VIS Meeting on 2015/11/20

2015/10/30 13:00 - 16:00

Kamioka NAOJ Room + SeeVogh

Participants: Mark, Fabian, Takahashi, Aso, Akutsu, Hirata, Ohishi, Ishizaki, Fujii, Shoda, Okutomi, Raffaele

Schedule

PR

  • Installation team organization change (Aso)
    • A new team plan
      • Team A: Takahashi, Shoda, Okutomi, Fujii
      • Team B: Mark, Fabian, Ohishi, Shift worker ?
    • Team B will start the preparation of the PR2 immediately
  • Test Hanging Status (Takahashi)
    • BF load adjustment was done: optimal load = 53kg
    • EQ stop rods below the BF were wrong : EQ stop position was higher than the design -> lowered them by inserting spacers.

    • Assembling IMRM: IMRM without OSEM was assembled.
    • BF is already level
    • Cabling: TM OSEMs and Picomotor are done. IM OSEMs, LVDT, picomotors and fishing rod needs to be done.
    • A cable clamp to be attached to the suspension rod has a wrong size collet. Fabian will bring the proper collets from Mitaka.

  • Payload weight issue
    • We need to test the theory of mistaking BF#1 and #2.
    • BF load check needs to be done at the ATC
      • Send the BF#1 to Mitaka by 11/27 (Takahashi)

      • Hirata and Saito (ATC) will measure the optimal load by 12/11. Takahashi will coordinate with ATC people.

      • We need BF#1 to be back to Kamioka by 12/21
  • Digital system (Okutomi, Fujii)
    • OSEM signal can be seen in the digital system
    • Roughly checked the actuation of the mirror by OSEM by changing the offset voltage
    • Damping loop of the TM is now working.
    • Having a problem with excitation signal injection: waiting for Miyakawa-san to fix it.
    • Working on the MEDM screen improvement
    • Also modifying the realtime model of PR3
  • Traverser actuation check
    • Vacuum compatible motors cannot be tested in air.
    • We have a vacuum non-compatible motor, so we can check the motor rotation.
    • Traverser cable has to be made (as a part of the cabling work)

  • Clean work procedure (Aso)
    • Particle count record: Shoda collected data, but don't know how to extract data. Takahashi will help it.

  • PR2 preparation (Mark, Fabian)
    • Made an inventory of the area.
    • Identified missing items (needs to be bought).
    • Clean area will be ready on Nov. 25
  • PR CAD model and assembly drawings (Hirata)
    • Done this week: Small hexagon + BF modification. Wire clamp
    • Remaining: assembly drawing with the inner frame -> need the yaw rotation angle information (Aso)

  • Cable status (Takahashi)
    • Made a cable list -> Will upload it to Wiki with more information

  • Call for shift for cable checking
    • One student available on the week of 11/30
    • Ask the student if he can come on the week of 12/7 (Takahashi)

    • If the student is only available in the week of 11/30, Akutsu-kun can come to Kamioka on this week.
  • Additional PR mirror box (Tatsumi):
    • Waiting for delivery
  • Production of additional PR winches (Akutsu)
    • Ikenoue-san will try to deliver it by Dec 21.
  • RM compensation mass
    • Design status (Fabian): working on it now, but not yet finished. Will finish sometime this weekend.

    • Order status (Takahashi): Haven't yet gotten a quotation. Will order early next week.

  • RM EQ stop screw position (Hirata)
    • ATC work (Hirata): Washed and arrived at Kamioka.
    • Out sourcing (Takahashi): Will ask for quotation with the RM compensation mass. All the plates are already sent to Mitaka.

  • PR Optical Bench (Akutsu)
    • Got half screws instead of fully threaded ones.
    • Stud bolts are available from BUMAX
    • SDC provided a quotation for the fully threaded screws too. Will compare these options.
  • OSEM assembly status (Akutsu)
    • Newly designed flexible circuits will be delivered at the end of the next week
  • Next week (from 11/24) plan
    • Test hanging
      • Tue: Adjust the IM level.
      • Wed: Level IMRM and put OSEMs, adjust the alignment of the flags. OSEM cablings
      • Thu: OSEM alignment
      • Fri: Signal check
      • Sat: If not finished
    • PR2 preparation work
      • Next week: Fabian and Ohishi-san will do inventory checking, move things into the clean area.
      • Next next week: Alignment of the frames.
  • Week of ELITES meeting (11/30-12/4)
    • Mon-Thu: Alignment of the assembly and hanging frame for PR2
    • Remote transfer function measurements (test hanging)
  • Travel (Week of 11/24)
    • Takahashi: Full week
    • Shoda: Full week
    • Mark: not coming
    • Fabian: (Full week)
    • Okutomi: Full week
    • Fujii: Full week
  • Travel (Week of 11/30)
    • Takahashi: not coming
    • Shoda: not coming
    • Mark: Mon-Thu
    • Fabian: not coming
    • Ishizaki: Mon-Thu
    • Okutomi: not coming
    • Fujii: not coming

BS

  • CLIO BS
    • In order to operate iKAGRA before the end of March 2016, SEO is considering the possibility of using CLIO BS instead of Type-B BS for iKAGRA.
    • This idea will be discussed at the chief meeting 11/24
    • BS related tasks have lower priority for the moment.
  • BS Assembly Frame Design (Aso, Hirata)
  • BS flag design (Mark, Fabian)
  • BS gluing jigs (Tatsumi)
  • Not enough crane height problem (Hirata, Saito)
  • IP base clamp (Fabian)
  • Bread board spring (Takahashi)
  • BS clean bag (Aso)

ETM

  • ETM installation procedure (Aso)
    • Aso explained the basic concept of the ETM installation procedure
    • A request from Mark is to make the assembly frame thinner so that we have more work space around.
    • Aso will compile the design information and send it to Mirapro by 11/25

Other

  • Watch dog system (Tanaka)
    • no progress
  • GAS blade inspection by Virgo (Takahashi)
    • Waiting for shipping information: Takahashi-san will send Ando-san a reminder

  • Safety at the site (Takahashi, Ishizaki)
  • Request to the ATC for the next year
    • We need to tell ATC our requests for the next fiscal year.
    • Possible tasks are:
      • PRM and SRM recoil masses production: The deadline can be the end of the FY2016. Still need a rough schedule
      • Type-A bottom filter production:
        • Need to cut the blades. For this, we may want to check the optimal load of the SFs before deciding on the blade width of the BF.
        • Checking the optimal load of SF at ATC is one of the big request candidate. We should tell ATC about this possibility.
    • Takahashi-san will send a plan to Akutsu-kun

  • JPS meeting talks
    • VIS overview: Shoda
    • Mechanics: Fujii
    • Control: Okutomi
  • Astronomy society meeting
    • Fabian will give an overview talk

Next meeting

2015/11/27 (Fri) 13:30 -