VIS Meeting on 2015/11/27
2015/11/27 13:30 - 17:00
Kamioka NAOJ Room + SeeVogh
Participants:
Schedule
- Schedule status (Aso)
- Latest schedule chart
PR
- Test Hanging Status (Takahashi)
A cable clamp to be attached to the suspension rod has a wrong size collet. Fabian will bring the proper collets from Mitaka. -> Status
- Payload weight issue
- BF load check at the ATC: arrangement status
- Digital system (Okutomi, Fujii)
- Traverser actuation check (Shoda)
Traverser cable has to be made (as a part of the cabling work) -> status
- Clean work procedure (Aso)
Particle count record: Shoda collected data, but don't know how to extract data. Takahashi will help it. -> Status
- PR2 preparation (Mark, Fabian)
- PR CAD model and assembly drawings (Hirata)
- Cable status (Takahashi)
Made a cable list -> Will upload it to Wiki with more information -> status
- Call for shift for cable checking
Ask the student if he can come on the week of 12/7 (Takahashi) -> status
- Additional PR mirror box (Tatsumi):
- Production of additional PR winches (Akutsu)
- RM compensation mass
Design status (Fabian): working on it now, but not yet finished. Will finish sometime this weekend. -> status
Order status (Takahashi): Haven't yet gotten a quotation. Will order early next week. -> status
- RM EQ stop screw position (Hirata)
Out sourcing (Takahashi): Will ask for quotation with the RM compensation mass. All the plates are already sent to Mitaka. -> status
- PR Optical Bench (Akutsu)
- OSEM assembly status (Akutsu)
- PR2 gluing schedule (Tatsumi)
- Next week (from 11/24) plan
- Test hanging
- Mon:
- Tue:
- Wed:
- Thu:
- Fri:
- Sat:
- PR2 preparation work
- Mon:
- Tue:
- Wed:
- Thu:
- Fri:
- Sat:
- Test hanging
- Travel (Week of 11/30)
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Ohishi:
- Travel (Week of 12/7)
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Ohishi:
BS
- CLIO BS
- BS Assembly Frame Design (Aso, Hirata)
- BS flag design (Mark, Fabian)
- BS gluing jigs (Tatsumi)
- Not enough crane height problem (Hirata, Saito)
- IP base clamp (Fabian)
- Bread board spring (Takahashi)
- BS clean bag (Aso)
ETM
- ETM installation procedure (Aso)
Aso will compile the design information and send it to Mirapro by 11/25 -> status
Other
- Watch dog system (Tanaka)
- GAS blade inspection by Virgo (Takahashi)
Waiting for shipping information: Takahashi-san will send Ando-san a reminder -> status
- Request to the ATC for the next year
- We need to tell ATC our requests for the next fiscal year.
Takahashi-san will send a plan to Akutsu-kun -> status
- Safety at the site (Takahashi, Ishizaki)
Next meeting