Hirata, Saito)
    • There seems to be some solution.
    • Asked Saito-san to give us the plan.
  • IP Base Clamp (Fabian)
    • Fabian will send a new version soon (by the end of the week)

  • BS clean bag (Aso)
    • Will design it soon as the size of the assembly frame is almost fixed

Other

  • Screw inventory (Ishizaki)
    • Ishizaki-san came to Kamioka to make an inventory of the screws we have.
    • Print out the inventory. Check when you use screws.
  • PR suspension model checking (Hirata, Akutsu)
    • EQ stop part is finished
    • Started working on the payload part
  • Watch dog system (Tanaka)
    • Got a new document from Tanaka-san
  • Clean suits (Aso)
    • Asked Miyoki-san to order many
  • ETM installation procedure (Takahashi)
    • Will have a discussion next week

  • Magnetism of the OSEM screw (Akutsu)
    • Sekiguchi-kun pointed out a possible problem with magnetism of the screws around OSEM. -> Check with Sekiguchi-kun

  • GAS blade inspection by Virgo (Takahashi)
    • Waiting for more information (mostly shipping info) from Ando-san
  • Safety at the site (Takahashi, Ishizaki)
    • Hirose-san will prepare a clean cloth to be put under the 2F floor to catch fallen items.

Next meeting

2015/11/13(Fri) 13:30